The Record
Data Centres: Boom and Backlash
What we told you to watch, what each side claimed, and what we got wrong. Every verdict shows its evidence.
Happened 2 · Unresolved 1 · Open 75 · Corrections 132
What we told you to watch
Happened · 2
Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.
From the 8 Sept briefing · Judged 22 Oct 2026
SEA's Alto Jahuel case file is available and was checked.
“SEA's resolution specifies about 990 tonnes of diesel.”
Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.
From the 8 Sept briefing · Judged 22 Oct 2026
CRU approved MPID 345 on 22 September 2026.
“CRU approved MPID 345 on 22 September 2026.”
Unresolved · 1
NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .
From the 24 Sept briefing · Judged 22 Oct 2026
Final ballot passed; Board adoption and FERC filing remain pending.
“The standards passed final ballot and advance to Board adoption.”
Still open · 75
Show the 10 most recentWhether the county-level moratorium wave forces a statewide response in Indiana
From the 7 Jul briefing
Whether Chevron takes a final investment decision on Project Kilby by the end of 2026, or the GE Vernova turbine queue pushes first power past 2028.
From the 28 Jun briefing
Whether FERC's six grid operators meet the 17 August show-cause deadline, or seek extensions that push any binding rule deep into 2027.
From the 28 Jun briefing · Deadline: 17 August
Whether another state copies Virginia's behind-the-meter tax now that one jurisdiction has a working model.
From the 28 Jun briefing
Whether Texas locks the Batch Zero cohort before its 438 GW queue grows enough to make the autumn 2027 plan obsolete on arrival.
From the 28 Jun briefing
Whether Virginia's 22 June Senate session breaks the exemption deadlock before the 30 June deadline, and whether the Lucas generator fee survives into the final budget or dies as a negotiating gambit.
From the 17 Jun briefing · Deadline: 22 June
Whether the Oregon PUC holds PGE's 29% large-load rise at its 7 July decision, or trims the figure and reopens the cost-attribution framework.
From the 17 Jun briefing · Deadline: 7 July
Whether Virginia DEQ attaches any PFAS testing condition to Amazon's Lake Anna discharge permit, which the 9 June hearing left undecided.
From the 17 Jun briefing · Deadline: 9 June
Whether FERC issues the RM26-4-000 interconnection rule by end-June or lets its own deadline pass.
From the 17 Jun briefing
Whether the Virginia Department of Environmental Quality (DEQ) attaches any PFAS (per- and polyfluoroalkyl substances, the persistent 'forever chemicals') testing condition when it finally rules on Amazon's 280,000-gallon-a-day Sedges Creek discharge into Lake Anna; the 9 June hearing produced objections but no decision.
From the 10 Jun briefing · Deadline: 9 June
Whether Virginia's 18 June special session breaks the $1.9bn tax-exemption deadlock before the 30 June fiscal deadline, with the Senate demanding full elimination and the House insisting on environmental conditions.
From the 10 Jun briefing · Deadline: 18 June
Whether FERC issues its RM26-4-000 large-load interconnection rule by end of June, or lets the self-imposed deadline pass.
From the 10 Jun briefing · Deadline: end of June
Whether any PJM-territory state publishes a cost-allocation framework before the September backstop procurement, or whether costs keep drifting to households by default.
From the 10 Jun briefing
Whether any PJM-territory state publishes a data-centre cost-allocation framework before the September Reliability Backstop Procurement, or lets the costs default to ratepayers.
From the 2 Jun briefing
Whether a Texas court grants RCM Hill's injunction against the Hill County moratorium, the first test of a Fifth Amendment taking claim against a US data-centre pause.
From the 2 Jun briefing
Whether Virginia DEQ approves Amazon's Sedges Creek permit after the 9 June hearing, and whether it adds any PFAS testing condition.
From the 2 Jun briefing · Deadline: 9 June
Whether Virginia's 18 June special session resolves the data-centre tax exemption or triggers a partial state shutdown by 30 June.
From the 2 Jun briefing · Deadline: 18 June
Whether FERC settles the RM26-4-000 permanent co-located-load rule by its end-June deadline, and whether it shields BTM generation or confirms its new role as interruptible reserve.
From the 26 May briefing
The Virginia budget resolution and whether any abatement cut applies retroactively to commitments already made.
From the 26 May briefing
Whether a third DOE Section 202(c) curtailment order lands during the summer peak, turning two orders into a settled pattern.
From the 26 May briefing
What each side claimed
Claims are what a named side said at the time. We record them as said and judge them only against later evidence.
No claims recorded yet.
What we got wrong
- MinorCorrected 18 Oct 2026We said
Teraco operates in South Africa, Nigeria and Kenya
What was trueTeraco's data centres are all in South Africa (Johannesburg, Cape Town, Durban), per teraco.co.za; Digital Realty's Kenyan and Nigerian sites are separate businesses
- MinorCorrected 18 Oct 2026We said
Teraco operates in South Africa, Nigeria and Kenya
What was trueTeraco's data centres are all in South Africa (Johannesburg, Cape Town, Durban), per teraco.co.za; Digital Realty's Kenyan and Nigerian sites are separate businesses
- MinorCorrected 18 Oct 2026We said
Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June
What was trueOn 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed
- MinorCorrected 18 Oct 2026We said
Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June
What was trueOn 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed
- MinorCorrected 18 Oct 2026We said
Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June
What was trueOn 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed
- MinorCorrected 18 Oct 2026We said
Teraco operates in South Africa, Nigeria and Kenya
What was trueTeraco's data centres are all in South Africa (Johannesburg, Cape Town, Durban), per teraco.co.za; Digital Realty's Kenyan and Nigerian sites are separate businesses
- MinorCorrected 18 Oct 2026We said
Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June
What was trueOn 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed
- MinorCorrected 18 Oct 2026We said
Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June
What was trueOn 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed
- MinorCorrected 18 Oct 2026We said
Kua Kia Soong is the director of Suaram
What was trueKua Kia Soong is a former Suaram director; his 26 June 2026 letter in Free Malaysia Today is signed "former MP and former Suaram director"
- MinorCorrected 18 Oct 2026We said
Kua Kia Soong is the director of Suaram
What was trueKua Kia Soong is a former Suaram director; his 26 June 2026 letter in Free Malaysia Today is signed "former MP and former Suaram director"
- MinorCorrected 18 Oct 2026We said
Kua Kia Soong is the director of Suaram
What was trueKua Kia Soong is a former Suaram director; his 26 June 2026 letter in Free Malaysia Today is signed "former MP and former Suaram director"
- MinorCorrected 18 Oct 2026We said
Kua Kia Soong is the director of Suaram
What was trueKua Kia Soong is a former Suaram director; his 26 June 2026 letter in Free Malaysia Today is signed "former MP and former Suaram director"
- MinorCorrected 18 Oct 2026We said
That spare hydropower sits mostly in the north; in the south, where prices track Germany and Britain, a data-centre booking competes directly with households for the same power.
What was trueNo source in the run's research supports the north/south price split; the sentence was cut from event analysis in review and is removed from the body before sync.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.
- SignificantCorrected 1 Oct 2026We said
Meta's El Paso data centre was described as running on, contracting, commissioning or operating a 366 MW behind-the-meter gas array, as a settled fact.
What was trueOn 1 March 2026 the 366 MW McCloud gas plant for Meta's El Paso data centre was a plan. El Paso Electric had applied to the Public Utility Commission of Texas, and no ruling had issued. It was still unapproved on 1 October 2026: administrative law judges recommended approval on 24 September 2026, and no final order had issued.