Data Centres: Boom and Backlash
18OCT

Brazil judge freezes Replan grid awards

3 min read
13:11UTC

A federal judge gave Brazil's power regulator 48 hours to rule on Pahlavan's bid to keep the grid capacity its old contracts covered, and froze awards at the Replan substation meanwhile.

IndustryDeveloping
Key takeaway

A Brazilian court froze grid awards at Replan while the regulator rules on Pahlavan's old contracts.

Pahlavan, a data-centre developer with three projects in the São Paulo town of Paulínia, went to court on 6 October, while Brazil's first grid-access round was still open, to keep the larger capacity its earlier contracts covered. A judge at the Tribunal Regional Federal da 1ª Região (TRF-1, a federal appeals court) gave the regulator, the Agência Nacional de Energia Elétrica (ANEEL), 48 hours to rule on Pahlavan's injunction requests⁠1.

The order said that until ANEEL ruled, winners of this year's first access season could not be awarded a connection at the Replan substation, where Pahlavan sought its connections, and capacity matching Pahlavan's requests could not be committed. The judge said his order grants no priority, reserves no capacity and authorises no contract. No ANEEL decision had been published by 17 October.

Pahlavan's projects were set up under the access rules that came before the new policy. They already held every paper that system asked for: a ministry ordinance, ANEEL authorisations, access opinions (the grid operator's technical sign-off that a connection is feasible) and signed transmission-use contracts (the agreements to pay for using the grid). Each Paulínia project was to step up from 71 MW to 157 MW of grid use in 2029. The national grid operator, the Operador Nacional do Sistema Elétrico (ONS), found that 86 MW step unviable under the new policy.

The same regulator cleared Scala Data Centers' AI City campus onto the grid in September. The minister promised developers more predictability from the new policy; a developer holding signed contracts under the earlier rules has so far got the reverse.

Deep Analysis

In plain English

Pahlavan is a company building three data centres at Paulínia, near São Paulo. Under Brazil's older grid rules it got signed contracts promising more electricity from 2029. Brazil then changed the rules, and the grid operator said the extra power could not be delivered. Pahlavan went to court. The judge did not take sides. He told Brazil's electricity regulator to decide quickly, and held back some capacity awards until it does.

Deep Analysis
Root Causes

Brazil changed its transmission-access rules while projects authorised under the earlier system still had capacity scheduled to arrive years later. The new policy did not settle what happens to signed contracts whose larger step-ups fall after the switch.

The grid operator's finding that the 86 MW step is unviable reflects physical congestion around Paulínia, home to Petrobras's Replan refinery. A contract can promise capacity the network can no longer deliver once other loads have connected.

What could happen next?
  • Precedent

    The regulator's ruling will show whether contracts signed under the earlier access rules protect future capacity step-ups.

    Short term · Assessed
  • Risk

    A ruling for Pahlavan would remove a block of capacity larger than the first round from future competitive allocation.

    Medium term · Suggested
  • Consequence

    Other holders of earlier-rule contracts may bring similar injunction requests.

    Short term · Suggested
First Reported In

Update #16 · Malaysia bills data centres for idle grid

TAGD Law· 18 Oct 2026
Read original →
Causes and effects
This Event
Brazil judge freezes Replan grid awards
A developer holding every permit the old access system asked for is testing in court whether Brazil's new allocation rules can take that capacity away.
Different Perspectives
Nexus Core Systems
Nexus Core Systems
Hired FiveNines Group, in a deal announced on 8 October, for early design, feasibility and permit work on a 20 MW AI data centre near Casablanca. It is the first named site of a planned 180 MW programme, still at concept design.
MC Digital Realty
MC Digital Realty
Began building the 24 MW KIX15 data centre in Osaka Prefecture on 7 October, due to open in the fourth quarter of 2028. The joint venture of Digital Realty and Mitsubishi Corporation says it will then run 10 data centres in Japan with about 220 MW of IT capacity.
KT Cloud
KT Cloud
Said on 7 October that it and Hyundai Engineering will build a 50 MW AI data centre at Cheongna, Incheon, from the fourth quarter of 2026. Completion is due in the first quarter of 2030, part of KT Cloud's target of more than 1 GW of AI capacity by 2031.
Town of Trebbin
Town of Trebbin
Said on 7 October that work has begun on two data-centre buildings and a substation under building permits already granted. The operating permit under the Federal Immission Control Act is still with Brandenburg's environment agency, so the town postponed its public presentation.
Óscar López, Digital Transformation minister
Óscar López, Digital Transformation minister
Said in Madrid on 8 October that he hopes to approve the data-centre royal decree shortly, with urgent processing to reach the cabinet before the 29 November election. He said the final text will take the more than 600 submissions into account, without saying what changes.
Hydro-Québec
Hydro-Québec
Defended its proposed Tarif CD before the Régie de l'énergie du Québec from 1 to 9 October, a rate for data centres of 5 MW or more that adds a premium when peak demand stays below 60% of forecast. Industrial consumers filed their own wording for the clause on who the rate covers.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.