Skip to content
Welcome, thoughtbot's Giant Robots listeners!Start here
Russia-Ukraine War 2026
22OCT

France-Germany May power spread doubles record

4 min read
19:10UTC

France May-26 baseload settled at €21.80/MWh on 28 April against Germany at €77.55/MWh, a €55.75 spread that more than doubles Kpler's January 2025 record on the same calendar product.

ConflictAssessed
Key takeaway

The spread closes when Flamanville-3 starts its overhaul in September; until then interconnector capacity caps any earlier compression.

France May-26 baseload power settled at €21.80/MWh on Tuesday 28 April, against Germany May-26 baseload at €77.55/MWh⁠1. The €55.75/MWh spread is more than double Kpler's January 2025 record of €27.50 on the same calendar product, the highest forward gap between the two grids that the market has recorded.

EDF's March nuclear output ran at the highest level since 2019 and is still suppressing French forward Continental power into Q2. Germany's May-26 baseload is clearing on a gas-dominated merit order anchored to TTF at around €44/MWh; France's is clearing on a fleet of pressurised water reactors running near nameplate. The Italy-France day-ahead spread hit €153/MWh on 26 April on the same Continental nuclear-surplus dynamic at the cash level. Forward markets have absorbed the May-26 print over a week of trading without significant compression.

France-Germany cross-border physical interconnector capacity runs at roughly 4.8 GW under day-ahead market coupling, the structural bottleneck the headline does not show. Even at full nominal allocation, the cable cannot transfer enough French nuclear surplus to clear into German prices without merit-order shifts in Germany itself. The arbitrage cannot fully clear inside the physical network, so the financial spread persists. For French-sited industrial offtakers, that translates into roughly €56,000 of monthly hedge advantage per MW of load against southern-Germany peers, with knock-on effects on cross-border manufacturing competitiveness in chemicals and metals through Q2-Q3.

The window has a defined close. Flamanville-3, EDF's newest reactor, enters its twelve-month overhaul in September 2026, removing roughly 1.6 GW of French nuclear at the heating-season cusp. Forward strips that lean on French nuclear past Q3 are pricing through the September calendar, so the spread compression should land before the heating-season buyers do. RTE and CRE auction signals on cross-border interconnector allocation through May become the test of whether regulatory remedy is in scope before the physical fleet shift forces it.

Deep Analysis

In plain English

Wholesale electricity for May 2026 costs around €22 per megawatt-hour in France and €78 in Germany. France has cheap power because its nuclear plants are running flat-out, producing far more electricity than France needs. Germany relies heavily on gas-fired power plants; at €44/MWh TTF, that pushes German clearing prices well above €70/MWh. The cable connections between the two countries can't carry enough cheap French electricity east to bring German prices down. This gap is good news for French factories, which pay far less for electricity than their German competitors. It closes in September, when France's newest nuclear reactor goes into a planned overhaul for a year, and France will have less electricity to export.

What could happen next?
  • Consequence

    German-sited chemicals and metals producers face monthly hedge-cost disadvantages of tens of millions of euros versus French peers through Q2-Q3 2026, amplifying industrial competitiveness pressure ahead of autumn EU energy policy review.

  • Risk

    Forward sellers of French power for the period after September 2026 are pricing a 1.6 GW nuclear buffer that Flamanville-3's overhaul removes; if autumn demand is cold, French forward prices may reprice sharply upward as the overhaul start nears.

First Reported In

Update #6 · REMIT II live; storage instrument absent

Prestige Business Solutions· 29 Apr 2026
Read original →
Causes and effects
This Event
France-Germany May power spread doubles record
EDF's nuclear surplus is suppressing French forward power below half of German clearing prices, and the cables between the two grids cannot move enough French electricity east to close the gap.
Different Perspectives
South Korean foreign ministry
South Korean foreign ministry
Seoul said on 20 October it will withdraw some Kyiv embassy staff, citing no constructive steps from Kyiv since it recalled its ambassador over the disclosure of two North Korean prisoners. A chargé d'affaires and consular staff stay, and Seoul says its aid continues.
Alexander Lukashenko
Alexander Lukashenko
Lukashenko said on 22 October that talks with the US show progress despite problems, which he said were highlighted with the exchange of political prisoners for the lifting of sanctions. He said Minsk keeps its promises and wants the US to deliver its side in full.
Moldovan government (Daniella Misail-Nichitin)
Moldovan government (Daniella Misail-Nichitin)
Moldova has pulled its border guards and customs officers from four crossings on Ukrainian soil after Russian strikes near the border. Interior Minister Daniella Misail-Nichitin said Chisinau is weighing moving Ukrainian checkpoints onto Moldovan territory.
Péter Magyar
Péter Magyar
Magyar told RTL that Ukrainian maize may cross Hungary in sealed trains bound for Western Europe. He set one condition: the cargo must only transit the country.
Donald Tusk
Donald Tusk
Tusk said Warsaw would seek an explanation from Kyiv for the drone's route across Poland. He said Poland allows no operations over its territory without its explicit consent.
Mindaugas Sinkevičius
Mindaugas Sinkevičius
Lithuania's prime minister said the Ukrainian drone that exploded in Pasvalys district on 18 October carried explosives and entered from Poland through the Schengen zone. Earlier drones over Lithuania had come from Belarus, not through allied airspace.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.