Texas grid queue hits 410 GW

4 min read
10:53UTC

ERCOT told Texas legislators its large-load queue has reached 410 GW, roughly 87 per cent data centres, even as transformer lead times stretch to 128 weeks.

IndustryDeveloping
Key takeaway

ERCOT's queue hit 410 GW, but a 128-week transformer wait decides what can actually connect.

ERCOT told Texas legislators its large-load interconnection queue has reached 410 GW, with roughly 87 per cent of it data centres⁠1. ERCOT, the Electric Reliability Council of Texas, runs about 90 per cent of the state grid. The figure comes from its own presentations to the Senate Committee on Business and Commerce on 1 April and the House Committee on State Affairs on 9 April. It is up from the 225 GW ERCOT logged weeks earlier, and it sits at nearly five times the state's 85 GW peak demand.

The requests keep coming; the iron to serve them will not arrive in time. PwC analysts, via pv-magazine, put average large power transformer lead times at 128 weeks, with some orders quoted at four years⁠2. That tracks GE Vernova's backlog, which grew to 100 GW with deliveries booked into 2029 before the firm added $5bn of transformer capacity through its Prolec deal. An order placed now arrives in 2028 at the earliest.

Industry trackers put close to half of US data-centre builds already delayed or cancelled on supply-chain grounds. ERCOT's connection-friendly rules let developers queue cheaply, so the 410 GW figure measures appetite, not committed demand. The transformer book measures what can actually be fed. When requests run at 410 GW and deliverable hardware runs at a fraction of that, the queue stops measuring intent and starts measuring who secured a slot.

Deep Analysis

In plain English

ERCOT is the company that runs the electricity grid for most of Texas. It told state lawmakers that companies have put in requests to connect 410 gigawatts of new load, almost all of it data centres. To put that in perspective, the entire state only uses about 85 gigawatts at its peak. The problem is that the equipment needed to handle all those connections, called large power transformers, now takes up to four years to build and deliver. So even if ERCOT approved every request tomorrow, most of them could not actually receive power until 2028 or later. The queue measures how many companies want to build; the transformer wait decides how many actually can.

Deep Analysis
Root Causes

ERCOT's connect-first interconnection design was built for predictable industrial load growth in a state whose regulatory philosophy favours market entry over prescreening. Applications require a study deposit of roughly $10,000 to $100,000 per MW, trivial against the $1bn-plus capital cost of a hyperscale campus. That entry price creates a queue that measures ambition and option-holding rather than committed demand, pushing the 410 GW figure far beyond any plausible build rate.

Separately, the large power transformer supply chain runs on a fundamentally different timescale from data-centre planning cycles. A 500 kV autotransformer requires roughly 14 months of lamination steel processing, nine months of core winding, and six months of factory testing before shipment.

The total 24-to-30-month manufacturing window cannot be compressed because the steel supplier and the transformer manufacturer are different firms. GE Vernova's Prolec acquisition adds $5bn of production capacity, but Prolec's Mexican plants must also tool up for the US specification transformers that ERCOT's grid requires. The supply constraint is structural over a five-year horizon, not a temporary backlog.

What could happen next?
  • Risk

    Transformer lead times of 128 weeks mean that a large share of the 410 GW queue cannot receive power before mid-2028 regardless of regulatory approval, creating capital-at-risk for developers who ordered hardware in advance of grid connection.

    Short term · Assessed
  • Consequence

    ERCOT's queue overhang will drive a secondary market in interconnection queue positions and transformer delivery slots as speculative entrants face deposit deadlines, rewarding operators with early-mover hardware contracts.

    Medium term · Suggested
  • Opportunity

    Jurisdictions with shorter transformer queues and cleaner grid-connection pathways, such as Finland's Fingrid or Arizona's APS, gain a supply-chain arbitrage advantage over ERCOT for near-term hyperscale builds.

    Short term · Suggested
First Reported In

Update #5 · Who pays when the grid bends for AI

ERCOT· 2 Jun 2026
Read original →
Different Perspectives
Chilean data-centre developers
Chilean data-centre developers
Seven projects, one linked to Google, asked SEA this month for rulings that they fall outside full environmental review; four declared diesel-storage volumes just under the review-triggering tonnage, mirroring the mechanism Alto Jahuel used in July. The clustering suggests the threshold is being engineered, not sized to need.
An Coimisiun Pleanala
An Coimisiun Pleanala
Ireland's planning appeals body refused the €1.5bn Killala data centre on 17 September, overturning Mayo County Council's 2025 grant for lack of a fixed grid-connection agreement and no corporate renewable power-purchase agreement. The ruling makes matched-power evidence, not planning consent alone, the deciding factor.
Housing Assembly and Foxglove
Housing Assembly and Foxglove
The two groups' 6 August appeal, filed through the Legal Resources Centre, kept Cape Town's approval of Equinix's data centre suspended through this window over missing water, emissions, noise and diesel-generator data. Deputy Mayor Eddie Andrews confirmed on 20-21 September that the suspension holds.
Brazil (President Lula, signing Redata)
Brazil (President Lula, signing Redata)
Lula signed Lei 15.504 on 15 September, creating the Redata tax programme and keeping the Senate's water cap with no veto, while Aneel authorised Scala's AI City to join the national grid from January 2028. Brazil is recruiting capacity other markets are now turning away.
Aragon regional government (Eva Valle)
Aragon regional government (Eva Valle)
Aragon's economy chief Eva Valle said on 11 September that Spain's draft decree, requiring 80% hourly-matched renewables via a 10-year power-purchase agreement, is unmeetable by any project and threatens Blackstone, Azora and Microsoft builds already under way. Aragon holds 3,600 MW of granted grid access against 108 MW built.
Texas Governor Greg Abbott
Texas Governor Greg Abbott
Abbott ordered TCEQ on 21 September to halt every pending data-centre permit until projects pay their own way and complete ERCOT and Texas Water Development Board audits. Texas built the country's most permissive data-centre market; freezing it signals even that market has hit its grid limit.