The Record
Data Centres: Boom and Backlash
What we told you to watch, what each side claimed, and what we got wrong. Every verdict shows its evidence.
Happened 2 · Unresolved 1 · Open 75 · Corrections 132
What we told you to watch
Happened · 2
Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.
From the 8 Sept briefing · Judged 22 Oct 2026
SEA's Alto Jahuel case file is available and was checked.
“SEA's resolution specifies about 990 tonnes of diesel.”
Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.
From the 8 Sept briefing · Judged 22 Oct 2026
CRU approved MPID 345 on 22 September 2026.
“CRU approved MPID 345 on 22 September 2026.”
Unresolved · 1
NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .
From the 24 Sept briefing · Judged 22 Oct 2026
Final ballot passed; Board adoption and FERC filing remain pending.
“The standards passed final ballot and advance to Board adoption.”
Still open · 75
Show the 10 most recentWhether the county-level moratorium wave forces a statewide response in Indiana
From the 7 Jul briefing
Whether Chevron takes a final investment decision on Project Kilby by the end of 2026, or the GE Vernova turbine queue pushes first power past 2028.
From the 28 Jun briefing
Whether FERC's six grid operators meet the 17 August show-cause deadline, or seek extensions that push any binding rule deep into 2027.
From the 28 Jun briefing · Deadline: 17 August
Whether another state copies Virginia's behind-the-meter tax now that one jurisdiction has a working model.
From the 28 Jun briefing
Whether Texas locks the Batch Zero cohort before its 438 GW queue grows enough to make the autumn 2027 plan obsolete on arrival.
From the 28 Jun briefing
Whether Virginia's 22 June Senate session breaks the exemption deadlock before the 30 June deadline, and whether the Lucas generator fee survives into the final budget or dies as a negotiating gambit.
From the 17 Jun briefing · Deadline: 22 June
Whether the Oregon PUC holds PGE's 29% large-load rise at its 7 July decision, or trims the figure and reopens the cost-attribution framework.
From the 17 Jun briefing · Deadline: 7 July
Whether Virginia DEQ attaches any PFAS testing condition to Amazon's Lake Anna discharge permit, which the 9 June hearing left undecided.
From the 17 Jun briefing · Deadline: 9 June
Whether FERC issues the RM26-4-000 interconnection rule by end-June or lets its own deadline pass.
From the 17 Jun briefing
Whether the Virginia Department of Environmental Quality (DEQ) attaches any PFAS (per- and polyfluoroalkyl substances, the persistent 'forever chemicals') testing condition when it finally rules on Amazon's 280,000-gallon-a-day Sedges Creek discharge into Lake Anna; the 9 June hearing produced objections but no decision.
From the 10 Jun briefing · Deadline: 9 June
Whether Virginia's 18 June special session breaks the $1.9bn tax-exemption deadlock before the 30 June fiscal deadline, with the Senate demanding full elimination and the House insisting on environmental conditions.
From the 10 Jun briefing · Deadline: 18 June
Whether FERC issues its RM26-4-000 large-load interconnection rule by end of June, or lets the self-imposed deadline pass.
From the 10 Jun briefing · Deadline: end of June
Whether any PJM-territory state publishes a cost-allocation framework before the September backstop procurement, or whether costs keep drifting to households by default.
From the 10 Jun briefing
Whether any PJM-territory state publishes a data-centre cost-allocation framework before the September Reliability Backstop Procurement, or lets the costs default to ratepayers.
From the 2 Jun briefing
Whether a Texas court grants RCM Hill's injunction against the Hill County moratorium, the first test of a Fifth Amendment taking claim against a US data-centre pause.
From the 2 Jun briefing
Whether Virginia DEQ approves Amazon's Sedges Creek permit after the 9 June hearing, and whether it adds any PFAS testing condition.
From the 2 Jun briefing · Deadline: 9 June
Whether Virginia's 18 June special session resolves the data-centre tax exemption or triggers a partial state shutdown by 30 June.
From the 2 Jun briefing · Deadline: 18 June
Whether FERC settles the RM26-4-000 permanent co-located-load rule by its end-June deadline, and whether it shields BTM generation or confirms its new role as interruptible reserve.
From the 26 May briefing
The Virginia budget resolution and whether any abatement cut applies retroactively to commitments already made.
From the 26 May briefing
Whether a third DOE Section 202(c) curtailment order lands during the summer peak, turning two orders into a settled pattern.
From the 26 May briefing
What each side claimed
Claims are what a named side said at the time. We record them as said and judge them only against later evidence.
No claims recorded yet.
What we got wrong
- SignificantCorrected 22 Oct 2026We said
Existing data centres in Seattle keep their current connections and can expand under pre-moratorium rules. Only new proposals above 20 MVA are blocked.
What was trueExisting data centres can keep operating. An expansion exemption permits at most another 20 MVA at eligible existing facilities; larger expansions also face the pause.
- SignificantCorrected 22 Oct 2026We said
voted unanimously on 9 and 10 June to stop
What was truevoted unanimously on 9 June, with the mayor signing on 11 June, to stop
- SignificantCorrected 22 Oct 2026We said
The ordinance exempts Seattle's existing data centres, which may keep expanding under current rules, so the freeze bites only on new arrivals.
What was trueQualifying operating facilities can continue operating. Their expansion exemption is limited to an additional **20 MVA**, so larger expansions also fall under the moratorium.
- SignificantCorrected 22 Oct 2026We said
making the freeze legally binding rather than provisional
What was truewith the ordinance taking effect when the mayor signed on **11 June**
- SignificantCorrected 22 Oct 2026We said
voted **9 to 0** on **9 and 10 June** to enact
What was truevoted **9 to 0** on **9 June** to approve
- SignificantCorrected 22 Oct 2026We said
voted 9 to 0 on 9 and 10 June to enact
What was truevoted 9 to 0 on 9 June to approve
- SignificantCorrected 22 Oct 2026We said
Seattle's City Council voted 9-0 on 9 and 10 June. The vote made its 365-day moratorium legally binding on new loads above 20 MVA
What was trueSeattle's City Council approved its 365-day moratorium 9-0 on 9 June. It took effect with the mayor's signature on 11 June and applies to defined data centres above 20 MVA
- SignificantCorrected 22 Oct 2026We said
Existing data centres are exempt and may expand under current rules.
What was trueOperating facilities may continue, but the expansion exemption is limited to an additional 20 MVA; larger expansions are subject to the moratorium.
- SignificantCorrected 22 Oct 2026We said
Seattle's City Council voted 9 to 0 on 9 and 10 June to enact the 365-day moratorium it had introduced on 30 April, making the freeze legally binding.
What was trueSeattle's City Council approved the proposed 365-day moratorium by 9 votes to 0 on 9 June. The ordinance took effect with the mayor's signature on 11 June.
- MinorCorrected 22 Oct 2026We said
The CRU decision text had not been checked.
What was trueCRU2026145 and CRU2026145c confirm the scope, date and derogation route.
- MinorCorrected 22 Oct 2026We said
All non-compliant data centres must seek a derogation.
What was trueThe derogation route applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
MPID 345 requires large users to ride through voltage dips.
What was trueMPID 345 applies to transmission-connected demand facilities.
- MinorCorrected 22 Oct 2026We said
All non-compliant data centres must seek a derogation.
What was trueThe derogation route applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
MPID 345 requires large users to ride through voltage dips.
What was trueMPID 345 applies to transmission-connected demand facilities.
- MinorCorrected 22 Oct 2026We said
The exact start date lacked primary confirmation.
What was trueCRU's approval letter confirms the effective date as 27 October 2026.
- MinorCorrected 22 Oct 2026We said
All non-compliant sites must seek an exemption.
What was trueOnly sites covered by MPID 345 need a derogation.
- MinorCorrected 22 Oct 2026We said
MPID 345 applies to large electricity users generally.
What was trueMPID 345 applies to transmission-connected demand facilities.
- MinorCorrected 22 Oct 2026We said
All Irish data centres need an exemption if they cannot comply.
What was trueMPID 345 applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
All non-compliant data centres must seek an exemption.
What was trueThe derogation route applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
MPID 345 requires large users to ride through voltage dips.
What was trueMPID 345 applies to transmission-connected demand facilities.