Ireland refuses €1.5bn Mayo data centre

1 min read
10:06UTC

Ireland's planning appeals body refused a €1.5bn data centre at Killala, County Mayo, because the developer showed no fixed grid connection and no renewable power contract.

IndustryAssessed
Key takeaway

Ireland's planning appeals body refused a data centre that could not prove grid capacity or renewable supply.

An Coimisiun Pleanala, Ireland's national planning appeals body, refused a €1.5bn data centre at Killala, County Mayo, on 17 September, overturning Mayo County Council's 2025 grant⁠1. The applicant, Mayo Data Hub, is backed by Avaio Digital.

The board found the developer had shown no fixed grid connection agreement and no proof that the grid could serve the site, RTE News reported. It also found the project had not shown it would meet the objectives of Ireland's Climate Action Plan 2025, citing the absence of any Corporate PPA (Power Purchase Agreement) with a renewable supplier.

Ireland's energy regulator, the Commission for Regulation of Utilities, had been consulting on grid-code obligations that EirGrid would impose on large demand sites such as data centres. Killala moves those tests forward to the planning stage. An Irish applicant now faces a demand for grid and power-purchase evidence at the planning stage, before any connection offer.

Deep Analysis

In plain English

Ireland's national planning appeals board rejected a €1.5bn data centre planned for Killala in County Mayo, even though the local county council had already approved it last year. The board's reasons were about power, not politics: the developer had no confirmed grid connection agreement, and no signed contract to buy renewable electricity. This matters beyond Mayo because it shows Ireland's appeals process is now applying the same tough grid and renewable-energy tests used around Dublin to projects anywhere in the country, even regions once seen as an escape route from Dublin's stricter rules.

Deep Analysis
Root Causes

Ireland's grid has operated under an effective restriction on new large-load connections around Dublin since 2021, pushing developers toward the regions; Mayo Data Hub tried to build outside that constrained zone but still needed the grid operator to confirm the west of Ireland's thinner transmission network could serve a €1.5bn campus, and went to appeal without that confirmation in hand.

The refusal also rests on the absence of a corporate power-purchase agreement, a financing instrument rather than a planning requirement in most jurisdictions; treating a missing PPA as grounds for refusal signals Ireland now expects developers to prove renewable electricity is contracted, not merely available, before construction can begin.

First Reported In

Update #15 · Texas freezes data-centre permits

RTE News· 24 Sept 2026
Read original →
Causes and effects
This Event
Ireland refuses €1.5bn Mayo data centre
In An Coimisiun Pleanala's decision, missing grid-capacity evidence and a missing renewable PPA became grounds to refuse planning permission, ahead of any grid connection.
Different Perspectives
Mohsen Rezaei
Mohsen Rezaei
The senior Iranian security official and former IRGC commander told Press TV that US-linked technology infrastructure in the region could become a target if war resumes. He named the UAE and valued the assets at more than US$2 trillion, without a breakdown.
Mykhailo Shelemba
Mykhailo Shelemba
Datagroup's chief executive says the Kyiv data centre hit on the night of 18 to 19 October is beyond repair. Services continue from backup sites, and no staff were hurt.
Kristen Umstattd
Kristen Umstattd
The Loudoun supervisor voted against fast-tracking Amazon's rezoning of the Ashburn campus. She said there were no figures yet on homes, school or road costs.
Akishima residents' litigation group
Akishima residents' litigation group
The group formed on 18 October and plans to sue Nihon GLP by year-end to stop eight data-centre buildings. Its lawyers will argue rights to life, health, clean water and a natural environment after mediation failed in August.
Óscar López
Óscar López
Spain's Digital Transformation minister said on 22 October he could not confirm when the data-centre decree will be approved. He added that Google has always committed to investing in Spain.
Google
Google
Google said it would comply with LVV's order to stop preparatory works at Muhos and Kajaani until environmental assessments finish. A spokesperson conceded the company had fallen short.