Data Centres: Boom and Backlash
2JUN

ERCOT large-load queue passes 225 GW

3 min read
10:42UTC

ERCOT disclosed in April that its large-load process has 225 GW of capacity in study, with over 70 per cent from data centres; West Texas operators want to convert 9.1 GW of crypto-mining brownfield to AI compute.

IndustryDeveloping
Key takeaway

ERCOT's process is overrun because every operator wanting out of FERC jurisdiction is routing through it.

ERCOT, the Texas grid operator, told an April 2026 state Senate hearing that more than 225 GW of large electricity loads are in formal interconnection study, with over 70 per cent from data centres. A further 137 unposted requests totalling roughly 140,000 MW would push the working total toward 380 GW if and when they hit the public queue chart. ERCOT received 225 new large-load requests during 2025 alone against an interconnection process designed to handle 40 to 50 at a time.

ERCOT is not synchronised with the Eastern or Western Interconnection, which means it falls outside FERC jurisdiction. Operators looking to escape the federal layer have begun routing capacity through West Texas already, and the 9.1 GW of crypto-mining brownfield infrastructure across the Midland-Abilene corridor is the brownfield route. Crypto sites already have grid connections, building shells, and cooling rated for high-density compute; converting that load class to AI inference and training is faster than greenfield construction by 18 to 24 months. xAI's 41 turbines at Memphis sit on the same behind-the-meter logic, but operators copying that play now have to find a turbine slot before they find a site, and the queue runs to 2031.

McKinsey has been contracted to deliver a short- and mid-term solutions framework for ERCOT, with a streamlined batch-study implementation expected to follow. The March 2026 Large Load Working Group meeting focused on flexible-interconnection models that allow loads to come online with curtailment commitments instead of full firm-capacity rights. The interaction with the FERC June order is straightforward: every operator who can route through ERCOT is doing so, every operator who cannot is waiting to see whether RM26-4-000 cuts the wait or extends it. The queue grows in either case, because the structural attractiveness of a non-FERC grid does not turn on a single rule cycle.

Deep Analysis

In plain English

ERCOT runs the Texas electricity grid, which operates independently from the rest of the US national grid. Companies wanting to connect large facilities to the Texas grid apply to ERCOT for permission. The queue currently holds more than 225,000 megawatts of applications waiting for approval, more than four times the total capacity Texas currently uses at peak. More than 70 per cent of those applications are from data centres. ERCOT hired McKinsey to work out how to process them faster. Meanwhile, companies in West Texas are trying a shortcut: convert existing Bitcoin mining facilities, which already have grid connections, into AI computing centres. This avoids the queue entirely because the electricity connection is already built.

First Reported In

Update #2 · Maine veto, Seattle freeze, $725bn capex

ERCOT· 6 May 2026
Read original
Different Perspectives
Singapore / IMDA
Singapore / IMDA
IMDA's Green Data Centre Roadmap releases 500 MW under non-negotiable PUE 1.3, liquid-cooling, and green-energy conditions set before construction, ending a seven-year freeze without triggering the consent or cost fights fragmenting three US regulatory fronts simultaneously.
US residential electricity ratepayers and community residents
US residential electricity ratepayers and community residents
Households in PJM's 13 states face grid-reinforcement costs defaulting to their bills if states miss the September deadline, while Lake Anna residents face a cooling-water permit that can clear Virginia law without any PFAS monitoring. Both costs are externalised at the regulatory stage and disputed only after the fact.
EdgeConneX in Italy (EU market)
EdgeConneX in Italy (EU market)
EdgeConneX committed €3bn to Italian data-centre capacity starting in 2026, routing capital to a jurisdiction where AI Act and NIS2 mandates create structural demand for EU-resident compute and the government actively attracts investment; Virginia's fiscal standoff and US moratoriums are redirecting pipeline offshore.
Enbridge and Baker Hughes (firmed-power and oilfield-services suppliers)
Enbridge and Baker Hughes (firmed-power and oilfield-services suppliers)
Enbridge committed $1.2bn to Wyoming solar-plus-storage for Meta and Baker Hughes redirected oilfield drilling capacity into enhanced geothermal in New Mexico; both companies are routing capital away from fossil infrastructure into data-centre power procurement at precisely the moment BTM gas became a federal curtailment target.
US federal regulators (DOE and FERC)
US federal regulators (DOE and FERC)
DOE reached for Section 202(c) twice in five months naming the same BTM load class, while FERC rejected PJM's bid to redefine the 20 MW co-located load threshold in April; together they have treated private data-centre generation as a dispatchable grid resource before the permanent RM26-4-000 rule settling its legal status has been written.
European energy regulators and climate advocates
European energy regulators and climate advocates
GE Vernova's 100 GW gas-turbine backlog, driven by AI data-centre demand, puts IEA net-zero pathways under pressure: 15-27 GW of onsite gas is forecast for US data centres by 2030. The Amazon Boardman $20.5m pollution settlement gives environmental litigation a financial template it previously lacked.