Data Centres: Boom and Backlash
4AUG

MISO's second grid emergency in July

2 min read
10:53UTC

MISO declared its second maximum-generation emergency of the month on 15 July as a heat dome drove demand to a 122 GW peak, five days before FERC's grid-adequacy filing deadline.

IndustryDeveloping
Key takeaway

MISO rationed power days before it had to certify to regulators that its supply was adequate.

MISO, the grid operator for 15 central US states, declared a maximum-generation emergency on 15 July, its second of the month, as a heat dome pushed demand to a 122 GW peak. A maximum-generation emergency calls on every available plant and asks large users to cut load, the last routine step before controlled blackouts.⁠1 The declaration landed five days before the 20 July deadline the Federal Energy Regulatory Commission (FERC), the US regulator for interstate power, set for its six regional transmission organisations (RTOs) to file generation-adequacy reports.

FERC ordered those reports in place of a binding connection rule, and MISO's own figures show why the paperwork lags the weather. Data-centre load in its footprint has grown at a 43% compound annual growth rate (load CAGR, the yearly rate at which demand compounds) since 2020. The operator forecasts a 163 GW peak by 2035; it already touched 122 GW in a single July heat wave, so that forecast stacks another 41 GW on a grid that is rationing supply today.

The adequacy report describes supply on paper the same week the operator was cutting it in practice. That is the contradiction the FERC docket exists to interrogate, and MISO has now written it into the record twice in one month.

Deep Analysis

In plain English

MISO runs the electricity grid across 15 US states in the middle of the country. On 15 July, a heat wave pushed demand so high, 122 gigawatts at the peak, that MISO had to declare an emergency for the second time that month, meaning it may need to ask big power users to cut back to keep the lights on everywhere else. A big part of the extra demand is data centres, which have grown their electricity use by 43% a year since 2020 within MISO's territory. Five days later, the US grid regulator FERC (Federal Energy Regulatory Commission) was due a report from MISO and five other grid operators explaining how they plan to keep up.

Deep Analysis
Root Causes

MISO's 43% compound annual growth rate in data-centre load since 2020 has outpaced the multi-year lead times for new gas turbines and transmission build-out, so the grid operator is absorbing demand growth faster than physical generation capacity can be added.

The 20 July FERC adequacy-report deadline lands five days after this emergency, giving MISO live evidence of exactly the stress its report is meant to describe, rather than a hypothetical scenario regulators asked it to model.

What could happen next?
  • Risk

    A second maximum-generation emergency in one month raises the chance MISO invokes involuntary load-shedding before the FERC-mandated tariff reforms, due around 17 August, take effect.

  • Meaning

    MISO's 122 GW peak and 43% data-centre CAGR give the 20 July adequacy filing concrete numbers to reconcile against, rather than a hypothetical stress test.

First Reported In

Update #11 · Pipeline vetoed, campus keeps building

RTO Insider· 25 Jul 2026
Read original →
Different Perspectives
Chilean data-centre developers
Chilean data-centre developers
Seven projects, one linked to Google, asked SEA this month for rulings that they fall outside full environmental review; four declared diesel-storage volumes just under the review-triggering tonnage, mirroring the mechanism Alto Jahuel used in July. The clustering suggests the threshold is being engineered, not sized to need.
An Coimisiun Pleanala
An Coimisiun Pleanala
Ireland's planning appeals body refused the €1.5bn Killala data centre on 17 September, overturning Mayo County Council's 2025 grant for lack of a fixed grid-connection agreement and no corporate renewable power-purchase agreement. The ruling makes matched-power evidence, not planning consent alone, the deciding factor.
Housing Assembly and Foxglove
Housing Assembly and Foxglove
The two groups' 6 August appeal, filed through the Legal Resources Centre, kept Cape Town's approval of Equinix's data centre suspended through this window over missing water, emissions, noise and diesel-generator data. Deputy Mayor Eddie Andrews confirmed on 20-21 September that the suspension holds.
Brazil (President Lula, signing Redata)
Brazil (President Lula, signing Redata)
Lula signed Lei 15.504 on 15 September, creating the Redata tax programme and keeping the Senate's water cap with no veto, while Aneel authorised Scala's AI City to join the national grid from January 2028. Brazil is recruiting capacity other markets are now turning away.
Aragon regional government (Eva Valle)
Aragon regional government (Eva Valle)
Aragon's economy chief Eva Valle said on 11 September that Spain's draft decree, requiring 80% hourly-matched renewables via a 10-year power-purchase agreement, is unmeetable by any project and threatens Blackstone, Azora and Microsoft builds already under way. Aragon holds 3,600 MW of granted grid access against 108 MW built.
Texas Governor Greg Abbott
Texas Governor Greg Abbott
Abbott ordered TCEQ on 21 September to halt every pending data-centre permit until projects pay their own way and complete ERCOT and Texas Water Development Board audits. Texas built the country's most permissive data-centre market; freezing it signals even that market has hit its grid limit.