Skip to content
Welcome, thoughtbot's Giant Robots listeners!Start here
Data Centres: Boom and Backlash
6MAY

FERC sets a 20 July adequacy deadline

2 min read
13:52UTC

FERC ordered its six regional grid operators to file generation-adequacy reports by 20 July, forcing them to show whether supply can keep pace with data-centre load growth.

IndustryAssessed
Key takeaway

FERC's 20 July reports will show whether US grids can meet the load data centres keep adding.

The Federal Energy Regulatory Commission (FERC), the US regulator for interstate power markets, has ordered its six regional transmission organisations (RTOs) to file generation-adequacy reports by 20 July under docket RM26-4-000.⁠1 The six, PJM, MISO, SPP, CAISO, ISO-NE and NYISO, run the grids that carry most US electricity; a generation-adequacy report is each operator's account of whether supply can meet forecast demand, data centres included.

The deadline follows FERC's decision on 18 June to issue Section 206 show-cause orders to the same six operators rather than write a binding large-load connection rule. That choice pushed any final standard to 2027, so the 20 July filings are the near-term measure of how each grid is coping while the rulemaking drags.

The reports will not by themselves connect or curtail a single campus. They set the evidentiary record FERC will lean on when it finally rules, and they arrive as RTO queues fill with gigawatts of data-centre demand that existing generation cannot yet serve.

Deep Analysis

In plain English

The US federal energy regulator, FERC, has told six of the country's biggest regional power grid operators, including the one covering Virginia and the Mid-Atlantic, to hand in reports on 20 July showing whether they will have enough electricity supply to meet demand, much of it from data centres. This is not a new rule itself, just the evidence-gathering stage. FERC chose this slower route in June rather than write a binding rule straight away, so any actual new requirement on how data centres connect to the grid is unlikely before 2027.

Deep Analysis
Root Causes

The 20 July deadline exists because FERC's own 18 June show-cause orders, issued to meet an end-June deadline it had set itself in April, asked PJM, MISO, SPP, CAISO, ISO-NE and NYISO to justify their large-load tariffs rather than propose a unified rule; adequacy reports are the first deliverable in that slower, evidence-gathering process, with show-cause responses not due until 17 August and public comment not closing until 16 September.

PJM already operates under the tightest version of this problem: it is the only one of the six that has twice used DOE's Section 202(c) emergency curtailment authority against backup-equipped data centres in 2026, so its adequacy report will land against a backdrop the other five RTOs do not share.

What could happen next?
  • Meaning

    FERC's evidence-first approach confirms no binding national large-load connection standard will exist before 2027, leaving states to keep legislating individually in the meantime.

First Reported In

Update #10 · New York freezes data centres by decree

FERC· 15 Jul 2026
Read original →
Different Perspectives
MUFG
MUFG
Mitsubishi UFJ (MUFG) and Morgan Stanley are preparing to sell a loan of about $4.5bn secured on the GPUs CoreWeave runs for Meta in Dalton, Georgia, with price talk of 7% to 7.5%, Bloomberg reported. Meta's contract is expected to win the loan investment-grade ratings, though CoreWeave is rated below investment grade and the loan has not priced.
CX Tech
CX Tech
CX Tech's £16.5bn, 1,000 MW plan for the former Chapelcross nuclear site has drawn more than 10,000 representations, the most Dumfries and Galloway's planners have received, BBC News reported. The company says the scheme could support up to 750 construction jobs and about 540 permanent posts; comments close on 29 November.
Nate Glubish, Alberta's technology and innovation minister
Nate Glubish, Alberta's technology and innovation minister
Glubish tabled Bill 42 on 18 November to ban power plants and data centres on Class 1 and 2 farmland and within 600 m of homes, a day after the regulator approved a 1,494 MW plant that fails both tests. The bill exempts projects already approved or under review, so the Indus plant stands.
NEXTDC's chairman and chief executive
NEXTDC's chairman and chief executive
After a second pay strike and a defeated spill on 20 November, NEXTDC's leaders said they are exploring a joint venture for the S4 Sydney campus and do not expect to raise shareholder capital for contracted capacity. They raised FY27 underlying EBITDA guidance to A$260m-A$275m, still excluding about A$140m tied to Melbourne's stalled M3 site.
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
The three groups argued in the High Court on 18 November that the CRU's data-centre connection framework breaches the 2015 Climate Act by ignoring carbon budgets, which the CRU denies. Judge Micheal O'Connell reserved judgment with no date, so the framework stands meanwhile.
South Korean data-centre industry groups
South Korean data-centre industry groups
Industry groups told Etnews on 13 November that tougher grid scoring for one sector alone is unfair, three days before the climate and energy ministry raised the capital-region pass mark to 75 from 70. Pending applications are judged on the new bar; the pilot assessed 28 capital-region projects worth 1.9 GW.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.