West Texas border city of about 680,000 people; site of Meta's $10bn data centre.

Meta raised its El Paso data-centre plan to 1 GW and more than $10bn on 26 March 2026. The 366 MW McCloud gas plant proposed to power it won a recommendation to approve on 24 September but still lacks a final state order.

Last refreshed: 1 October 2026 · Appears in 1 active topic

Timeline for El Paso

#4 18 May
#1 1 Mar

xAI wins 41 gas turbines for Colossus

Data Centres: Boom and Backlash
View full timeline →

Background

El Paso is a city of about 680,000 people on the US-Mexico border in far West Texas, facing Ciudad Juárez across the Rio Grande, and the seat of El Paso County. Its economy rests on cross-border trade, the military presence at Fort Bliss and a growing industrial base.

Unlike most of Texas, El Paso is not on the ERCOT grid; its utility, El Paso Electric, belongs to the Western Interconnection. That difference shapes how large power users such as Meta's data centre are supplied.

The county also appears in national election litigation. It was among the parties affected when Judge Amir Ali struck down FEMA's election conditions on counterterrorism grants on 28 September 2026.

Key Issues
Data centre power

Meta's El Paso power plant awaits approval

Meta raised its El Paso data-centre site to 1 GW and more than $10bn of investment on 26 March 2026, one of the largest industrial commitments the city has seen. Its power is meant to come from McCloud, a 366 MW gas plant that El Paso Electric wants to build for the site.

That plant is not yet approved. An administrative law judge recommended approval on 24 September, but the Public Utility Commission of Texas has issued no final order. The city itself opposed the plant on 18 June. The proposal fits a wider 2026 turn towards dedicated gas generation for AI sites, from xAI's turbines in Memphis onwards. For El Paso it would mean a new gas plant and fresh demand on water in an arid region.

Common Questions
Does Meta have a data centre in El Paso?
Yes. Meta broke ground in October 2025, and in March 2026 said the site would grow to 1 GW with more than $10bn of investment. It is due to run on a 366 MW gas plant that El Paso Electric has asked Texas regulators to approve.Source: Meta; Texas Tribune
Is El Paso on the ERCOT grid?
No. El Paso Electric is part of the Western Interconnection, which links El Paso to New Mexico and the western US, not to the ERCOT grid that serves most of Texas.Source: El Paso Electric system expansion plan
Why is the El Paso data centre gas plant controversial?
Residents and the City of El Paso fear higher power bills, worse air pollution and a setback for renewables. The city filed testimony in June 2026 asking regulators to deny the plant.Source: City of El Paso; Texas Tribune
How many people live in El Paso, Texas?
About 682,000 in July 2024 by Census Bureau estimate, the sixth largest city in Texas.Source: US Census Bureau