Skip to content
Welcome, thoughtbot's Giant Robots listeners!Start here
Data Centres: Boom and Backlash
15JUL

Oregon PUC delays its data-centre tariff

3 min read
13:16UTC

The Oregon PUC delayed Portland General Electric's 29% large-load rate rise and the matching 1.3% household cut to 7 July, citing 200 pages of tariff updates staff had not yet reviewed.

IndustryDeveloping
Key takeaway

Oregon's data-centre tariff is filed but frozen until 7 July, so the cost shift onto operators exists only on paper.

Oregon's Public Utility Commission (PUC, the state regulator that sets electricity rates) delayed Portland General Electric's (PGE) proposed 29% large-load rate rise, and the matching 1.3% household bill cut, to a decision on 7 July⁠1. PUC chair Letha Tawney cited roughly 200 pages of tariff updates that staff needed time to review. PGE had filed the rise under the Oregon POWER Act, a state law that attributes grid-reinforcement costs to large loads such as data centres, and it filed as the first US utility to turn such a law into an actual tariff.

Neither side of the tariff has taken effect. The 29% increase and the residential reduction are both on hold, which means the precedent everyone cited, that operators rather than households absorb grid costs, exists on paper and nowhere else. A delay is not a defeat, but it is not the clean win the framing implied either. If the commission trims the 29% figure on 7 July or reopens the cost-attribution method, Oregon's claim to be first to implement the mechanism narrows to first to file it.

The stall mirrors the procedural friction holding up Virginia's capacity fee, where a cancelled session rather than a hostile vote is what blocks the charge. Both instruments now wait on a calendar rather than a count of yeses and noes, and both aim at the same large data-centre loads. The mechanism advances even where no decision has landed, which is a different kind of progress from a vote won.

Deep Analysis

In plain English

Oregon has a law called the POWER Act (Prioritising Operational and Wholesale Energy Responsibility) that says electricity companies must charge big users, like data centres, the true cost of the extra grid upgrades needed to serve them, instead of spreading those costs across ordinary households. Portland General Electric (PGE), the main electricity company in the Portland area, filed a plan to raise rates for large data centres by 29% and cut household bills by 1.3%, putting the Oregon law into practice for the first time in the US. The state's Public Utility Commission (PUC), the regulator that must approve this kind of rate change, asked for more time to study the 200-page filing and set 7 July as its new decision date. No bills have changed yet. The delay means everyone is waiting to see whether Oregon's regulator actually approves the model, which would give 12 other US states that are considering similar laws a real-world example to point to.

Deep Analysis
Root Causes

Two structural gaps explain why Oregon needed the POWER Act at all. First, utility tariff law in the US defaults to average-cost pricing: all customers in a rate class pay the system-average cost of serving them, even when a single customer class drives the majority of new infrastructure investment.

Data centres above 20 MW drew enough load growth in PGE's service territory to require substation upgrades whose cost, under the pre-POWER Act default, would have been spread across PGE's 900,000 residential customers.

Second, FERC's jurisdiction over wholesale electricity transmission means that a state regulator can only set the retail rate; it cannot compel FERC to attribute transmission upgrade costs in a particular way. The POWER Act is a retail-side instrument operating within that boundary.

Its enforceability depends on the PUC approving the tariff filing and on no party successfully invoking FERC jurisdiction to preempt the state rate structure, a risk that becomes more concrete once FERC acts on RM26-4-000.

What could happen next?
  • Precedent

    A 7 July PUC approval of PGE's tariff would give 12 other states carrying active cost-attribution bills a filed, approved tariff with specific rate figures to cite in their own proceedings.

  • Risk

    If a PUC modification reduces the 29% figure materially, operators will use the revised number to argue that a properly calibrated cost-attribution tariff imposes less than half the headline rate, undercutting the deterrent effect in other states.

First Reported In

Update #7 · Virginia taxes the backup, not the draw

OPB· 17 Jun 2026
Read original →
Different Perspectives
MUFG
MUFG
Mitsubishi UFJ (MUFG) and Morgan Stanley are preparing to sell a loan of about $4.5bn secured on the GPUs CoreWeave runs for Meta in Dalton, Georgia, with price talk of 7% to 7.5%, Bloomberg reported. Meta's contract is expected to win the loan investment-grade ratings, though CoreWeave is rated below investment grade and the loan has not priced.
CX Tech
CX Tech
CX Tech's £16.5bn, 1,000 MW plan for the former Chapelcross nuclear site has drawn more than 10,000 representations, the most Dumfries and Galloway's planners have received, BBC News reported. The company says the scheme could support up to 750 construction jobs and about 540 permanent posts; comments close on 29 November.
Nate Glubish, Alberta's technology and innovation minister
Nate Glubish, Alberta's technology and innovation minister
Glubish tabled Bill 42 on 18 November to ban power plants and data centres on Class 1 and 2 farmland and within 600 m of homes, a day after the regulator approved a 1,494 MW plant that fails both tests. The bill exempts projects already approved or under review, so the Indus plant stands.
NEXTDC's chairman and chief executive
NEXTDC's chairman and chief executive
After a second pay strike and a defeated spill on 20 November, NEXTDC's leaders said they are exploring a joint venture for the S4 Sydney campus and do not expect to raise shareholder capital for contracted capacity. They raised FY27 underlying EBITDA guidance to A$260m-A$275m, still excluding about A$140m tied to Melbourne's stalled M3 site.
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
The three groups argued in the High Court on 18 November that the CRU's data-centre connection framework breaches the 2015 Climate Act by ignoring carbon budgets, which the CRU denies. Judge Micheal O'Connell reserved judgment with no date, so the framework stands meanwhile.
South Korean data-centre industry groups
South Korean data-centre industry groups
Industry groups told Etnews on 13 November that tougher grid scoring for one sector alone is unfair, three days before the climate and energy ministry raised the capital-region pass mark to 75 from 70. Pending applications are judged on the new bar; the pilot assessed 28 capital-region projects worth 1.9 GW.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.