Data Centres: Boom and Backlash
18OCT

Norwegian MPs seek data-centre grid halt

3 min read
13:11UTC

Four MPs filed a proposal in the Storting on 5 October to stop new grid allocations to data centres, citing about 12 GW already reserved or queued with Statnett.

IndustryAssessed
Key takeaway

Norway's data-centre grid queue, at about 12 GW, now faces a proposed parliamentary halt.

Four members of the Storting (Norway's parliament) led by Marie Sneve Martinussen filed a proposal on 5 October for a temporary halt on new grid allocations to data centres until Norway adopts a national data-centre policy⁠1. Their filing states that Statnett, Norway's grid operator, has reserved or queued about 12 GW of capacity for roughly 120 data-centre projects. Norwegian data centres used 3.14 terawatt-hours (TWh, a measure of energy used over a year) in 2025.

The proposal, Dok 8:6 S (the Storting's format for a proposal from individual MPs rather than the government), exempts critical public functions. It adds a concession system and a Storting vote on any project of 25 MW or more. The concession would be a state licence a large consumer must hold before it connects; the vote copies the review parliament already gives big petroleum investments.

Run at the 70% utilisation that NVE (the Norwegian Water Resources and Energy Directorate) assumes, the queue would use about 70 TWh a year, some 22 times what the sector used in 2025 and more than half of Norway's total consumption. Finland's grid operator Fingrid attached the same warning to its own total in August: a signed connection does not mean a building. The filing also cites Statistics Norway's count of 677 data-centre jobs in 2024, against the 11,000 the filing says were promised in 2021.

As a private members' proposal, it must pass committee and a full vote. Whatever happens to the vote, the 12 GW figure is now on the parliamentary record, from a grid that runs almost wholly on hydropower.

Deep Analysis

In plain English

Norway makes almost all of its electricity from rivers and dams. That power is cheap, which attracts data centres, the buildings full of computers that run online services. Statnett, the company that runs Norway's high-voltage grid, has a long list of data centres waiting for power. Four members of the Storting, Norway's parliament, want to stop adding to that list until the country decides what it wants from these buildings. Their plan would also make the biggest projects get a vote in parliament before they connect.

Deep Analysis
Root Causes

Norway's Energy Act places a connection obligation on grid companies, so Statnett cannot refuse a data-centre booking on policy grounds. Since 1 July 2026 a new section 3-8 of the act lets the government order grid companies to prioritise a named customer on national-security grounds, but it gives no general power to ration the queue, which is why the proposal goes through the Storting rather than the regulator.

The 2021 national data-centre strategy courted the sector as a hydropower export, promising jobs the filing now contrasts with Statistics Norway's count. That strategy created the pipeline the proposal now wants to pause.

Norway's bidding zones split the country. The southern zones couple to continental and British prices, so new load there competes with households for power whose price is set abroad.

What could happen next?
  • Risk

    A Storting vote at 25 MW would add political approval risk to project finance for large Norwegian data centres.

    Medium term · Assessed
  • Meaning

    The 12 GW queue figure now sits on the parliamentary record and will anchor the debate whatever the vote decides.

    Immediate · Reported
  • Consequence

    Developers may shift bookings to Sweden or Finland if Norway's halt looks likely to pass.

    Short term · Suggested
First Reported In

Update #16 · Malaysia bills data centres for idle grid

Stortinget· 18 Oct 2026
Read original →
Different Perspectives
Nexus Core Systems
Nexus Core Systems
Hired FiveNines Group, in a deal announced on 8 October, for early design, feasibility and permit work on a 20 MW AI data centre near Casablanca. It is the first named site of a planned 180 MW programme, still at concept design.
MC Digital Realty
MC Digital Realty
Began building the 24 MW KIX15 data centre in Osaka Prefecture on 7 October, due to open in the fourth quarter of 2028. The joint venture of Digital Realty and Mitsubishi Corporation says it will then run 10 data centres in Japan with about 220 MW of IT capacity.
KT Cloud
KT Cloud
Said on 7 October that it and Hyundai Engineering will build a 50 MW AI data centre at Cheongna, Incheon, from the fourth quarter of 2026. Completion is due in the first quarter of 2030, part of KT Cloud's target of more than 1 GW of AI capacity by 2031.
Town of Trebbin
Town of Trebbin
Said on 7 October that work has begun on two data-centre buildings and a substation under building permits already granted. The operating permit under the Federal Immission Control Act is still with Brandenburg's environment agency, so the town postponed its public presentation.
Óscar López, Digital Transformation minister
Óscar López, Digital Transformation minister
Said in Madrid on 8 October that he hopes to approve the data-centre royal decree shortly, with urgent processing to reach the cabinet before the 29 November election. He said the final text will take the more than 600 submissions into account, without saying what changes.
Hydro-Québec
Hydro-Québec
Defended its proposed Tarif CD before the Régie de l'énergie du Québec from 1 to 9 October, a rate for data centres of 5 MW or more that adds a premium when peak demand stays below 60% of forecast. Industrial consumers filed their own wording for the clause on who the rate covers.