Data Centres: Boom and Backlash
24SEP

xAI wins 41 gas turbines for Colossus

4 min read
13:52UTC

xAI received approval in March 2026 for 41 natural gas turbines totalling 1.2 GW to power its Colossus complex; Meta's El Paso project will run on a 366 MW behind-the-meter gas array.

IndustryDeveloping
Key takeaway

xAI, Meta and Wonder Valley are committing decades of fossil generation behind the meter to bypass the grid queue.

xAI received approval in March 2026 for 41 natural gas turbines totalling 1.2 GW to power its Colossus data centre complex outside Memphis.⁠1 Meta's El Paso project will run on a 366 MW behind-the-meter (BTM) natural gas array. Kevin O'Leary's Wonder Valley campus in Alberta, announced at $70 billion, has a 7.5 GW bring-your-own-power (BYOP) gas plan attached.

"behind-the-meter" describes generation built on the customer's side of the grid connection, dispatched to serve the customer's load directly without selling into the wholesale market. "Bring-your-own-power" is the operator-led variant: a campus is sited specifically to host its own generation rather than wait for transmission upgrades. Both routes solve the same problem: years-long waits for new transmission interconnection. Both also commit the operator to a fossil-fuel asset that runs for decades. A combined-cycle gas turbine ordered today comes online late in this decade and is depreciated over a twenty- to thirty-year operating life.

Colossus is xAI's Memphis training cluster, the site that hit roughly 100,000 H100 GPUs in late 2024 and was reported at 200,000 by mid-2025. Its previous power supply attracted complaints from the Southern Environmental Law Center over Clean Air Act permitting on its existing turbines. The March 2026 approval is the formal regulatory consent for the larger 1.2 GW build-out. Meta's El Paso project sits inside ERCOT, the Texas grid that has explicitly relaxed large-load interconnection rules to attract data centre demand the rest of the US grid will not connect.

The BYOP build-out runs alongside hyperscaler net-zero commitments published to investors and ESG indices. The cooling-water and renewables work covered in their sustainability reports does not retire the gas plant the same operator just queued behind the meter. Wonder Valley's 7.5 GW would meet the entire peak demand of a mid-sized European country, attached to a single private campus. Whether this gas capacity ever runs at the contracted load factor depends on how fast renewable interconnection clears, but the contracts are being signed now, and turbine lead times mean the bet is locked in.

Deep Analysis

In plain English

Most buildings get their electricity from the public grid, the network of power stations and cables that delivers electricity to homes and businesses. Large data centres need so much power that getting connected to the grid can take three to five years. behind-the-meter gas is a different approach: the operator builds its own gas-fired power stations on or next to the data centre site, generating electricity directly without ever connecting to the public grid. The gas comes from a pipeline; the turbines convert it to electricity on site. xAI, the AI company founded by Elon Musk, won approval for 41 of these turbines at its Colossus facility in Memphis, totalling 1.2 GW. Meta and Kevin O'Leary's planned Wonder Valley campus in Alberta are taking the same route. The advantage is speed: turbines can be delivered and installed in 18-24 months. The disadvantage is that they burn fossil fuel and emit carbon and local air pollutants.

Deep Analysis
Root Causes

Grid interconnection timelines in the US average three to five years for large industrial loads. AI data centres require power delivery on 12-18 month deployment cycles to remain competitive. The gap between what the grid can deliver and what operators require has made BTM gas economically rational even at the cost of higher per-MWh fuel prices, permitting complexity, and reputational risk.

The secondary cause is the GE Vernova backlog: gas turbines are deliverable within 18-24 months (subject to queue position), whereas new grid connections in congested areas are not. Equipment manufacturers have pulled forward delivery capacity that transmission planners cannot match.

What could happen next?
  • Consequence

    The IEA's 15-27 GW US onsite gas projection by 2030 is now on track to be achieved early: xAI alone accounts for 1.2 GW, Meta El Paso for 0.37 GW, and Wonder Valley (if built) for 7.5 GW.

    Medium term · Medium
  • Risk

    Memphis's minor modification permitting pathway for 41 turbines is now the subject of EPA regional scrutiny; if challenged successfully, it could invalidate the approval and strand capital already committed.

    Short term · Medium
  • Precedent

    Three major BTM gas commitments in a single quarter establishes BTM self-generation as the default model for AI campuses above 300 MW, which will shape utility planning and grid investment models for the next decade.

    Long term · High
First Reported In

Update #1 · Boom hits wall: grid says no, states freeze

Data Center Frontier· 26 Apr 2026
Read original →
Different Perspectives
Chilean data-centre developers
Chilean data-centre developers
Seven projects, one linked to Google, asked SEA this month for rulings that they fall outside full environmental review; four declared diesel-storage volumes just under the review-triggering tonnage, mirroring the mechanism Alto Jahuel used in July. The clustering suggests the threshold is being engineered, not sized to need.
An Coimisiun Pleanala
An Coimisiun Pleanala
Ireland's planning appeals body refused the €1.5bn Killala data centre on 17 September, overturning Mayo County Council's 2025 grant for lack of a fixed grid-connection agreement and no corporate renewable power-purchase agreement. The ruling makes matched-power evidence, not planning consent alone, the deciding factor.
Housing Assembly and Foxglove
Housing Assembly and Foxglove
The two groups' 6 August appeal, filed through the Legal Resources Centre, kept Cape Town's approval of Equinix's data centre suspended through this window over missing water, emissions, noise and diesel-generator data. Deputy Mayor Eddie Andrews confirmed on 20-21 September that the suspension holds.
Brazil (President Lula, signing Redata)
Brazil (President Lula, signing Redata)
Lula signed Lei 15.504 on 15 September, creating the Redata tax programme and keeping the Senate's water cap with no veto, while Aneel authorised Scala's AI City to join the national grid from January 2028. Brazil is recruiting capacity other markets are now turning away.
Aragon regional government (Eva Valle)
Aragon regional government (Eva Valle)
Aragon's economy chief Eva Valle said on 11 September that Spain's draft decree, requiring 80% hourly-matched renewables via a 10-year power-purchase agreement, is unmeetable by any project and threatens Blackstone, Azora and Microsoft builds already under way. Aragon holds 3,600 MW of granted grid access against 108 MW built.
Texas Governor Greg Abbott
Texas Governor Greg Abbott
Abbott ordered TCEQ on 21 September to halt every pending data-centre permit until projects pay their own way and complete ERCOT and Texas Water Development Board audits. Texas built the country's most permissive data-centre market; freezing it signals even that market has hit its grid limit.