As of November 2026, Sara Aagesen is the minister behind Spain's data-centre decree, in force since 22 November, which makes new sites of 10 MW or more match 80% of their power with renewables every hour.
Last refreshed: 26 November 2026 · Appears in 1 active topic
Aagesen says the decree saves €5,000m a year; will it survive Spain's election?
Timeline for Sara Aagesen
Spain sets hourly test for data centres
Data Centres: Boom and BacklashBackground
Sara Aagesen is Spain's vice-president and minister for the ecological transition. Energy and climate policy sit with her department, from renewables to the rules for connecting large new users to the grid.
Data centres became a defining file for her in November 2026. The decree she defends ties every new site of 10 MW or more to hourly renewable supply, and it appeared in the official gazette on 21 November. Tech firms, builders and utilities have attacked it as unworkable.
The election on 29 November decides whether her rule lasts. The Partido Popular has pledged to throw it out and write its own, which would put Spain's approach to data-centre power back on the table within weeks of its start.
Her hourly renewables test faces repeal
Spain's Cabinet signed off the royal decree on data centres on 20 November 2026, and it took effect two days later as Real Decreto 1032/2026. Government sources said the final text barely changed from the draft the Council of State reviewed in late October. At its core is an hourly test: every new site of 10 MW or more has to meet 80% of its demand from renewables each hour, or else agree to disconnection whenever the grid is under strain.
A royal decree needs no vote in Parliament, which leaves Aagesen's rule open to reversal. The Partido Popular has pledged repeal, with Spain voting on 29 November 2026. A decree can be undone the way it was made: the 2015 solar tax was scrapped by the next government's decree in 2018.
What did Sara Aagesen say about Spain's data-centre decree?
What does Spain's data-centre decree require?