France May-26 baseload settled at EUR 21.80/MWh on 28 April against Germany at EUR 77.55/MWh, a EUR 55.75 spread that more than doubles Kpler's January 2025 record on the same calendar product.

EconomicAssessed
Key takeaway

The spread closes when Flamanville-3 starts its overhaul in September; until then interconnector capacity caps any earlier compression.

France May-26 baseload power settled at EUR 21.80/MWh on Tuesday 28 April, against Germany May-26 baseload at EUR 77.55/MWh 1. The EUR 55.75/MWh spread is more than double Kpler's January 2025 record of EUR 27.50 on the same calendar product, the highest forward gap between the two grids that the market has recorded.

EDF's March nuclear output ran at the highest level since 2019 and is still suppressing French forward Continental power into Q2. Germany's May-26 baseload is clearing on a gas-dominated merit order anchored to TTF at around EUR 44/MWh; France's is clearing on a fleet of pressurised water reactors running near nameplate. The Italy-France day-ahead spread hit EUR 153/MWh on 26 April on the same Continental nuclear-surplus dynamic at the cash level. Forward markets have absorbed the May-26 print over a week of trading without significant compression.

France-Germany cross-border physical interconnector capacity runs at roughly 4.8 GW under day-ahead market coupling, the structural bottleneck the headline does not show. Even at full nominal allocation, the cable cannot transfer enough French nuclear surplus to clear into German prices without merit-order shifts in Germany itself. The arbitrage cannot fully clear inside the physical network, so the financial spread persists. For French-sited industrial offtakers, that translates into roughly EUR 56,000 of monthly hedge advantage per MW of load against southern-Germany peers, with knock-on effects on cross-border manufacturing competitiveness in chemicals and metals through Q2-Q3.

The window has a defined close. Flamanville-3, EDF's newest reactor, enters its twelve-month overhaul in September 2026 , removing roughly 1.6 GW of French nuclear at the heating-season cusp. Forward strips that lean on French nuclear past Q3 are pricing through the September calendar, so the spread compression should land before the heating-season buyers do. RTE and CRE auction signals on cross-border interconnector allocation through May become the test of whether regulatory remedy is in scope before the physical fleet shift forces it.

Deep Analysis

In plain English

Wholesale electricity for May 2026 costs around EUR 22 per megawatt-hour in France and EUR 78 in Germany. France has cheap power because its nuclear plants are running flat-out, producing far more electricity than France needs. Germany relies heavily on gas-fired power plants; at EUR 44/MWh TTF, that pushes German clearing prices well above EUR 70/MWh. The cable connections between the two countries can't carry enough cheap French electricity east to bring German prices down. This gap is good news for French factories, which pay far less for electricity than their German competitors. It closes in September, when France's newest nuclear reactor goes into a planned overhaul for a year, and France will have less electricity to export.

What could happen next?
  • Consequence

    German-sited chemicals and metals producers face monthly hedge-cost disadvantages of tens of millions of euros versus French peers through Q2-Q3 2026, amplifying industrial competitiveness pressure ahead of autumn EU energy policy review.

  • Risk

    Forward sellers of French power for the period after September 2026 are pricing a 1.6 GW nuclear buffer that Flamanville-3's overhaul removes; if autumn demand is cold, French forward prices may reprice sharply upward as the overhaul start nears.

First Reported In

Update #6 · REMIT II live; storage instrument absent

Prestige Business Solutions· 29 Apr 2026
Read original
Causes and effects
This Event
France-Germany May power spread doubles record
EDF's nuclear surplus is suppressing French forward power below half of German clearing prices, and the cables between the two grids cannot move enough French electricity east to close the gap.
Different Perspectives
LNG spreads desk
LNG spreads desk
The JKM-TTF arb flipped to a TTF premium of roughly USD 0.6/MMBtu on 15 July, the first time this cycle Europe has outbid Asia, yet no Atlantic cargo has rerouted west. Until a cargo actually moves, the desk reads the Hormuz premium as unconfirmed and the EUR 55 print as vulnerable to a fast reversal.
United States
United States
Washington reimposed a blockade on Iranian ports and a 20% Strait of Hormuz cargo toll on 13 July, driving TTF's 9% two-session rally to EUR 54.995/MWh. The posture is again setting Europe's gas benchmark by sentiment rather than by any confirmed change in cargo flows.
EDF
EDF
EDF slipped the Bugey 3, Golfech 2 and Chooz 2 restarts to 19, 22 and 25 July, pushing all three past the 20 July Bugey heat exemption, after river-cooling limits on the Rhone, Garonne and Meuse forced the cuts. The same thermal ceiling has capped the fleet in every major heatwave since 2003, and this cycle is no exception.
German power desk
German power desk
German day-ahead power climbed from EUR 126 to EUR 156/MWh over 14-16 July as the heat dome held, flipping the clean spark spread positive for the first time since 14 July. Gas-for-power demand is now back in competition with mandate storage injection right as the injection margin itself is thinning.
EU carbon and storage regulators
EU carbon and storage regulators
EUA carbon broke EUR 81/tonne on 13 July as the ETS Market Stability Reserve's scheduled withdrawals met fresh fuel-switching demand from France's nuclear curtailment. Brussels' mandatory storage-fill rule kept German and French injection running regardless of the TTF swings, the mechanism working as designed four years after the 2022 shock.
Equinor
Equinor
Equinor returned its Asgard field from maintenance on 11 July, lifting Gassco's exit nominations to 319.8 mcm/day just as TTF round-tripped on Hormuz risk. The restart gave Norway spare pipeline capacity to help Europe absorb the gas rally without drawing down storage, reinforcing its role as the post-2022 swing supplier.