The Record
Data Centres: Boom and Backlash
What we told you to watch, what each side claimed, and what we got wrong. Every verdict shows its evidence.
Happened 2 · Unresolved 1 · Open 75 · Corrections 132
What we told you to watch
Happened · 2
Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.
From the 8 Sept briefing · Judged 22 Oct 2026
SEA's Alto Jahuel case file is available and was checked.
“SEA's resolution specifies about 990 tonnes of diesel.”
Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.
From the 8 Sept briefing · Judged 22 Oct 2026
CRU approved MPID 345 on 22 September 2026.
“CRU approved MPID 345 on 22 September 2026.”
Unresolved · 1
NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .
From the 24 Sept briefing · Judged 22 Oct 2026
Final ballot passed; Board adoption and FERC filing remain pending.
“The standards passed final ballot and advance to Board adoption.”
Still open · 75
Show the 10 most recentWhether the county-level moratorium wave forces a statewide response in Indiana
From the 7 Jul briefing
Whether Chevron takes a final investment decision on Project Kilby by the end of 2026, or the GE Vernova turbine queue pushes first power past 2028.
From the 28 Jun briefing
Whether FERC's six grid operators meet the 17 August show-cause deadline, or seek extensions that push any binding rule deep into 2027.
From the 28 Jun briefing · Deadline: 17 August
Whether another state copies Virginia's behind-the-meter tax now that one jurisdiction has a working model.
From the 28 Jun briefing
Whether Texas locks the Batch Zero cohort before its 438 GW queue grows enough to make the autumn 2027 plan obsolete on arrival.
From the 28 Jun briefing
Whether Virginia's 22 June Senate session breaks the exemption deadlock before the 30 June deadline, and whether the Lucas generator fee survives into the final budget or dies as a negotiating gambit.
From the 17 Jun briefing · Deadline: 22 June
Whether the Oregon PUC holds PGE's 29% large-load rise at its 7 July decision, or trims the figure and reopens the cost-attribution framework.
From the 17 Jun briefing · Deadline: 7 July
Whether Virginia DEQ attaches any PFAS testing condition to Amazon's Lake Anna discharge permit, which the 9 June hearing left undecided.
From the 17 Jun briefing · Deadline: 9 June
Whether FERC issues the RM26-4-000 interconnection rule by end-June or lets its own deadline pass.
From the 17 Jun briefing
Whether the Virginia Department of Environmental Quality (DEQ) attaches any PFAS (per- and polyfluoroalkyl substances, the persistent 'forever chemicals') testing condition when it finally rules on Amazon's 280,000-gallon-a-day Sedges Creek discharge into Lake Anna; the 9 June hearing produced objections but no decision.
From the 10 Jun briefing · Deadline: 9 June
Whether Virginia's 18 June special session breaks the $1.9bn tax-exemption deadlock before the 30 June fiscal deadline, with the Senate demanding full elimination and the House insisting on environmental conditions.
From the 10 Jun briefing · Deadline: 18 June
Whether FERC issues its RM26-4-000 large-load interconnection rule by end of June, or lets the self-imposed deadline pass.
From the 10 Jun briefing · Deadline: end of June
Whether any PJM-territory state publishes a cost-allocation framework before the September backstop procurement, or whether costs keep drifting to households by default.
From the 10 Jun briefing
Whether any PJM-territory state publishes a data-centre cost-allocation framework before the September Reliability Backstop Procurement, or lets the costs default to ratepayers.
From the 2 Jun briefing
Whether a Texas court grants RCM Hill's injunction against the Hill County moratorium, the first test of a Fifth Amendment taking claim against a US data-centre pause.
From the 2 Jun briefing
Whether Virginia DEQ approves Amazon's Sedges Creek permit after the 9 June hearing, and whether it adds any PFAS testing condition.
From the 2 Jun briefing · Deadline: 9 June
Whether Virginia's 18 June special session resolves the data-centre tax exemption or triggers a partial state shutdown by 30 June.
From the 2 Jun briefing · Deadline: 18 June
Whether FERC settles the RM26-4-000 permanent co-located-load rule by its end-June deadline, and whether it shields BTM generation or confirms its new role as interruptible reserve.
From the 26 May briefing
The Virginia budget resolution and whether any abatement cut applies retroactively to commitments already made.
From the 26 May briefing
Whether a third DOE Section 202(c) curtailment order lands during the summer peak, turning two orders into a settled pattern.
From the 26 May briefing
What each side claimed
Claims are what a named side said at the time. We record them as said and judge them only against later evidence.
No claims recorded yet.
What we got wrong
- MinorCorrected 16 Nov 2026We said
A Metropolitan Development Commission committee voted 10-3 on 13 July 2026 to recommend the moratorium.
What was trueThe City-County Council's Metropolitan and Economic Development Committee cast the 10-3 vote (WFYI, 13/07/2026).
- MinorCorrected 16 Nov 2026We said
Red Eléctrica de España entity page: majority state-owned via SEPI
What was trueSEPI holds 20% of parent Redeia (Redeia shareholder page); entity 5364 background and two FAQ answers corrected via enrichment on 16/11/2026
- SignificantCorrected 16 Nov 2026We said
Charlotte entity page: Bank of America Stadium was a 2026 FIFA World Cup host venue
What was trueCharlotte was not one of the 11 US host cities for the 2026 World Cup; entity 7588 background, definition, search terms and quick facts corrected via enrichment on 16/11/2026
- MinorCorrected 14 Nov 2026We said
The regional leaders argued that the pause reflects OpenAI's US-first prioritisation rather than UK dysfunction.
What was trueThe cited source gives their argument as the region keeping its AI Growth Zone status and being "open for business". The only analyst quoted, Professor Richard Whittle, called the pause a warning about the UK's AI-infrastructure model.
- MinorCorrected 14 Nov 2026We said
North East Mayor Kim McGuinness and Nscale chief executive Bjoern Norda rejected the framing of the OpenAI pause.
What was trueThe cited source (ResultSense via Prolific North, 23 April 2026) attributes the pushback to the North East Combined Authority, Dynamo North East and the North East Chamber of Commerce. It names neither McGuinness nor any Nscale executive. No person called Bjoern Norda can be found; Nscale's chief executive is Josh Payne.
- MinorCorrected 8 Nov 2026We said
internal process notes published in the body
What was truenotes not for readers
- MinorCorrected 8 Nov 2026We said
internal process notes published in the body
What was truenotes not for readers
- MinorCorrected 22 Oct 2026We said
Amazon Web Services was the Amazon subsidiary that bought the former George Washington University site.
What was trueAmazon Data Services bought the site; AWS appears in the update through event 6435's historical comparison.
- SignificantCorrected 22 Oct 2026We said
Voted 9-0 on 9-10 June to enact a 365-day moratorium on new loads above 20 MVA
What was trueApproved a 365-day moratorium on defined data centres above 20 MVA by 9-0 on 9 June; the mayor signed on 11 June
- SignificantCorrected 22 Oct 2026We said
Enacted the 365-day data-centre moratorium 9-0 on 9-10 June
What was trueApproved the 365-day data-centre moratorium 9-0 on 9 June; the mayor signed on 11 June
- SignificantCorrected 22 Oct 2026We said
Seattle's 365-day freeze arrived five days after the Maine override failed
What was trueSeattle's proposed 365-day freeze followed the Maine override defeat
- SignificantCorrected 22 Oct 2026We said
when Seattle froze
What was truewhen Seattle proposed its freeze
- SignificantCorrected 22 Oct 2026We said
and that process is now unavailable until at least **30 April 2027**.
What was truebut the April proposal had not yet enacted a year-long freeze.
- SignificantCorrected 22 Oct 2026We said
Seattle's city council voted to pause new large data centre projects for one year
What was trueSeattle councilmembers proposed pausing new large data centre projects for one year
- SignificantCorrected 22 Oct 2026We said
Seattle freezes data centres for a year
What was trueSeattle proposes a year-long data-centre freeze
- SignificantCorrected 22 Oct 2026We said
Seattle's moratorium exempts everything already connected.
What was trueSeattle's moratorium permits existing operations, but its expansion exemption is limited to an additional 20 MVA at eligible facilities.
- SignificantCorrected 22 Oct 2026We said
Seattle's City Council voted 9-0 on 9-10 June to make its 365-day moratorium legally binding on new loads above 20 MVA
What was trueSeattle's City Council approved its 365-day moratorium 9-0 on 9 June; it took effect with the mayor's signature on 11 June and covers defined data centres above 20 MVA
- SignificantCorrected 22 Oct 2026We said
The 9-0 ordinance exempts Seattle's existing data centres, which may keep expanding under current rules.
What was trueExisting facilities can keep operating, but the expansion exemption permits at most another **20 MVA** at eligible facilities.
- SignificantCorrected 22 Oct 2026We said
making the freeze binding rather than provisional
What was truewith the ordinance taking effect when the mayor signed on **11 June**
- SignificantCorrected 22 Oct 2026We said
voted **9 to 0** on **9 and 10 June** to enact
What was truevoted **9 to 0** on **9 June** to approve