Skip to content
You can now search across every topic, entity and event.What's new
Data Centres: Boom and Backlash
14AUG

Six US grid operators file, none say yes

3 min read
10:48UTC

All six US regional transmission organisations filed the generation-adequacy reports FERC ordered, and not one claims it can serve its data-centre queue under existing market rules.

IndustryDeveloping
Key takeaway

Every US regional grid operator told FERC its current rules cannot accommodate the data-centre queue.

All six US regional transmission organisations (RTO), the non-profit bodies that run wholesale power markets and dispatch electricity across multi-state regions, filed the generation-adequacy reports the Federal Energy Regulatory Commission (FERC) ordered by 20 July . The filings reach us summarised by docket in a Day Pitney memorandum to NEPOOL committees dated 23 July and hosted on ISO-NE's site, rather than through the filings themselves 1. Every one of the six says its markets hold in the near term. Not one claims it can serve its data-centre queue under current rules, and all six propose new tools instead.

ISO-NE goes furthest. It proposes that new large loads bring their own new generation, and that they be excluded from the load forecasts used to set the Installed Capacity Requirement, the volume of capacity the market buys each year to cover forecast peak demand plus a reserve margin 2. A data centre excluded from that requirement has no capacity bought on its behalf. It supplies its own energy or accepts curtailment. New England has seen almost none of this load and its demand has been flat or falling for a decade, so the proposal is pre-emptive rather than a response to strain.

The Midcontinent Independent System Operator (MISO), covering 15 central US states, cites a possible 4.7 GW shortfall by 2028 and will file a parallel study process for loads of 250 MW and above 3. The New York Independent System Operator (NYISO) sees no statewide deficiency until 2033, with New York City needs from 2031, and does not attribute an imminent gap to data centres at all. The California Independent System Operator (CAISO) and the Southwest Power Pool (SPP) are the slowest, both targeting filings on 16 November.

The spread between NYISO's 2033 and MISO's 2028 is the useful detail. These are not six regions in identical trouble; they are six regions writing the same clause into their rulebooks anyway, because the load arrives faster than a generator can be built and every operator would rather have the tool before it needs it.

Deep Analysis

In plain English

In the United States, regional grid operators are responsible for making sure there is enough electricity supply to meet demand where they operate. US energy regulator FERC ordered all six of these operators to report whether they can handle the wave of new data centres wanting to connect. None of them said yes under their current rules. Instead, each is proposing a different fix, from New England requiring data centres to bring their own power plants, to the mid-Atlantic region running a special one-off auction to buy extra capacity.

Deep Analysis
Root Causes

The structural cause identified across all six filings is that resource adequacy planning was built around gradual, geographically dispersed load growth, while data centres add large, concentrated blocks of demand at single substations within a matter of quarters, faster than new generation can typically be permitted and built.

A second structural driver, specific to ISO-NE, is that New England's overall load has been flat or declining for a decade, so its capacity market was never designed with mechanisms to absorb a new class of large, fast-growing demand; ISO-NE's own filing states it has 'not yet encountered significant large-load growth such as data centers,' meaning its proposed reform is pre-emptive rather than a response to an existing shortfall.

What could happen next?
  • Risk

    Without new tools, six separate US grid regions collectively project they cannot serve the data-centre queue they have already received.

  • Precedent

    ISO-NE's proposed self-supply requirement for new large loads, if adopted, gives other US grid operators a second working model beyond SPP's existing large-load tariff.

First Reported In

Update #12 · Ofgem prices the grid queue by the megawatt

Day Pitney LLP (hosted by ISO New England)· 4 Aug 2026
Read original
Different Perspectives
Antel, Uruguay's state telecom
Antel, Uruguay's state telecom
Antel will build a $70m AI data centre in Canelones, announced after an 11-12 August Council of Ministers meeting, with construction from Q1 2027 and roughly 250 direct jobs. Uruguay is putting a sovereign AI facility on the state balance sheet rather than courting a hyperscaler to build one.
Comtel
Comtel
Comtel is building a Figline Valdarno data centre inside the H2-Era Green Valley complex, powered by an 84 MW solar plant and selling waste heat to on-site farming. Co-location with generation and a heat offtaker is the model regulators elsewhere are now writing into connection terms rather than negotiating case by case.
Greg Abbott, Texas Governor
Greg Abbott, Texas Governor
Abbott directed PUCT and ERCOT on 3 August to audit every queued data centre's ownership, incentives and water use, saying projects that fail the state's survey should lose grid access. QTS's co-chief executives welcomed the review; Agriculture Commissioner Sid Miller called it too vague and wants a special legislative session instead.
Government of Gujarat
Government of Gujarat
Gujarat notified a Data Centre Policy on 7 August offering capital, interest, tax and duty subsidies for projects sourcing at least 51% green power, targeting 7.5 GW against a 74 GW installed base. Where other jurisdictions priced or restricted grid access this month, Gujarat is paying developers to come instead.
Taiwan's Legislative Yuan Economics Committee
Taiwan's Legislative Yuan Economics Committee
The committee gave preliminary approval on 5 August to a self-generation mandate for large power users, including data centres, with fines up to NT$750,000. It agreed the obligation in principle while leaving the megawatt threshold that defines its reach to later implementing regulation.
Australian Energy Market Commission
Australian Energy Market Commission
AEMC advised ministers on 5 August that data centres should surrender renewable certificates against actual consumption, prove new demand with new firm capacity, and register as market participants. The advice would turn passive customers into obligated participants inside the market's dispatch and settlement machinery, ahead of an access-standards determination due in late October.