Ireland refuses €1.5bn Mayo data centre

1 min read
23:07UTC

Ireland's planning appeals body refused a €1.5bn data centre at Killala, County Mayo, because the developer showed no fixed grid connection and no renewable power contract.

IndustryAssessed
Key takeaway

Ireland's planning appeals body refused a data centre that could not prove grid capacity or renewable supply.

An Coimisiun Pleanala, Ireland's national planning appeals body, refused a €1.5bn data centre at Killala, County Mayo, on 17 September, overturning Mayo County Council's 2025 grant⁠1. The applicant, Mayo Data Hub, is backed by Avaio Digital.

The board found the developer had shown no fixed grid connection agreement and no proof that the grid could serve the site, RTE News reported. It also found the project had not shown it would meet the objectives of Ireland's Climate Action Plan 2025, citing the absence of any corporate PPA (power purchase agreement) with a renewable supplier.

Ireland's energy regulator, the Commission for Regulation of Utilities, had been consulting on grid-code obligations that EirGrid would impose on large demand sites such as data centres. Killala moves those tests forward to the planning stage. An Irish applicant now faces a demand for grid and power-purchase evidence at the planning stage, before any connection offer.

Deep Analysis

In plain English

Ireland's national planning appeals board rejected a €1.5bn data centre planned for Killala in County Mayo, even though the local county council had already approved it last year. The board's reasons were about power, not politics: the developer had no confirmed grid connection agreement, and no signed contract to buy renewable electricity. This matters beyond Mayo because it shows Ireland's appeals process is now applying the same tough grid and renewable-energy tests used around Dublin to projects anywhere in the country, even regions once seen as an escape route from Dublin's stricter rules.

Deep Analysis
Root Causes

Ireland's grid has operated under an effective restriction on new large-load connections around Dublin since 2021, pushing developers toward the regions; Mayo Data Hub tried to build outside that constrained zone but still needed the grid operator to confirm the west of Ireland's thinner transmission network could serve a €1.5bn campus, and went to appeal without that confirmation in hand.

The refusal also rests on the absence of a corporate power-purchase agreement, a financing instrument rather than a planning requirement in most jurisdictions; treating a missing PPA as grounds for refusal signals Ireland now expects developers to prove renewable electricity is contracted, not merely available, before construction can begin.

First Reported In

Update #15 · Texas freezes data-centre permits

RTE News· 24 Sept 2026
Read original →
Causes and effects
This Event
Ireland refuses €1.5bn Mayo data centre
In An Coimisiun Pleanala's decision, missing grid-capacity evidence and a missing renewable PPA became grounds to refuse planning permission, ahead of any grid connection.
Different Perspectives
Mooresville Board of Commissioners
Mooresville Board of Commissioners
The town board north of Charlotte voted unanimously on 2 November to stop taking data-centre applications for 12 months. Commissioners cited environmental and electrical impacts, joining other North Carolina towns that have paused new projects.
Naver
Naver
Naver signed a US$9bn contract under which a Brookfield vehicle owns the GPUs and buildings and sells computing to Naver Cloud. It guarantees the fees for up to eight years, which also unlocked Nvidia's US$1bn equity investment.
Saudi Aramco
Saudi Aramco
Aramco closed its purchase of 49% of HUMAIN on 1 November, paying about US$2.6bn in cash and adding its own AI, compute and digital assets. Chief executive Amin Nasser cast the deal as a gain in technology standing.
NEXTDC board
NEXTDC board
The board called the Goodman and Digital Realty stake opportunistic and said it had received no takeover proposal. It enters the 20 November meeting with a new chairman search, a 10% fee cut and a spill resolution on the agenda.
Brasscom
Brasscom
Sergio Sgobbi of Brazil's technology industry association says investors face uncertainty until the Redata rules are public. Members need rulings on gas and the CDE levy after Lula said data centres must build their own power.
Johari Abdul Ghani, Malaysia's investment, trade and industry minister
Johari Abdul Ghani, Malaysia's investment, trade and industry minister
He told the Dewan Rakyat in October that data centres pay for all the grid capacity they reserve and fund upgrades to TNB's network. Google's 4 November pledge repeats those terms as its own.