Skip to content
You can now search across every topic, entity and event.What's new
Data Centres: Boom and Backlash
8SEP

Gujarat pays for 7.5 GW of capacity

2 min read
13:06UTC

Gujarat notified a data-centre policy on 7 August targeting 7.5 GW of capacity against a 74 GW installed power base, with subsidies conditional on projects sourcing at least 51% green power.

IndustryDeveloping
Key takeaway

Gujarat subsidises data centres that source at least 51% green power, targeting 7.5 GW.

Gujarat notified its Data Centre Policy 2026-29 on 7 August, targeting 7.5 GW of capacity against a 74 GW installed power base, with capital and interest subsidies, SGST reimbursement (the state share of India's Goods and Services Tax), electricity-duty reimbursement, desalination assistance and stamp-duty exemption, conditional on projects sourcing at least 51% green power. The policy names Dholera Special Investment Region as the primary hub. The direct government fetch was blocked and the detail rests on wire corroboration 1.

Set the two power figures beside each other and the ambition is plain: the target would add roughly a tenth to Gujarat's entire existing power system for one industry alone. Dholera is the state's greenfield industrial city on the Gulf of Khambhat, already the site of India's semiconductor fabrication push, so the policy stacks chip manufacturing and compute on the same grid and the same desalinated water.

The 51% clause is the condition Gujarat attaches instead of a bill. Where six US grid operators told their federal regulator in July that current rules cannot serve the queue at all , the Indian state has chosen the opposite lever, paying developers to come and pricing the green obligation into the subsidy rather than into the connection. Whether 7.5 GW of firm renewable supply can be built to match is the question the policy leaves open.

Deep Analysis

In plain English

Gujarat, an Indian state, published a new policy on 7 August offering data-centre developers a package of tax breaks and subsidies, but only if their project runs on at least 51% green power. The state wants to add 7.5 GW of data-centre capacity, roughly a tenth of its current total power supply, and has named the Dholera Special Investment Region as the main place it wants that capacity built.

First Reported In

Update #13 · GPUs now collateral as Nebius borrows $775m

Government of Gujarat· 14 Aug 2026
Read original
Different Perspectives
NVIDIA
NVIDIA
NVIDIA told the Securities and Exchange Commission on 26 August it had signed memorandums aiming to mobilise over $500bn for buyers' equipment purchases, then said in the same filing the arrangements may not become definitive. It may also carry limited residual-value risk on the equipment itself.
IREN Limited
IREN Limited
IREN signed $2.4bn of financing on 25 August that only releases cash once its Mackenzie GPU servers are accepted, and only through 31 December 2026. A shipping delay from here now creates a funding problem as well as a revenue one.
Energy Commission (Malaysia)
Energy Commission (Malaysia)
Malaysia's Energy Commission recorded data centres at 9.3% of national power in one hot week in August, against a 7% year-to-date average, and is projecting 31% of peninsular demand by 2035. It wants roughly 9 GW of new gas-fired capacity by 2032 to cover the gap.
Economic Development Board and Infocomm Media Development Authority
Economic Development Board and Infocomm Media Development Authority
Singapore's EDB and IMDA rationed 200 MW across four operators on 21 August and followed with a tropical liquid-cooling standard six days later, fixing the terms before construction starts. The agencies will decide within 18 to 24 months whether to run a third call.
Legal Resources Centre
Legal Resources Centre
The Legal Resources Centre put the water and power draw of two approved Cape Town Equinix sites in public, at roughly 4.4 billion litres and 1.4 to 1.5 billion kWh a year, because the city and the operator would not. It wants a cumulative assessment before any more of the five approvals proceed.
Ministerio de Minas e Energia
Ministerio de Minas e Energia
Brazil's energy ministry published Redata's five conditions after the Senate passed PL 278/2026 on 1 September, betting a repeatable annual water test enforces cooling design better than a one-off approval. Redata now needs President Lula's signature before any of it takes effect.