Data Centres: Boom and Backlash
17JUN

PJM auction falls 6,623 MW short

2 min read
10:13UTC

PJM's 2027/28 capacity auction cleared 6,623 MW below its reserve target, forcing a supplemental procurement with a 21 July deadline as the largest US grid hunts for power it has already sold.

IndustryDeveloping
Key takeaway

PJM's 2027/28 auction came up 6,623 MW short, buying power years before the campuses driving demand connect.

PJM Interconnection, the largest US regional transmission organisation, cleared its 2027/28 capacity auction 6,623 MW below its reserve target, and set a 21 July deadline for supplemental procurement to close the gap. A capacity auction is where a grid operator buys commitments from power plants to be available years ahead; the reserve target is the cushion of supply above forecast peak demand it must secure.⁠1⁠2

A shortfall this far out means PJM is short of generation it has, in effect, already promised to deliver. It sharpens the question the operator's board put to 13 governors in May, warning that grid-reinforcement costs could fall on household bills unless states write cost-allocation rules first. Every megawatt the auction fails to clear now is one the supplemental round must buy at a premium, and the load driving the gap is data-centre demand that has not yet connected.

Deep Analysis

In plain English

PJM runs the electricity market for the largest US grid area, covering 13 states plus Washington DC. Its most recent auction, which lines up power supply for 2027 and 2028, came up 6,623 megawatts short of the reserve PJM wants to keep on hand as a safety margin, roughly enough to power several million homes. PJM now has until 21 July to buy extra power supply to help close that gap. The shortfall follows PJM's board asking the governors of all 13 states in its territory in May how to fairly split the rising costs data centres are adding to the grid.

What could happen next?
  • Risk

    Capacity-market clearing prices for the 2027/28 delivery year are likely to rise further given the confirmed 6,623 MW shortfall, adding to the cost-allocation dispute already before PJM's board and the 13 state governors.

First Reported In

Update #11 · Pipeline vetoed, campus keeps building

Foley Hoag· 25 Jul 2026
Read original →
Different Perspectives
Chilean data-centre developers
Chilean data-centre developers
Seven projects, one linked to Google, asked SEA this month for rulings that they fall outside full environmental review; four declared diesel-storage volumes just under the review-triggering tonnage, mirroring the mechanism Alto Jahuel used in July. The clustering suggests the threshold is being engineered, not sized to need.
An Coimisiun Pleanala
An Coimisiun Pleanala
Ireland's planning appeals body refused the €1.5bn Killala data centre on 17 September, overturning Mayo County Council's 2025 grant for lack of a fixed grid-connection agreement and no corporate renewable power-purchase agreement. The ruling makes matched-power evidence, not planning consent alone, the deciding factor.
Housing Assembly and Foxglove
Housing Assembly and Foxglove
The two groups' 6 August appeal, filed through the Legal Resources Centre, kept Cape Town's approval of Equinix's data centre suspended through this window over missing water, emissions, noise and diesel-generator data. Deputy Mayor Eddie Andrews confirmed on 20-21 September that the suspension holds.
Brazil (President Lula, signing Redata)
Brazil (President Lula, signing Redata)
Lula signed Lei 15.504 on 15 September, creating the Redata tax programme and keeping the Senate's water cap with no veto, while Aneel authorised Scala's AI City to join the national grid from January 2028. Brazil is recruiting capacity other markets are now turning away.
Aragon regional government (Eva Valle)
Aragon regional government (Eva Valle)
Aragon's economy chief Eva Valle said on 11 September that Spain's draft decree, requiring 80% hourly-matched renewables via a 10-year power-purchase agreement, is unmeetable by any project and threatens Blackstone, Azora and Microsoft builds already under way. Aragon holds 3,600 MW of granted grid access against 108 MW built.
Texas Governor Greg Abbott
Texas Governor Greg Abbott
Abbott ordered TCEQ on 21 September to halt every pending data-centre permit until projects pay their own way and complete ERCOT and Texas Water Development Board audits. Texas built the country's most permissive data-centre market; freezing it signals even that market has hit its grid limit.