Skip to content
Welcome, thoughtbot's Giant Robots listeners!Start here
Data Centres: Boom and Backlash
25JUL

Stargate US: $500B headline, 1.2 GW operational

3 min read
11:23UTC

Stargate US launched at $500 billion in January 2025, but only Abilene is partially operational at roughly 1.2 GW against a nominal 10 GW programme; Latitude Media forecasts 30-50% of 2026 data centre completions will slip.

IndustryDeveloping
Key takeaway

Stargate US runs 1.2 GW of a 10 GW headline; a third of 2026 capacity is paper only.

The Stargate US programme was unveiled in January 2025 at $500 billion of headline capex, of which only the first $100 billion was described as committed.⁠1 Abilene, Texas is the only Stargate US site partially operational, at roughly 1.2 GW against a nominal 10 GW US programme. SemiAnalysis, the semiconductor and infrastructure research firm, has questioned whether SoftBank can finance the full commitment. Latitude Media estimates that 30% to 50% of large data centres scheduled for 2026 completion will slip, against a 2025 delay rate of 26%, with only 5 GW of the planned 16 GW physically under construction.⁠2

Stargate is the OpenAI-Oracle-SoftBank joint vehicle unveiled at a White House event in January 2025, structured as a holding company that channels SoftBank-led equity into US data centre campuses contracted to OpenAI workloads. The $500 billion total is the four-year programme headline; the $100 billion first-phase figure is the only number disclosed alongside actual commitment letters. Abilene, Texas hosts the Crusoe-built campus that is the programme's flagship and to date its only partially operational site. Roughly 1.2 GW of the planned 10 GW US programme is energised, with the remainder still in early-stage permitting or unannounced.

SemiAnalysis is the Dylan Patel-led research outfit whose hyperscaler capex modelling is closely tracked by chip and infrastructure investors. Its question on SoftBank's financing capacity is grounded: SoftBank's Vision Fund balance sheet is concentrated in Arm Holdings, with limited liquid capacity to fund a multi-year $100 billion direct-equity commitment without partner co-investment. Latitude Media is the energy-and-data-centre trade publication whose 2025 delay-rate baseline of 26% is the sector's most-cited figure. Its 30-50% forecast for 2026 implies that roughly two-thirds of announced capacity for the year is either still on paper or already delayed.

Latitude Media's 5-of-16 GW figure is the year's cleanest single metric for the headline-versus-ground gap. The 2025 hyperscaler capex of $400 billion is real and is showing up in 10-Q filings, but commissioned megawatts in 2026 will run well below the implied build rate. Synergy Research Group's Q1 2026 hyperscale figures, due mid-May, are the next confirmation point. Whether the gap closes depends on whether the gas-turbine deliveries arrive on time, whether transmission upgrades clear in PJM and ERCOT, and whether OpenAI's pauses at sites like Cobalt Park spread or stay isolated. SoftBank's Q1 2026 disclosures and the Abilene commissioning timeline are the two specific signals to watch.

Deep Analysis

In plain English

Stargate is the name of a joint programme announced by OpenAI, SoftBank (a Japanese investment firm), and Oracle in January 2025 to build AI data centres across the United States, eventually totalling $500 billion in investment. That figure attracted enormous attention. By April 2026, the only site that has made significant progress is in Abilene, Texas, which has about 1.2 GW of capacity operating, a fraction of the 10 GW originally described for the full US programme. SemiAnalysis, a technology research firm, questioned whether SoftBank has enough financial resources to fund the entire commitment. Latitude Media, which tracks data centre construction, estimates that 30-50% of the large data centres scheduled for completion in 2026 will be delayed. Only 5 GW of the 16 GW globally planned for 2026 is actually being built right now. Latitude Media tracks what is physically being built: 5 GW, not 16 GW.

Deep Analysis
Root Causes

Large infrastructure programmes announce at headline to capture political and market attention, then rely on sequential financing tranches as construction milestones validate the commercial case. Stargate's structure, three primary partners (OpenAI, Oracle, SoftBank) with different balance sheets and motivations, created a financing architecture that requires continuous alignment between partners whose interests may diverge as the programme scales.

The Latitude Media delay rate increase from 26% to 30-50% reflects supply-side constraints (turbine backlog, grid connections, skilled labour) rather than demand-side weakness. The projects are not being cancelled; they are being delayed by the physical constraints documented in earlier events.

What could happen next?
  • Risk

    If SoftBank requires additional co-investors to fund Stargate phases beyond the initial $100 billion, the programme's expansion timeline becomes contingent on capital market conditions and SoftBank's Vision Fund performance, both subject to macro volatility.

  • Meaning

    The 5-GW-of-16-GW construction figure quantifies the headline-to-ground gap across the global data centre pipeline, establishing that announced AI infrastructure investment should be discounted by roughly 70% when assessing near-term electricity demand impact.

First Reported In

Update #1 · Boom hits wall: grid says no, states freeze

CNBC· 26 Apr 2026
Read original →
Different Perspectives
Mohsen Rezaei
Mohsen Rezaei
The senior Iranian security official and former IRGC commander told Press TV that US-linked technology infrastructure in the region could become a target if war resumes. He named the UAE and valued the assets at more than US$2 trillion, without a breakdown.
Mykhailo Shelemba
Mykhailo Shelemba
Datagroup's chief executive says the Kyiv data centre hit on the night of 18 to 19 October is beyond repair. Services continue from backup sites, and no staff were hurt.
Kristen Umstattd
Kristen Umstattd
The Loudoun supervisor voted against fast-tracking Amazon's rezoning of the Ashburn campus. She said there were no figures yet on homes, school or road costs.
Akishima residents' litigation group
Akishima residents' litigation group
The group formed on 18 October and plans to sue Nihon GLP by year-end to stop eight data-centre buildings. Its lawyers will argue rights to life, health, clean water and a natural environment after mediation failed in August.
Óscar López
Óscar López
Spain's Digital Transformation minister said on 22 October he could not confirm when the data-centre decree will be approved. He added that Google has always committed to investing in Spain.
Google
Google
Google said it would comply with LVV's order to stop preparatory works at Muhos and Kajaani until environmental assessments finish. A spokesperson conceded the company had fallen short.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.