MISO's second grid emergency in July

2 min read
13:06UTC

MISO declared its second maximum-generation emergency of the month on 15 July as a heat dome drove demand to a 122 GW peak, five days before FERC's grid-adequacy filing deadline.

IndustryDeveloping
Key takeaway

MISO rationed power days before it had to certify to regulators that its supply was adequate.

MISO, the grid operator for 15 central US states, declared a maximum-generation emergency on 15 July, its second of the month, as a heat dome pushed demand to a 122 GW peak. A maximum-generation emergency calls on every available plant and asks large users to cut load, the last routine step before controlled blackouts. 1 The declaration landed five days before the 20 July deadline the Federal Energy Regulatory Commission (FERC), the US regulator for interstate power, set for its six regional transmission organisations (RTOs) to file generation-adequacy reports .

FERC ordered those reports in place of a binding connection rule , and MISO's own figures show why the paperwork lags the weather. Data-centre load in its footprint has grown at a 43% compound annual growth rate (load CAGR, the yearly rate at which demand compounds) since 2020. The operator forecasts a 163 GW peak by 2035; it already touched 122 GW in a single July heat wave, so that forecast stacks another 41 GW on a grid that is rationing supply today.

The adequacy report describes supply on paper the same week the operator was cutting it in practice. That is the contradiction the FERC docket exists to interrogate, and MISO has now written it into the record twice in one month.

Deep Analysis

In plain English

MISO runs the electricity grid across 15 US states in the middle of the country. On 15 July, a heat wave pushed demand so high, 122 gigawatts at the peak, that MISO had to declare an emergency for the second time that month, meaning it may need to ask big power users to cut back to keep the lights on everywhere else. A big part of the extra demand is data centres, which have grown their electricity use by 43% a year since 2020 within MISO's territory. Five days later, the US grid regulator FERC (Federal Energy Regulatory Commission) was due a report from MISO and five other grid operators explaining how they plan to keep up.

Deep Analysis
Root Causes

MISO's 43% compound annual growth rate in data-centre load since 2020 has outpaced the multi-year lead times for new gas turbines and transmission build-out, so the grid operator is absorbing demand growth faster than physical generation capacity can be added.

The 20 July FERC adequacy-report deadline lands five days after this emergency, giving MISO live evidence of exactly the stress its report is meant to describe, rather than a hypothetical scenario regulators asked it to model.

What could happen next?
  • Risk

    A second maximum-generation emergency in one month raises the chance MISO invokes involuntary load-shedding before the FERC-mandated tariff reforms, due around 17 August, take effect.

  • Meaning

    MISO's 122 GW peak and 43% data-centre CAGR give the 20 July adequacy filing concrete numbers to reconcile against, rather than a hypothetical stress test.

First Reported In

Update #11 · Pipeline vetoed, campus keeps building

RTO Insider· 25 Jul 2026
Read original
Different Perspectives
NVIDIA
NVIDIA
NVIDIA told the Securities and Exchange Commission on 26 August it had signed memorandums aiming to mobilise over $500bn for buyers' equipment purchases, then said in the same filing the arrangements may not become definitive. It may also carry limited residual-value risk on the equipment itself.
IREN Limited
IREN Limited
IREN signed $2.4bn of financing on 25 August that only releases cash once its Mackenzie GPU servers are accepted, and only through 31 December 2026. A shipping delay from here now creates a funding problem as well as a revenue one.
Energy Commission (Malaysia)
Energy Commission (Malaysia)
Malaysia's Energy Commission recorded data centres at 9.3% of national power in one hot week in August, against a 7% year-to-date average, and is projecting 31% of peninsular demand by 2035. It wants roughly 9 GW of new gas-fired capacity by 2032 to cover the gap.
Economic Development Board and Infocomm Media Development Authority
Economic Development Board and Infocomm Media Development Authority
Singapore's EDB and IMDA rationed 200 MW across four operators on 21 August and followed with a tropical liquid-cooling standard six days later, fixing the terms before construction starts. The agencies will decide within 18 to 24 months whether to run a third call.
Legal Resources Centre
Legal Resources Centre
The Legal Resources Centre put the water and power draw of two approved Cape Town Equinix sites in public, at roughly 4.4 billion litres and 1.4 to 1.5 billion kWh a year, because the city and the operator would not. It wants a cumulative assessment before any more of the five approvals proceed.
Ministerio de Minas e Energia
Ministerio de Minas e Energia
Brazil's energy ministry published Redata's five conditions after the Senate passed PL 278/2026 on 1 September, betting a repeatable annual water test enforces cooling design better than a one-off approval. Redata now needs President Lula's signature before any of it takes effect.