Data Centres: Boom and Backlash
4AUG

PJM wants 50 MW loads curtailable

2 min read
10:53UTC

A Federal Register notice on 4 August opened comment on PJM's Interim Resource Adequacy Service, which would make loads of 50 MW and above curtailable as a condition of connection from June 2027.

IndustryDeveloping
Key takeaway

PJM would make curtailment a standing condition of connection for loads above 50 MW.

PJM Interconnection, the grid operator that runs wholesale power markets across 13 Mid-Atlantic and Midwest states, filed at the Federal Energy Regulatory Commission (FERC, which regulates interstate electricity transmission) on 31 July under docket ER26-3380-000. The filing bundles the Reliability Backstop Procurement we covered with an Interim Resource Adequacy Service (IRAS), which makes loads of 50 MW and above curtailable as a condition of connection from 1 June 2027 unless they bring their own capacity. The Federal Register notice opening comment published on 4 August, comments close at 5pm Eastern on 21 August, and PJM asks for an effective date of 29 September⁠1.

PJM's capacity auction fell 6,623 MW short in July. That shortfall is the arithmetic sitting under both halves of the docket: one half procures backstop capacity, the other reduces the load the system has to guarantee.

Draw a line no source draws. IRAS writes curtailability into the terms of connection and stays there until FERC changes it, a market rule of indefinite duration. The Department of Energy's Section 202(c) grant to PJM, which let the operator cut backup-equipped data centres during a heat event, ran as an emergency order under statute, temporary and exceptional by design. Different instrument, different authority, different permanence.

For a developer, the practical consequence lands in the financing model rather than in the engineering. A load that accepts IRAS accepts curtailment as its ordinary condition of service, which changes the availability assumption a lender underwrites, and the escape route, bringing your own capacity, means generation on site or contracted firm supply. Comments close before the operator can know how many will take it.

Deep Analysis

In plain English

PJM Interconnection runs the electricity grid across 13 US states and Washington DC. On 4 August, the government's Federal Register published PJM's request to make any electricity user drawing 50 megawatts or more, enough to power tens of thousands of homes, subject to being switched off during grid stress unless it has its own backup power. The rule would take effect from June 2027 and would replace the emergency curtailment orders regulators have already used twice this year with a permanent, standing requirement.

Deep Analysis
Root Causes

PJM's 2027/28 capacity auction cleared 6,623 MW short of its reliability requirement in July, and a separate 6,831 MW shortfall against the 2028/29 delivery year is what PJM's reliability backstop auction, filed in the same docket as IRAS, is trying to close. IRAS addresses the demand side of that gap: rather than paying more generators to exist, as the backstop auction does, it makes large loads bring their own capacity or accept curtailment.

The structural driver behind both halves of docket ER26-3380-000 is the same shortfall counted two ways. PJM's reliability requirement has outpaced the generation actually connecting to its grid, which is why IRAS addresses demand while the backstop auction addresses supply, and neither alone closes the gap on its own.

What could happen next?
  • Precedent

    IRAS would convert emergency curtailment, used twice by DOE in 2026, into a standing condition of grid connection.

First Reported In

Update #13 · GPUs now collateral as Nebius borrows $775m

Scottish Government Planning and Environmental Appeals Division· 14 Aug 2026
Read original →
Different Perspectives
Chilean data-centre developers
Chilean data-centre developers
Seven projects, one linked to Google, asked SEA this month for rulings that they fall outside full environmental review; four declared diesel-storage volumes just under the review-triggering tonnage, mirroring the mechanism Alto Jahuel used in July. The clustering suggests the threshold is being engineered, not sized to need.
An Coimisiun Pleanala
An Coimisiun Pleanala
Ireland's planning appeals body refused the €1.5bn Killala data centre on 17 September, overturning Mayo County Council's 2025 grant for lack of a fixed grid-connection agreement and no corporate renewable power-purchase agreement. The ruling makes matched-power evidence, not planning consent alone, the deciding factor.
Housing Assembly and Foxglove
Housing Assembly and Foxglove
The two groups' 6 August appeal, filed through the Legal Resources Centre, kept Cape Town's approval of Equinix's data centre suspended through this window over missing water, emissions, noise and diesel-generator data. Deputy Mayor Eddie Andrews confirmed on 20-21 September that the suspension holds.
Brazil (President Lula, signing Redata)
Brazil (President Lula, signing Redata)
Lula signed Lei 15.504 on 15 September, creating the Redata tax programme and keeping the Senate's water cap with no veto, while Aneel authorised Scala's AI City to join the national grid from January 2028. Brazil is recruiting capacity other markets are now turning away.
Aragon regional government (Eva Valle)
Aragon regional government (Eva Valle)
Aragon's economy chief Eva Valle said on 11 September that Spain's draft decree, requiring 80% hourly-matched renewables via a 10-year power-purchase agreement, is unmeetable by any project and threatens Blackstone, Azora and Microsoft builds already under way. Aragon holds 3,600 MW of granted grid access against 108 MW built.
Texas Governor Greg Abbott
Texas Governor Greg Abbott
Abbott ordered TCEQ on 21 September to halt every pending data-centre permit until projects pay their own way and complete ERCOT and Texas Water Development Board audits. Texas built the country's most permissive data-centre market; freezing it signals even that market has hit its grid limit.