Data Centres: Boom and Backlash
14AUG

Texas developer sues county over pause

4 min read
10:48UTC

RCM Hill LLC sued Hill County, Texas on 28 May for $100m, arguing the moratorium on its 1,235 MW Project Aquila campus is an unconstitutional regulatory taking.

IndustryDeveloping
Key takeaway

RCM Hill's suit is the first Fifth Amendment taking claim against a US data-centre moratorium.

RCM Hill LLC sued Hill County, Texas on 28 May 2026, asking for $100m in damages and arguing the county had no power to halt its Project Aquila data centre, a 1,235 MW campus planned across 800 acres 1. The developer says it signed four landowner contracts worth more than $80m over 16 months, and faces a 24 July ERCOT deadline requiring a $61.75m deposit to hold its grid slot.

Every prior backlash story ran one way: a community blocks a build. This one runs the other. The complaint, as reported by KWTX and KXXV, invokes regulatory taking under the Fifth and Fourteenth Amendments and the Texas Constitution, the principle that government cannot strip the economic use of private property without paying for it. It quotes the county's own 12 May meeting back at it. County Judge Shane Brassell called the moratorium "illegal"; county attorney David Holmes warned commissioners they lacked the authority. They passed it 3-2 regardless, then tabled the suit.

Texas counties hold weaker police powers than its cities, which is why service blocks in Ohio and Michigan stuck and Maine's statewide freeze cleared its legislature , while a county pause now faces a constitutional test. A construction ban on a contracted, deposit-backed 1,235 MW site is a far stronger taking claim than a routine zoning limit, because the developer can show concrete investment-backed expectations the moratorium destroyed.

Deep Analysis

In plain English

In most of the US, a local government can restrict what gets built in its area. But in Texas, counties and cities have different legal powers. Texas cities can zone land; Texas counties generally cannot, unless the state has given them specific authority to do so. Hill County voted to pause a massive data-centre project called Project Aquila. The developer, RCM Hill LLC, is now suing the county for $100 million, arguing the county never had the legal power to stop it in the first place. The county's own judge and lawyer said the moratorium looked unlawful before the vote. The three commissioners voted for it anyway. There is also a financial deadline: the developer must pay a $61.75 million deposit to ERCOT by 24 July 2026 to keep its grid connection slot. A moratorium that runs past that date wipes out the slot, which took over a year of queue work to secure.

Deep Analysis
Root Causes

Texas counties derive their land-use authority from a fragmented set of enabling statutes rather than a general zoning power. The Texas Government Code grants limited extraterritorial jurisdiction powers to municipalities but gives counties far narrower tools, primarily nuisance abatement and some subdivision rules.

A commissioner's court moratorium on a specific land use has no clear statutory basis unless the legislature has authorised it. The county attorney's pre-vote warning tracked exactly this gap.

The financial urgency in the case, the 24 July ERCOT deadline requiring a $61.75m deposit, is itself a structural artefact of ERCOT's queue reform. ERCOT imposed binding deposit deadlines to force speculative applicants to either commit capital or exit the queue.

That reform, designed to clean the book, now gives a developer a hard countdown that a moratorium can destroy, creating a class of taking claim where the regulatory action imposes a concrete financial deadline loss rather than a vague future reduction in value.

What could happen next?
  • Precedent

    A developer win, whether on ultra vires or taking grounds, would discourage other Texas counties from imposing moratoriums without clear statutory authority, reshaping the geography of moratorium activity toward stronger-authority jurisdictions like cities and states.

    Medium term · Assessed
  • Risk

    If the Hill County case proceeds to a damages phase and the county cannot pay, it creates a fiscal crisis for a small rural government, potentially chilling elected officials in similar jurisdictions from voting their constituents' wishes on land-use questions.

    Medium term · Suggested
  • Consequence

    Developer strategy in moratorium-threatened jurisdictions shifts: commit capital to ERCOT deposits early to establish investment-backed expectations evidence, strengthen any future taking claim while simultaneously creating a financial hostage to the moratorium's duration.

    Short term · Suggested
First Reported In

Update #5 · Who pays when the grid bends for AI

Virginia Mercury· 2 Jun 2026
Read original
Different Perspectives
Antel, Uruguay's state telecom
Antel, Uruguay's state telecom
Antel will build a $70m AI data centre in Canelones, announced after an 11-12 August Council of Ministers meeting, with construction from Q1 2027 and roughly 250 direct jobs. Uruguay is putting a sovereign AI facility on the state balance sheet rather than courting a hyperscaler to build one.
Comtel
Comtel
Comtel is building a Figline Valdarno data centre inside the H2-Era Green Valley complex, powered by an 84 MW solar plant and selling waste heat to on-site farming. Co-location with generation and a heat offtaker is the model regulators elsewhere are now writing into connection terms rather than negotiating case by case.
Greg Abbott, Texas Governor
Greg Abbott, Texas Governor
Abbott directed PUCT and ERCOT on 3 August to audit every queued data centre's ownership, incentives and water use, saying projects that fail the state's survey should lose grid access. QTS's co-chief executives welcomed the review; Agriculture Commissioner Sid Miller called it too vague and wants a special legislative session instead.
Government of Gujarat
Government of Gujarat
Gujarat notified a Data Centre Policy on 7 August offering capital, interest, tax and duty subsidies for projects sourcing at least 51% green power, targeting 7.5 GW against a 74 GW installed base. Where other jurisdictions priced or restricted grid access this month, Gujarat is paying developers to come instead.
Taiwan's Legislative Yuan Economics Committee
Taiwan's Legislative Yuan Economics Committee
The committee gave preliminary approval on 5 August to a self-generation mandate for large power users, including data centres, with fines up to NT$750,000. It agreed the obligation in principle while leaving the megawatt threshold that defines its reach to later implementing regulation.
Australian Energy Market Commission
Australian Energy Market Commission
AEMC advised ministers on 5 August that data centres should surrender renewable certificates against actual consumption, prove new demand with new firm capacity, and register as market participants. The advice would turn passive customers into obligated participants inside the market's dispatch and settlement machinery, ahead of an access-standards determination due in late October.