Data Centres: Boom and Backlash
16MAY

ERCOT large-load queue passes 225 GW

3 min read
13:06UTC

ERCOT disclosed in April that its large-load process has 225 GW of capacity in study, with over 70 per cent from data centres; West Texas operators want to convert 9.1 GW of crypto-mining brownfield to AI compute.

IndustryDeveloping
Key takeaway

ERCOT's process is overrun because every operator wanting out of FERC jurisdiction is routing through it.

ERCOT, the Texas grid operator, told an April 2026 state Senate hearing that more than 225 GW of large electricity loads are in formal interconnection study, with over 70 per cent from data centres. A further 137 unposted requests totalling roughly 140,000 MW would push the working total toward 380 GW if and when they hit the public queue chart. ERCOT received 225 new large-load requests during 2025 alone against an interconnection process designed to handle 40 to 50 at a time.

ERCOT is not synchronised with the Eastern or Western Interconnection, which means it falls outside FERC jurisdiction. Operators looking to escape the federal layer have begun routing capacity through West Texas already, and the 9.1 GW of crypto-mining brownfield infrastructure across the Midland-Abilene corridor is the brownfield route. Crypto sites already have grid connections, building shells, and cooling rated for high-density compute; converting that load class to AI inference and training is faster than greenfield construction by 18 to 24 months. xAI's 41 turbines at Memphis sit on the same behind-the-meter logic, but operators copying that play now have to find a turbine slot before they find a site, and the queue runs to 2031.

McKinsey has been contracted to deliver a short- and mid-term solutions framework for ERCOT, with a streamlined batch-study implementation expected to follow. The March 2026 Large Load Working Group meeting focused on flexible-interconnection models that allow loads to come online with curtailment commitments instead of full firm-capacity rights. The interaction with the FERC June order is straightforward: every operator who can route through ERCOT is doing so, every operator who cannot is waiting to see whether RM26-4-000 cuts the wait or extends it. The queue grows in either case, because the structural attractiveness of a non-FERC grid does not turn on a single rule cycle.

Deep Analysis

In plain English

ERCOT runs the Texas electricity grid, which operates independently from the rest of the US national grid. Companies wanting to connect large facilities to the Texas grid apply to ERCOT for permission. The queue currently holds more than 225,000 megawatts of applications waiting for approval, more than four times the total capacity Texas currently uses at peak. More than 70 per cent of those applications are from data centres. ERCOT hired McKinsey to work out how to process them faster. Meanwhile, companies in West Texas are trying a shortcut: convert existing Bitcoin mining facilities, which already have grid connections, into AI computing centres. This avoids the queue entirely because the electricity connection is already built.

First Reported In

Update #2 · Maine veto, Seattle freeze, $725bn capex

ERCOT· 6 May 2026
Read original
Causes and effects
This Event
ERCOT large-load queue passes 225 GW
The Texas grid sits outside FERC jurisdiction; that exemption now drives every operator looking to escape federal interconnection rules into a queue designed for a tenth of current demand.
Different Perspectives
European energy regulators and climate advocates
European energy regulators and climate advocates
GE Vernova's 100 GW gas-turbine backlog, driven by AI data-centre demand, puts IEA net-zero pathways under pressure: 15-27 GW of onsite gas is forecast for US data centres by 2030. The Amazon Boardman $20.5m pollution settlement gives environmental litigation a financial template it previously lacked.
Irish Commission for Regulation of Utilities (CRU)
Irish Commission for Regulation of Utilities (CRU)
The CRU-compliant Pure DC behind-the-meter template gives operators a replicable European consent pathway outside the UK queue. Ireland's existing hyperscaler density and the CRU framework's behind-the-meter provisions make it the lowest-friction large-load jurisdiction in Europe for 2026 approvals.
Nordic operators (Equinix-CPP-atNorth, Aikido Technologies)
Nordic operators (Equinix-CPP-atNorth, Aikido Technologies)
Equinix's CPP-atNorth acquisition and Aikido's AO60DC floating-wind pilot at METCentre Norway offer hyperscalers a consented, low-carbon supply chain that bypasses both US moratorium risk and European grid queues. Norway's renewable surplus and Fingrid connection windows make the Nordic corridor the clearest alternative supply chain in the current environment.
G42 and Abu Dhabi sovereign funds
G42 and Abu Dhabi sovereign funds
G42 and Khazna are tracking Stargate UAE phase 1 for Q3 2026 commissioning with a sovereign anchor tenant. The model insulates the project from community opposition and planning litigation, making Abu Dhabi the furthest-advanced non-US build on the current verified green-light map.
UK Government and NESO
UK Government and NESO
NESO began issuing Gate 2 Phase 1 transmission connection offers this week against a 116 GW applications backlog, with electricity discounts and HV self-build rights attached. The UK is using grid access as an industrial-policy instrument to attract compute investment redirected from US jurisdictions with active moratoriums.
US hyperscalers and OpenAI
US hyperscalers and OpenAI
The four big hyperscalers raised collective 2026 guidance to ~$725bn while OpenAI compressed its own commitment by 57% to $600bn and pivoted to leased compute; the divergence shows capital allocation cycles running independently of AI developer demand, with hyperscalers betting that transformer-slot scarcity in 2027 is riskier than current community opposition.