Data Centres: Boom and Backlash
8SEP

PJM auction falls 6,623 MW short

2 min read
13:06UTC

PJM's 2027/28 capacity auction cleared 6,623 MW below its reserve target, forcing a supplemental procurement with a 21 July deadline as the largest US grid hunts for power it has already sold.

IndustryDeveloping
Key takeaway

PJM's 2027/28 auction came up 6,623 MW short, buying power years before the campuses driving demand connect.

PJM Interconnection, the largest US regional transmission organisation, cleared its 2027/28 capacity auction 6,623 MW below its reserve target, and set a 21 July deadline for supplemental procurement to close the gap. A capacity auction is where a grid operator buys commitments from power plants to be available years ahead; the reserve target is the cushion of supply above forecast peak demand it must secure. 1 2

A shortfall this far out means PJM is short of generation it has, in effect, already promised to deliver. It sharpens the question the operator's board put to 13 governors in May, warning that grid-reinforcement costs could fall on household bills unless states write cost-allocation rules first . Every megawatt the auction fails to clear now is one the supplemental round must buy at a premium, and the load driving the gap is data-centre demand that has not yet connected.

Deep Analysis

In plain English

PJM runs the electricity market for the largest US grid area, covering 13 states plus Washington DC. Its most recent auction, which lines up power supply for 2027 and 2028, came up 6,623 megawatts short of the reserve PJM wants to keep on hand as a safety margin, roughly enough to power several million homes. PJM now has until 21 July to buy extra power supply to help close that gap. The shortfall follows PJM's board asking the governors of all 13 states in its territory in May how to fairly split the rising costs data centres are adding to the grid.

What could happen next?
  • Risk

    Capacity-market clearing prices for the 2027/28 delivery year are likely to rise further given the confirmed 6,623 MW shortfall, adding to the cost-allocation dispute already before PJM's board and the 13 state governors.

First Reported In

Update #11 · Pipeline vetoed, campus keeps building

Foley Hoag· 25 Jul 2026
Read original
Different Perspectives
NVIDIA
NVIDIA
NVIDIA told the Securities and Exchange Commission on 26 August it had signed memorandums aiming to mobilise over $500bn for buyers' equipment purchases, then said in the same filing the arrangements may not become definitive. It may also carry limited residual-value risk on the equipment itself.
IREN Limited
IREN Limited
IREN signed $2.4bn of financing on 25 August that only releases cash once its Mackenzie GPU servers are accepted, and only through 31 December 2026. A shipping delay from here now creates a funding problem as well as a revenue one.
Energy Commission (Malaysia)
Energy Commission (Malaysia)
Malaysia's Energy Commission recorded data centres at 9.3% of national power in one hot week in August, against a 7% year-to-date average, and is projecting 31% of peninsular demand by 2035. It wants roughly 9 GW of new gas-fired capacity by 2032 to cover the gap.
Economic Development Board and Infocomm Media Development Authority
Economic Development Board and Infocomm Media Development Authority
Singapore's EDB and IMDA rationed 200 MW across four operators on 21 August and followed with a tropical liquid-cooling standard six days later, fixing the terms before construction starts. The agencies will decide within 18 to 24 months whether to run a third call.
Legal Resources Centre
Legal Resources Centre
The Legal Resources Centre put the water and power draw of two approved Cape Town Equinix sites in public, at roughly 4.4 billion litres and 1.4 to 1.5 billion kWh a year, because the city and the operator would not. It wants a cumulative assessment before any more of the five approvals proceed.
Ministerio de Minas e Energia
Ministerio de Minas e Energia
Brazil's energy ministry published Redata's five conditions after the Senate passed PL 278/2026 on 1 September, betting a repeatable annual water test enforces cooling design better than a one-off approval. Redata now needs President Lula's signature before any of it takes effect.