Project Matador
Fermi's planned 17 GW behind-the-meter power and data-centre campus in the Texas Panhandle.
As of November 2026, Project Matador has agreements for 600 MW starting in 2027 with an unnamed cloud giant, secured by a $200m prepayment, but Fermi disclosed on 12 November that no lease is signed and the campus's first tenant has gone.
Last refreshed: 26 November 2026 · Appears in 1 active topic
Project Matador targets 17 GW; why is only 600 MW signed, and without a lease?
Timeline for Project Matador
Gained its first hyperscaler agreements
Data Centres: Boom and Backlash: Fermi signs 600 MW tenant, no lease yetBackground
Project Matador is Fermi's planned campus in the Texas Panhandle, designed to make its own power behind the meter and rent capacity to AI data-centre tenants. Its value depends on signing those tenants to binding leases.
On 12 November 2026 Fermi said it had agreements covering an initial 600 MW for a hyperscaler it did not name, starting in 2027 and supported by a $200m prepayment, but no definitive lease. The site's first lease, signed with TensorWave, had already been terminated. Fermi reported a $141.6m loss for the third quarter and no revenue.
Until a lease is signed, Matador has no paying tenant. The 600 MW tranche is the first test of whether a private power campus of this kind can turn land and generating plans into rent.
Reference
Where is Fermi's Project Matador?
Who is the tenant at Project Matador?
How will Project Matador be powered?