Skip to content
Briefings are running a touch slower this week while we rebuild the foundations.See roadmap
Data Centres: Boom and Backlash
16MAY

xAI wins 41 gas turbines for Colossus

4 min read
13:06UTC

xAI received approval in March 2026 for 41 natural gas turbines totalling 1.2 GW to power its Colossus complex; Meta's El Paso project will run on a 366 MW behind-the-meter gas array.

IndustryDeveloping
Key takeaway

xAI, Meta and Wonder Valley are committing decades of fossil generation behind the meter to bypass the grid queue.

xAI received approval in March 2026 for 41 natural gas turbines totalling 1.2 GW to power its Colossus data centre complex outside Memphis. 1 Meta's El Paso project will run on a 366 MW behind-the-meter (BTM) natural gas array. Kevin O'Leary's Wonder Valley campus in Alberta, announced at $70 billion, has a 7.5 GW bring-your-own-power (BYOP) gas plan attached.

"behind-the-meter" describes generation built on the customer's side of the grid connection, dispatched to serve the customer's load directly without selling into the wholesale market. "Bring-your-own-power" is the operator-led variant: a campus is sited specifically to host its own generation rather than wait for transmission upgrades. Both routes solve the same problem: years-long waits for new transmission interconnection. Both also commit the operator to a fossil-fuel asset that runs for decades. A combined-cycle gas turbine ordered today comes online late in this decade and is depreciated over a twenty- to thirty-year operating life.

Colossus is xAI's Memphis training cluster, the site that hit roughly 100,000 H100 GPUs in late 2024 and was reported at 200,000 by mid-2025. Its previous power supply attracted complaints from the Southern Environmental Law Center over Clean Air Act permitting on its existing turbines. The March 2026 approval is the formal regulatory consent for the larger 1.2 GW build-out. Meta's El Paso project sits inside ERCOT, the Texas grid that has explicitly relaxed large-load interconnection rules to attract data centre demand the rest of the US grid will not connect.

The BYOP build-out runs alongside hyperscaler net-zero commitments published to investors and ESG indices. The cooling-water and renewables work covered in their sustainability reports does not retire the gas plant the same operator just queued behind the meter. Wonder Valley's 7.5 GW would meet the entire peak demand of a mid-sized European country, attached to a single private campus. Whether this gas capacity ever runs at the contracted load factor depends on how fast renewable interconnection clears, but the contracts are being signed now, and turbine lead times mean the bet is locked in.

Deep Analysis

In plain English

Most buildings get their electricity from the public grid, the network of power stations and cables that delivers electricity to homes and businesses. Large data centres need so much power that getting connected to the grid can take three to five years. Behind-the-meter gas is a different approach: the operator builds its own gas-fired power stations on or next to the data centre site, generating electricity directly without ever connecting to the public grid. The gas comes from a pipeline; the turbines convert it to electricity on site. xAI, the AI company founded by Elon Musk, won approval for 41 of these turbines at its Colossus facility in Memphis, totalling 1.2 GW. Meta and Kevin O'Leary's planned Wonder Valley campus in Alberta are taking the same route. The advantage is speed: turbines can be delivered and installed in 18-24 months. The disadvantage is that they burn fossil fuel and emit carbon and local air pollutants.

Deep Analysis
Root Causes

Grid interconnection timelines in the US average three to five years for large industrial loads. AI data centres require power delivery on 12-18 month deployment cycles to remain competitive. The gap between what the grid can deliver and what operators require has made BTM gas economically rational even at the cost of higher per-MWh fuel prices, permitting complexity, and reputational risk.

The secondary cause is the GE Vernova backlog: gas turbines are deliverable within 18-24 months (subject to queue position), whereas new grid connections in congested areas are not. Equipment manufacturers have pulled forward delivery capacity that transmission planners cannot match.

What could happen next?
  • Consequence

    The IEA's 15-27 GW US onsite gas projection by 2030 is now on track to be achieved early: xAI alone accounts for 1.2 GW, Meta El Paso for 0.37 GW, and Wonder Valley (if built) for 7.5 GW.

    Medium term · Medium
  • Risk

    Memphis's minor modification permitting pathway for 41 turbines is now the subject of EPA regional scrutiny; if challenged successfully, it could invalidate the approval and strand capital already committed.

    Short term · Medium
  • Precedent

    Three major BTM gas commitments in a single quarter establishes BTM self-generation as the default model for AI campuses above 300 MW, which will shape utility planning and grid investment models for the next decade.

    Long term · High
First Reported In

Update #1 · Boom hits wall: grid says no, states freeze

Data Center Frontier· 26 Apr 2026
Read original
Different Perspectives
European energy regulators and climate advocates
European energy regulators and climate advocates
GE Vernova's 100 GW gas-turbine backlog, driven by AI data-centre demand, puts IEA net-zero pathways under pressure: 15-27 GW of onsite gas is forecast for US data centres by 2030. The Amazon Boardman $20.5m pollution settlement gives environmental litigation a financial template it previously lacked.
Irish Commission for Regulation of Utilities (CRU)
Irish Commission for Regulation of Utilities (CRU)
The CRU-compliant Pure DC behind-the-meter template gives operators a replicable European consent pathway outside the UK queue. Ireland's existing hyperscaler density and the CRU framework's behind-the-meter provisions make it the lowest-friction large-load jurisdiction in Europe for 2026 approvals.
Nordic operators (Equinix-CPP-atNorth, Aikido Technologies)
Nordic operators (Equinix-CPP-atNorth, Aikido Technologies)
Equinix's CPP-atNorth acquisition and Aikido's AO60DC floating-wind pilot at METCentre Norway offer hyperscalers a consented, low-carbon supply chain that bypasses both US moratorium risk and European grid queues. Norway's renewable surplus and Fingrid connection windows make the Nordic corridor the clearest alternative supply chain in the current environment.
G42 and Abu Dhabi sovereign funds
G42 and Abu Dhabi sovereign funds
G42 and Khazna are tracking Stargate UAE phase 1 for Q3 2026 commissioning with a sovereign anchor tenant. The model insulates the project from community opposition and planning litigation, making Abu Dhabi the furthest-advanced non-US build on the current verified green-light map.
UK Government and NESO
UK Government and NESO
NESO began issuing Gate 2 Phase 1 transmission connection offers this week against a 116 GW applications backlog, with electricity discounts and HV self-build rights attached. The UK is using grid access as an industrial-policy instrument to attract compute investment redirected from US jurisdictions with active moratoriums.
US hyperscalers and OpenAI
US hyperscalers and OpenAI
The four big hyperscalers raised collective 2026 guidance to ~$725bn while OpenAI compressed its own commitment by 57% to $600bn and pivoted to leased compute; the divergence shows capital allocation cycles running independently of AI developer demand, with hyperscalers betting that transformer-slot scarcity in 2027 is riskier than current community opposition.