Data Centres: Boom and Backlash
18OCT

Quebec data centres face under-use fee

3 min read
13:11UTC

Hydro-Québec's proposed data-centre tariff, heard by Quebec's energy regulator from 1 to 9 October, would charge sites that use too little of their contracted demand as well as those that ramp up too fast.

IndustryAssessed
Key takeaway

Hydro-Québec wants Quebec data centres to pay for contracted power they leave unused.

A data centre in Quebec whose peak demand stays below 60% of its contracted forecast for 12 months would pay a premium of C$92.28 a kilowatt on the gap between that peak and the 60% mark, under the proposed tariff of Hydro-Québec, the province's state-owned utility⁠1. The Régie de l'énergie du Québec, the province's energy regulator, heard the case in public from 1 to 9 October, across six volumes of transcript in case R-4333-2026⁠2.

The proposed Tarif CD covers any data centre that commits to at least 5,000 kilowatts (5 MW), at C$32.70 a kilowatt of billed demand each month plus 8.71 cents a kilowatt-hour⁠3. For a 100 MW site running flat out, that comes to about C$9.6m a month, roughly 13 cents a kilowatt-hour. Power drawn in hours above 110% of a site's agreed ramp-up carries a 17.42-cent surcharge on top of the 8.71-cent rate, tripling the price of energy in those hours.

The under-use premium follows the same take-or-pay logic Malaysia's minister set out on 15 October: a developer that books more than it needs pays for the difference. Ontario is heading the same way: in August it opened consultation on a data-centre playbook built on full energy-cost recovery and no cash incentives. A ruling is unlikely before 2027, because Hydro-Québec's filing points to further sessions on 7 to 11 and 15 to 18 December. A joint intervener for large industrial consumers filed its own wording on 7 October for tariff article 5.52, the clause that defines which customers the rate covers.

Deep Analysis

In plain English

Hydro-Québec is the state-owned power company in Quebec, Canada. It sells electricity cheaply because most of it comes from large dams. It has proposed a special price list for data centres. They would pay for the peak power they need each month, plus a charge for the energy they use. If a data centre uses far less than it promised, it pays a penalty, because the company had to plan supply for it. The Régie de l'énergie, Quebec's energy regulator, must approve the plan first.

Deep Analysis
Root Causes

Since 2023 Quebec law has required ministerial approval before Hydro-Québec supplies a new load of 5 MW or more. The 5,000 kW floor in Tarif CD matches that threshold, so the tariff prices loads the government has already chosen to admit.

Hydro-Québec's surplus has shrunk as export contracts to New England and New York and domestic electrification claim more output. New supply from wind and new dams costs far more than the heritage pool, so a cheap flat tariff for data centres would transfer that cost to other customers.

Ramp-up forecasts are the weak point of any large-load contract. A site that over-forecasts makes the utility build or buy supply that sits idle, which is the risk the under-use premium targets.

What could happen next?
  • Consequence

    Developers without signed tenants face higher risk of paying for unused capacity in Quebec.

    Medium term · Assessed
  • Precedent

    A penalty for under-use alongside a surcharge for over-use may become a template for other hydro-rich grids.

    Long term · Suggested
  • Risk

    Industrial interveners may narrow the definition in article 5.52, changing which customers the rate covers.

    Short term · Reported
First Reported In

Update #16 · Malaysia bills data centres for idle grid

Régie de l'énergie du Québec· 18 Oct 2026
Read original →
Different Perspectives
Nexus Core Systems
Nexus Core Systems
Hired FiveNines Group, in a deal announced on 8 October, for early design, feasibility and permit work on a 20 MW AI data centre near Casablanca. It is the first named site of a planned 180 MW programme, still at concept design.
MC Digital Realty
MC Digital Realty
Began building the 24 MW KIX15 data centre in Osaka Prefecture on 7 October, due to open in the fourth quarter of 2028. The joint venture of Digital Realty and Mitsubishi Corporation says it will then run 10 data centres in Japan with about 220 MW of IT capacity.
KT Cloud
KT Cloud
Said on 7 October that it and Hyundai Engineering will build a 50 MW AI data centre at Cheongna, Incheon, from the fourth quarter of 2026. Completion is due in the first quarter of 2030, part of KT Cloud's target of more than 1 GW of AI capacity by 2031.
Town of Trebbin
Town of Trebbin
Said on 7 October that work has begun on two data-centre buildings and a substation under building permits already granted. The operating permit under the Federal Immission Control Act is still with Brandenburg's environment agency, so the town postponed its public presentation.
Óscar López, Digital Transformation minister
Óscar López, Digital Transformation minister
Said in Madrid on 8 October that he hopes to approve the data-centre royal decree shortly, with urgent processing to reach the cabinet before the 29 November election. He said the final text will take the more than 600 submissions into account, without saying what changes.
Hydro-Québec
Hydro-Québec
Defended its proposed Tarif CD before the Régie de l'énergie du Québec from 1 to 9 October, a rate for data centres of 5 MW or more that adds a premium when peak demand stays below 60% of forecast. Industrial consumers filed their own wording for the clause on who the rate covers.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.