An Coimisiun Pleanala, Ireland's national planning appeals body, refused a €1.5bn data centre at Killala, County Mayo, on 17 September, overturning Mayo County Council's 2025 grant1. The applicant, Mayo Data Hub, is backed by Avaio Digital.
The board found the developer had shown no fixed grid connection agreement and no proof that the grid could serve the site, RTE News reported. It also found the project had not shown it would meet the objectives of Ireland's Climate Action Plan 2025, citing the absence of any corporate PPA (power purchase agreement) with a renewable supplier.
Ireland's energy regulator, the Commission for Regulation of Utilities, had been consulting on grid-code obligations that EirGrid would impose on large demand sites such as data centres. Killala moves those tests forward to the planning stage. An Irish applicant now faces a demand for grid and power-purchase evidence at the planning stage, before any connection offer.