Fermi signs 600 MW tenant, no lease yet

2 min read
18:00UTC

Fermi signed agreements with an unnamed investment-grade hyperscaler for 600 MW at Project Matador, backed by a $200m prepayment, but the two have not yet signed a lease.

IndustryAssessed
Key takeaway

Fermi has a hyperscaler's prepayment for 600 MW, but no signed lease and no revenue.

Fermi, a US-listed Texas developer, said in a filing on Thursday 12 November that it has signed agreements with an unnamed investment-grade hyperscaler for an initial 600 MW at Project Matador, in the Texas Panhandle, from 2027⁠1. A $200m prepayment agreement and a $15m early construction agreement back them, and a $90m structural steel purchase is being finalised. The parties are still working towards a definitive long-term lease.

Fermi's first tenant has gone. Fermi and TensorWave, an AI cloud provider, terminated their August 2026 lease, and the related credit support from AMD (Advanced Micro Devices, the chipmaker) ended with it. Fermi is pre-revenue and lost $141.6m in the third quarter. It held $315.5m of cash and restricted cash, and its net debt, after that cash, was $958.4m.

Matador is designed behind the meter, with generation on the site's side of any grid connection: a private grid of gas, a planned nuclear complex, grid power, solar and batteries, ramping to about 17 GW subject to binding contracts. The 600 MW signed so far is about 3.5% of that headline (600 ÷ 17,000). Land-lease conditions with the Texas Tech University System must still be met before vertical construction starts. In October Nebius signed a preliminary framework for capacity at Saudi Arabia's Oxagon campus that did not say whether it binds.

Deep Analysis

In plain English

Fermi wants to build an enormous private power and data-centre campus, called Project Matador, in the Texas Panhandle. It plans its own power station, solar, batteries and eventually nuclear reactors, so the site would not depend on the public grid. The company has no revenue yet. Its first planned tenant, an AI cloud firm called TensorWave, cancelled. Now a large unnamed cloud company has paid towards 600 megawatts, enough for a very large data centre, starting in 2027. The two sides have not yet signed a long-term lease, the contract that would guarantee Fermi years of rent.

Deep Analysis
Root Causes

A prepayment and an early works contract let a hyperscaler buy an option rather than a commitment. They secure a place in line at a powered site without the decade-long rent a lease would lock in, which suits buyers who cannot yet tell when gas turbines and grid links will arrive.

Texas's grid queue drives the behind-the-meter design. ERCOT had more than 225 GW of large-load requests in study by April 2026, so a developer that builds its own generation avoids years of waiting, at the cost of carrying the power plant's financing itself.

What could happen next?
  • Risk

    If no lease follows, Fermi must fund a large private power system with no contracted income behind it.

  • Meaning

    Hyperscalers are using prepayments to reserve power at speculative sites without signing long leases.

First Reported In

Update #19 · US grids set a price to cut off data centres

US Securities and Exchange Commission (Fermi Inc.)· 26 Nov 2026
Read original →
Different Perspectives
MUFG
MUFG
Mitsubishi UFJ (MUFG) and Morgan Stanley are preparing to sell a loan of about $4.5bn secured on the GPUs CoreWeave runs for Meta in Dalton, Georgia, with price talk of 7% to 7.5%, Bloomberg reported. Meta's contract is expected to win the loan investment-grade ratings, though CoreWeave is rated below investment grade and the loan has not priced.
CX Tech
CX Tech
CX Tech's £16.5bn, 1,000 MW plan for the former Chapelcross nuclear site has drawn more than 10,000 representations, the most Dumfries and Galloway's planners have received, BBC News reported. The company says the scheme could support up to 750 construction jobs and about 540 permanent posts; comments close on 29 November.
Nate Glubish, Alberta's technology and innovation minister
Nate Glubish, Alberta's technology and innovation minister
Glubish tabled Bill 42 on 18 November to ban power plants and data centres on Class 1 and 2 farmland and within 600 m of homes, a day after the regulator approved a 1,494 MW plant that fails both tests. The bill exempts projects already approved or under review, so the Indus plant stands.
NEXTDC's chairman and chief executive
NEXTDC's chairman and chief executive
After a second pay strike and a defeated spill on 20 November, NEXTDC's leaders said they are exploring a joint venture for the S4 Sydney campus and do not expect to raise shareholder capital for contracted capacity. They raised FY27 underlying EBITDA guidance to A$260m-A$275m, still excluding about A$140m tied to Melbourne's stalled M3 site.
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
The three groups argued in the High Court on 18 November that the CRU's data-centre connection framework breaches the 2015 Climate Act by ignoring carbon budgets, which the CRU denies. Judge Micheal O'Connell reserved judgment with no date, so the framework stands meanwhile.
South Korean data-centre industry groups
South Korean data-centre industry groups
Industry groups told Etnews on 13 November that tougher grid scoring for one sector alone is unfair, three days before the climate and energy ministry raised the capital-region pass mark to 75 from 70. Pending applications are judged on the new bar; the pilot assessed 28 capital-region projects worth 1.9 GW.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.