Data Centres: Boom and Backlash
14AUG

ERCOT closes its Batch Zero queue window

1 min read
10:48UTC

ERCOT closed Batch Zero interconnection submissions on 24 July, with classification results on the Texas data-centre queue due by 7 August.

IndustryDeveloping
Key takeaway

ERCOT publishes its Batch Zero classification by 7 August, the first audited count of the Texas queue.

The Electric Reliability Council of Texas (ERCOT), the grid operator running most of the Texas electricity market, closed Batch Zero interconnection submissions on 24 July, with classification results due by 7 August 1. Batch Zero is the first tranche under the large-load interconnection process created after Texas legislated on data-centre connections, and classification sorts the applications by how far advanced each project actually is.

ERCOT is the outlier among the six operators that filed generation-adequacy reports this fortnight. It sits outside FERC's jurisdiction, being a grid deliberately kept inside one state's borders, and it has courted large loads rather than rationed them. Where Ofgem proposes a deposit to make speculation expensive, Texas is instead going to publish who is serious.

The Texas Public Utility Commission approved this study process in June , and the classification results are its first output. Nobody believes the whole Texas queue will be built. The results due on 7 August produce the first audited estimate of how much of it might be, in a market that charges nothing to deter a speculative applicant. Whatever share survives classification becomes the reference point every other jurisdiction's queue estimate gets measured against.

Deep Analysis

In plain English

Texas has its own electricity grid operator, ERCOT, separate from the rest of the United States. Many companies have applied to connect huge data centres to that grid, but nobody knows how much of that demand is genuine versus speculative applications that will never actually get built. ERCOT just closed the window for grid companies to submit detailed information on these projects, and will announce by 7 August which ones it classifies as real.

Deep Analysis
Escalation

The scale of Texas's data-centre queue has not eased; ERCOT's own large-load interconnection page put the total queue at 438 GW as of late May 2026, with over 300 GW of that not yet having submitted studies, meaning most of the queue remains unconfirmed pending the 7 August classification.

What could happen next?
  • Meaning

    Batch Zero's 7 August classification results will be the first hard test of how much of Texas's data-centre interconnection queue is genuine demand versus speculative applications.

First Reported In

Update #12 · Ofgem prices the grid queue by the megawatt

Day Pitney LLP (hosted by ISO New England)· 4 Aug 2026
Read original
Causes and effects
This Event
ERCOT closes its Batch Zero queue window
Texas is about to publish the first hard count of how much of its data-centre queue is real, in a market that has priced grid access lightly.
Different Perspectives
Antel, Uruguay's state telecom
Antel, Uruguay's state telecom
Antel will build a $70m AI data centre in Canelones, announced after an 11-12 August Council of Ministers meeting, with construction from Q1 2027 and roughly 250 direct jobs. Uruguay is putting a sovereign AI facility on the state balance sheet rather than courting a hyperscaler to build one.
Comtel
Comtel
Comtel is building a Figline Valdarno data centre inside the H2-Era Green Valley complex, powered by an 84 MW solar plant and selling waste heat to on-site farming. Co-location with generation and a heat offtaker is the model regulators elsewhere are now writing into connection terms rather than negotiating case by case.
Greg Abbott, Texas Governor
Greg Abbott, Texas Governor
Abbott directed PUCT and ERCOT on 3 August to audit every queued data centre's ownership, incentives and water use, saying projects that fail the state's survey should lose grid access. QTS's co-chief executives welcomed the review; Agriculture Commissioner Sid Miller called it too vague and wants a special legislative session instead.
Government of Gujarat
Government of Gujarat
Gujarat notified a Data Centre Policy on 7 August offering capital, interest, tax and duty subsidies for projects sourcing at least 51% green power, targeting 7.5 GW against a 74 GW installed base. Where other jurisdictions priced or restricted grid access this month, Gujarat is paying developers to come instead.
Taiwan's Legislative Yuan Economics Committee
Taiwan's Legislative Yuan Economics Committee
The committee gave preliminary approval on 5 August to a self-generation mandate for large power users, including data centres, with fines up to NT$750,000. It agreed the obligation in principle while leaving the megawatt threshold that defines its reach to later implementing regulation.
Australian Energy Market Commission
Australian Energy Market Commission
AEMC advised ministers on 5 August that data centres should surrender renewable certificates against actual consumption, prove new demand with new firm capacity, and register as market participants. The advice would turn passive customers into obligated participants inside the market's dispatch and settlement machinery, ahead of an access-standards determination due in late October.