Skip to content
Welcome, thoughtbot's Giant Robots listeners!Start here
Data Centres: Boom and Backlash
8SEP

Edinburgh appeal now sits with ministers

2 min read
13:06UTC

The Redheughs Avenue appeal was recalled on 17 August and now sits with Scottish Ministers against a 28 September target. Lowdown counted 2,202 entries on the register Britain's queue figures are checked against, and not one is demand alone.

IndustryDeveloping
Key takeaway

Britain's TEC register holds no demand-only entries, so no demand-queue total can be derived from it.

The Redheughs Avenue appeal in Edinburgh, case reference PPA-230-2794, was recalled on 17 August and now sits on hold with Scottish Ministers, carrying a target decision date of 28 September⁠1. A recall lifts the decision away from the reporter appointed to hear it and puts it in ministers' hands. The application seeks planning permission in principle only, which settles whether a development of this kind belongs on the site without approving a design.

The scheme's agent confirmed in August that it would produce a full environmental impact assessment, the formal study of a development's environmental effects. Cases like this now turn on evidence about power and water demand rather than on land use alone, and that evidence has to come from a published dataset somewhere.

Britain's national demand figures come apart under the same scrutiny. Britain's data-centre connection queue is most often checked against the Transmission Entry Capacity register published by NESO, the National Energy System Operator that runs Great Britain's electricity system. Transmission Entry Capacity is the contracted right to put power on to the transmission system, and a data centre does the opposite: it takes power off. Lowdown counted the register's 2,202 entries on 8 September. 106 of them, 4.8%, carry any demand component in their plant type, and not one is demand alone; where demand appears it is compounded with generation at hybrid sites, in forms such as "Demand;Energy Storage System"⁠2. The register updates twice weekly, so those counts carry that date.

A register holding no demand-only entries cannot produce a demand-queue total. The 125 GW that circulates as one traces instead to a NESO presentation on future demand increase, which attributes the figure there to Energy Networks Association connection data⁠3. That presentation is an image-only document, so the attribution stands as what the slide says rather than as something we could verify at source. NESO's own reformed connections pipeline, published with its December 2025 reform results, reports 99 GW of transmission-connected demand⁠4. Two datasets, two definitions, and a third number that belongs to neither.

Both figures already do work in live policy arguments. Ofgem proposed a refundable deposit on grid connection offers in late July, priced at up to £712,500 per MW, which means the case for pricing a queue rests on a queue length nobody has published authoritatively. Edinburgh shows the same problem at one address. Ministers hold a decision that turns on how much power a single scheme would draw, in a country where the national total cannot be read off the register everyone reaches for.

Deep Analysis

In plain English

Britain keeps a public list of everything waiting to connect to the electricity grid, but that list was originally designed to track power plants, not big electricity users like data centres. Because demand and generation entries are not cleanly separated, nobody can simply add up a column and get an accurate total for how much new data-centre demand is really in the queue.

Deep Analysis
Root Causes

NESO's Transmission Entry Capacity register was built to track generation connecting to the grid, decades before data centres became large enough loads to need their own queue category.

Demand connections were added to the same register later without a clean field separating them from generation, which is why a straightforward count of demand-only entries does not exist and any published aggregate depends on how the counter chooses to filter the underlying rows.

What could happen next?
  • Meaning

    Any UK data-centre capacity figure attributed to the TEC register should be treated as an estimate derived from filtering choices rather than a published, authoritative total, until NESO adds a clean demand-only field.

First Reported In

Update #14 · Brazil bill ties tax break to a water cap

National Energy System Operator· 8 Sept 2026
Read original →
Different Perspectives
Mohsen Rezaei
Mohsen Rezaei
The senior Iranian security official and former IRGC commander told Press TV that US-linked technology infrastructure in the region could become a target if war resumes. He named the UAE and valued the assets at more than US$2 trillion, without a breakdown.
Mykhailo Shelemba
Mykhailo Shelemba
Datagroup's chief executive says the Kyiv data centre hit on the night of 18 to 19 October is beyond repair. Services continue from backup sites, and no staff were hurt.
Kristen Umstattd
Kristen Umstattd
The Loudoun supervisor voted against fast-tracking Amazon's rezoning of the Ashburn campus. She said there were no figures yet on homes, school or road costs.
Akishima residents' litigation group
Akishima residents' litigation group
The group formed on 18 October and plans to sue Nihon GLP by year-end to stop eight data-centre buildings. Its lawyers will argue rights to life, health, clean water and a natural environment after mediation failed in August.
Óscar López
Óscar López
Spain's Digital Transformation minister said on 22 October he could not confirm when the data-centre decree will be approved. He added that Google has always committed to investing in Spain.
Google
Google
Google said it would comply with LVV's order to stop preparatory works at Muhos and Kajaani until environmental assessments finish. A spokesperson conceded the company had fallen short.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.