Data Centres: Boom and Backlash
8SEP

Malaysia bills data centres' unused grid

3 min read
13:06UTC

Johari Abdul Ghani told Malaysia's parliament on 15 October that a data centre booking 200 MW of grid and drawing 100 MW now pays for all 200.

IndustryDeveloping
Key takeaway

Malaysian data centres now pay for every megawatt of grid they reserve, whether they use it or not.

A data centre in Malaysia that books 200 megawatts (MW) of grid capacity and draws 100 MW will now pay for all 200. Johari Abdul Ghani, the Investment, Trade and Industry Minister, set out the rule in the Dewan Rakyat (the lower house of parliament) on 15 October⁠1. Operators also pay a market electricity tariff set apart from other customers' rates, carry the cost of upgrading the transmission network of Tenaga Nasional Berhad (TNB), the national utility, recycle their water and buy at least 3% of their services locally⁠2.

"It is no longer about cheap energy," Johari said, according to Free Malaysia Today. He told state governments to be careful when approving new applications⁠3.

Some 57 data centres run on 6,237 MW supplied by TNB, while 60 more projects at approval or construction stages want 11,172 MW, almost double the operating fleet and roughly the capacity of eleven large nuclear reactors, the minister said as reported by Free Malaysia Today⁠4. A different count in June, of contracted capacity, put 38 projects at 5.9 gigawatts (GW), more than two-fifths of everything TNB had contracted to customers. The two tallies measure different things and cannot be joined into a trend.

A developer who books capacity before signing a tenant now pays for it every month, on take-or-pay terms like those of a gas pipeline contract. Total reported investment in the sector stands at 385.7bn Malaysian ringgit (RM385.7bn), and the minister put its economic contribution at RM14.1bn this year, up from RM900m in 2021⁠5. Johor, the southern state across the strait from Singapore, halted approvals over water in April; the federal government has now chosen to price access rather than stop it.

Deep Analysis

In plain English

Data centres are warehouses full of computers that run websites, apps and artificial intelligence. They use huge amounts of electricity. In Malaysia, companies building them ask the national power company, Tenaga Nasional Berhad, to set aside grid capacity. Some ask for far more than they use, which blocks others. The government now makes them pay for everything they set aside, used or not. It is like paying for a whole restaurant table you reserved, even if half your party never turns up.

Deep Analysis
Root Causes

Malaysia regulates Tenaga Nasional Berhad under Incentive-Based Regulation, which recovers approved network spending through tariffs paid by every customer. Until now a developer could book transmission capacity cheaply while the upgrades it triggered flowed into everyone's base tariff.

Singapore's 2019 freeze pushed regional demand across the causeway into Johor, where land was cheap and the grid had headroom. That displacement, not domestic demand, explains why the queue grew faster than the operating fleet.

Water compounds the grid problem. Johor halted approvals over water in April, so the federal water-recycling condition now applies the state's constraint nationwide.

What could happen next?
  • Consequence

    Developers holding capacity without signed tenants may release part of their bookings, shortening the queue behind them.

    Short term · Assessed
  • Precedent

    Other Southeast Asian grids facing Johor-style queues gain a worked model for charging on reservation rather than use.

    Medium term · Suggested
  • Risk

    If hyperscale tenants absorb the charge easily, the queue may shrink only at the speculative fringe while water stress persists.

    Medium term · Suggested
First Reported In

Update #16 · Malaysia bills data centres for idle grid

Free Malaysia Today· 18 Oct 2026
Read original →
Causes and effects
This Event
Malaysia bills data centres' unused grid
Malaysia now prices every megawatt a data-centre developer reserves, so a speculative grid booking costs money before any server arrives.
Different Perspectives
Mohsen Rezaei
Mohsen Rezaei
The senior Iranian security official and former IRGC commander told Press TV that US-linked technology infrastructure in the region could become a target if war resumes. He named the UAE and valued the assets at more than US$2 trillion, without a breakdown.
Mykhailo Shelemba
Mykhailo Shelemba
Datagroup's chief executive says the Kyiv data centre hit on the night of 18 to 19 October is beyond repair. Services continue from backup sites, and no staff were hurt.
Kristen Umstattd
Kristen Umstattd
The Loudoun supervisor voted against fast-tracking Amazon's rezoning of the Ashburn campus. She said there were no figures yet on homes, school or road costs.
Akishima residents' litigation group
Akishima residents' litigation group
The group formed on 18 October and plans to sue Nihon GLP by year-end to stop eight data-centre buildings. Its lawyers will argue rights to life, health, clean water and a natural environment after mediation failed in August.
Óscar López
Óscar López
Spain's Digital Transformation minister said on 22 October he could not confirm when the data-centre decree will be approved. He added that Google has always committed to investing in Spain.
Google
Google
Google said it would comply with LVV's order to stop preparatory works at Muhos and Kajaani until environmental assessments finish. A spokesperson conceded the company had fallen short.