Climate Action Plan 2025
AI-generated illustration
Legislation

Climate Action Plan 2025

Ireland's national climate strategy, setting emissions-reduction targets and sectoral measures.

On 17 September, An Coimisiún Pleanála cited Climate Action Plan 2025 when refusing a €1.5bn data-centre proposal at Killala, after the developer failed to show it would meet the plan's objectives.

Last refreshed: 24 September 2026

Timeline for Climate Action Plan 2025

#15 17 Sept
View full timeline →

Background

Climate Action Plan 2025 is Ireland's national climate strategy. It sets emissions-reduction targets and sectoral measures across the economy, giving government policy a common framework for climate action.

The plan matters to decisions whose energy demand and infrastructure needs may affect those targets. On 17 September, An Coimisiún Pleanála cited the plan's objectives in refusing a proposed data centre at Killala, County Mayo.

Its lasting significance lies in linking national emissions goals with sector-by-sector policy measures. The Killala decision shows that the plan's objectives can form part of the evidence considered when a major project's power demand is assessed.

Key Issues
Data centre planning

The plan shaped a refusal

On 17 September, An Coimisiún Pleanála cited Climate Action Plan 2025 when it refused the proposed Killala data centre in County Mayo. The developer had not demonstrated that the €1.5bn project would meet the plan's objectives.

The same 17 September ruling also noted that the developer lacked a fixed grid-connection agreement and a corporate renewable-Power Purchase Agreement. For Climate Action Plan 2025, the decision put its objectives directly into the planning assessment of a high-demand development.

Common Questions
What is Ireland's Climate Action Plan 2025?
It is the Irish government's current national climate strategy, setting sectoral emissions-reduction targets and policy measures.
Why did Ireland refuse the Killala data centre?
An Coimisiún Pleanála found the developer had not shown the project would meet Ireland's Climate Action Plan 2025, and cited the absence of a fixed grid connection agreement or a renewable Power Purchase Agreement.Source:
What evidence must Irish data centres now show at planning stage?
Following the Killala refusal, developers face scrutiny of grid-connection agreements and renewable Power Purchase Agreements at the planning stage, before any connection offer.Source: