Skip to content
You can now search across every topic, entity and event.What's new
Data Centres: Boom and Backlash
8SEP

Pure DC Dublin microgrid surfaces as Irish template

2 min read
13:06UTC

Pure DC's 110 MW Dublin microgrid, deployed with AVK and commissioned in March, has emerged as the working compliance template for Ireland's CRU on-site-generation requirement.

IndustryDeveloping
Key takeaway

The CRU on-site-generation rule now has a worked example, and other regulators are watching closely.

Pure DC's 110 MW Dublin microgrid , built with engineering partner AVK and described by the developer as Europe's first deployment at that scale, has emerged this week as the working compliance template for CRU's December 2025 on-site-generation requirement. CRU, Ireland's Commission for Regulation of Utilities, set a rule requiring new data centres to source 80 per cent of annual demand from additional Irish-sited renewables within six years of energisation. The Pure DC microgrid uses gas generation with biomethane and hydrotreated vegetable oil switching capability, the configuration the rule's drafters had in mind when they approved it.

The surfacing matters because Ireland's policy environment had been the murkiest in Europe for new data-centre projects since Dublin's grid moratorium effectively sealed the market in 2022. CRU's December 2025 framework reopened the door, conditional on on-site generation, but operators had no example of a compliant build until Pure DC's. The same CRU directive instructed EirGrid and ESB Networks to publish a data-centre engagement and connection process by 31 March 2026; that deadline passed without a public publication, and the gap remains an open compliance question for the next round of Dublin applicants.

The Pure DC template will be read carefully across two other jurisdictions. American state utilities exploring on-site-generation requirements as an alternative to outright moratoriums now have an EU example of how the rule plays in practice, which is relevant for any FERC ruling on RM26-4-000 that addresses behind-the-meter cost allocation. Spanish and Iberian operators are watching for the biomethane and HVO switching mechanism, because the same fuel-flex configuration suits a renewable-heavy grid where dispatchable backup is the contested layer. The Dublin microgrid is one project; the regulatory pathway it has cleared is the asset.

Deep Analysis

In plain English

Ireland's energy regulator (the CRU, or Commission for Regulation of Utilities) told data centres in December 2025 that they needed to generate their own electricity on-site rather than relying entirely on the national grid. Pure DC, a data centre operator, became the first to comply with this rule by installing its own 110 MW power plant at its Dublin campus in March 2026, built with a Danish engineering company called AVK. The power plant runs mainly on gas but is designed to switch to biomethane (a renewable gas made from organic waste) or HVO (a plant-based diesel alternative). This gives the campus its own power supply independent of the national grid, which was the regulator's goal. The catch: there is not enough biomethane made in Ireland to run the whole plant on renewable fuel.

First Reported In

Update #2 · Maine veto, Seattle freeze, $725bn capex

Pure DC· 6 May 2026
Read original
Different Perspectives
NVIDIA
NVIDIA
NVIDIA told the Securities and Exchange Commission on 26 August it had signed memorandums aiming to mobilise over $500bn for buyers' equipment purchases, then said in the same filing the arrangements may not become definitive. It may also carry limited residual-value risk on the equipment itself.
IREN Limited
IREN Limited
IREN signed $2.4bn of financing on 25 August that only releases cash once its Mackenzie GPU servers are accepted, and only through 31 December 2026. A shipping delay from here now creates a funding problem as well as a revenue one.
Energy Commission (Malaysia)
Energy Commission (Malaysia)
Malaysia's Energy Commission recorded data centres at 9.3% of national power in one hot week in August, against a 7% year-to-date average, and is projecting 31% of peninsular demand by 2035. It wants roughly 9 GW of new gas-fired capacity by 2032 to cover the gap.
Economic Development Board and Infocomm Media Development Authority
Economic Development Board and Infocomm Media Development Authority
Singapore's EDB and IMDA rationed 200 MW across four operators on 21 August and followed with a tropical liquid-cooling standard six days later, fixing the terms before construction starts. The agencies will decide within 18 to 24 months whether to run a third call.
Legal Resources Centre
Legal Resources Centre
The Legal Resources Centre put the water and power draw of two approved Cape Town Equinix sites in public, at roughly 4.4 billion litres and 1.4 to 1.5 billion kWh a year, because the city and the operator would not. It wants a cumulative assessment before any more of the five approvals proceed.
Ministerio de Minas e Energia
Ministerio de Minas e Energia
Brazil's energy ministry published Redata's five conditions after the Senate passed PL 278/2026 on 1 September, betting a repeatable annual water test enforces cooling design better than a one-off approval. Redata now needs President Lula's signature before any of it takes effect.