Data Centres: Boom and Backlash
24SEP

Five grid operators miss FERC deadline

1 min read
13:52UTC

Five US grid operators missed the Federal Energy Regulatory Commission's 17 August show-cause deadline on large loads and were granted abeyance until 16 November.

IndustryDeveloping
Key takeaway

The five operators now answer the Commission on large loads by 16 November, not 17 August.

Five US grid operators missed the Federal Energy Regulatory Commission's 17 August show-cause deadline on large loads and were granted abeyance until 16 November⁠1. A show-cause order requires its recipient to explain why its rules should not be changed. Abeyance holds the proceeding open without that explanation being filed.

Six grid operators had already told the Commission in July that none of them can serve data-centre demand under current rules. What has slipped is the deadline for setting out what they would put in place instead. The abeyance keeps the docket alive and pushes the answer to November, which leaves the existing connection rules for very large loads running through the autumn on markets that have already said those rules do not work.

Deep Analysis

In plain English

US energy regulators told grid operators to explain by 17 August how they plan to handle huge new electricity users like data centres. None of the five operators made that deadline, so the regulator has given them until 16 November instead. Until then, the existing rules for connecting big new loads stay exactly as they were.

Deep Analysis
Root Causes

FERC's show-cause process requires grid operators to justify existing interconnection rules or propose changes, but designing new large-load rules touches rate design, reliability standards and existing customer contracts across each operator's footprint, work that typically takes regulatory staff many months to draft and internally clear before filing.

Missing the original deadline reflects that drafting load, not a decision to delay for its own sake, which is why the Commission granted abeyance rather than penalty.

Escalation

The rules governing how US grid operators must handle large new electricity demand remain unresolved for a further three months, extending the period in which large-load connection policy is set case by case rather than under a settled framework.

First Reported In

Update #14 · Brazil bill ties tax break to a water cap

Stoel Rives LLP· 8 Sept 2026
Read original →
Different Perspectives
Chilean data-centre developers
Chilean data-centre developers
Seven projects, one linked to Google, asked SEA this month for rulings that they fall outside full environmental review; four declared diesel-storage volumes just under the review-triggering tonnage, mirroring the mechanism Alto Jahuel used in July. The clustering suggests the threshold is being engineered, not sized to need.
An Coimisiun Pleanala
An Coimisiun Pleanala
Ireland's planning appeals body refused the €1.5bn Killala data centre on 17 September, overturning Mayo County Council's 2025 grant for lack of a fixed grid-connection agreement and no corporate renewable power-purchase agreement. The ruling makes matched-power evidence, not planning consent alone, the deciding factor.
Housing Assembly and Foxglove
Housing Assembly and Foxglove
The two groups' 6 August appeal, filed through the Legal Resources Centre, kept Cape Town's approval of Equinix's data centre suspended through this window over missing water, emissions, noise and diesel-generator data. Deputy Mayor Eddie Andrews confirmed on 20-21 September that the suspension holds.
Brazil (President Lula, signing Redata)
Brazil (President Lula, signing Redata)
Lula signed Lei 15.504 on 15 September, creating the Redata tax programme and keeping the Senate's water cap with no veto, while Aneel authorised Scala's AI City to join the national grid from January 2028. Brazil is recruiting capacity other markets are now turning away.
Aragon regional government (Eva Valle)
Aragon regional government (Eva Valle)
Aragon's economy chief Eva Valle said on 11 September that Spain's draft decree, requiring 80% hourly-matched renewables via a 10-year power-purchase agreement, is unmeetable by any project and threatens Blackstone, Azora and Microsoft builds already under way. Aragon holds 3,600 MW of granted grid access against 108 MW built.
Texas Governor Greg Abbott
Texas Governor Greg Abbott
Abbott ordered TCEQ on 21 September to halt every pending data-centre permit until projects pay their own way and complete ERCOT and Texas Water Development Board audits. Texas built the country's most permissive data-centre market; freezing it signals even that market has hit its grid limit.