Pahlavan, a data-centre developer with three projects in the São Paulo town of Paulínia, went to court on 6 October, while Brazil's first grid-access round was still open, to keep the larger capacity its earlier contracts covered. A judge at the Tribunal Regional Federal da 1ª Região (TRF-1, a federal appeals court) gave the regulator, the Agência Nacional de Energia Elétrica (ANEEL), 48 hours to rule on Pahlavan's injunction requests1.
The order said that until ANEEL ruled, winners of this year's first access season could not be awarded a connection at the Replan substation, where Pahlavan sought its connections, and capacity matching Pahlavan's requests could not be committed. The judge said his order grants no priority, reserves no capacity and authorises no contract. No ANEEL decision had been published by 17 October.
Pahlavan's projects were set up under the access rules that came before the new policy. They already held every paper that system asked for: a ministry ordinance, ANEEL authorisations, access opinions (the grid operator's technical sign-off that a connection is feasible) and signed transmission-use contracts (the agreements to pay for using the grid). Each Paulínia project was to step up from 71 MW to 157 MW of grid use in 2029. The national grid operator, the Operador Nacional do Sistema Elétrico (ONS), found that 86 MW step unviable under the new policy.
The same regulator cleared Scala Data Centers' AI City campus onto the grid in September. The minister promised developers more predictability from the new policy; a developer holding signed contracts under the earlier rules has so far got the reverse.