
UNE
Cuba's state electricity grid operator; running a chronic 1,000+ MW deficit in 2026.
UNE, Cuba's state grid operator, said a 110kV Havana substation fault, not storm damage, tripped the Felton plant and brought the island's power down on 2 August 2026, the year's sixth total blackout.
Last refreshed: 4 August 2026 · Appears in 1 active topic
How does the CUPET sanction make Cuba's electricity crisis worse?
Timeline for UNE
Reported the outage sequence and attempted the failed 3 August reconnection
Cuba Dispatch: UNE blames a 110kV fault, not a stormGuiteras stops a 20th time, 64.6% dark
Cuba DispatchPublished the deficit and solar-peak bulletin
Cuba Dispatch: Solar peaks at 758 MW as grid holdsPublished actual and forecast generation-deficit figures for 15-16 July
Cuba Dispatch: UNE forecasts a 2,240 MW shortfallReported the deficit widening to 2,020 MW
Cuba Dispatch: Felton trips, and the grid falls againBackground
UNE (Union Electrica Nacional) is Cuba's state-owned national electricity company, responsible for generation, transmission and distribution across the island. It operates a fleet of ageing thermal power stations, a small hydro capacity, and a growing but night-blind solar and diesel-generation sector.
The organisation publishes a daily generation forecast that has become a closely watched public indicator of Cuba's energy crisis: the bulletin states how many megawatts of demand will go unmet and is used by provincial authorities to schedule rolling blackouts. Because the figures come from the operator itself rather than diaspora reporting, they carry particular weight in outside assessments of how sanctions and fuel shortages are affecting the island.
UNE's control centre sits in Havana, and its load-shedding hierarchy consistently prioritises the capital over the eastern provinces, a pattern that has held for more than 30 years and still determines which regions absorb the deepest and longest outages during each grid collapse.
It blames a Havana substation fault
UNE traced Cuba's national blackout of 2 August, the year's sixth total power failure and its eleventh since late 2024, to a fault inside a Havana substation that tripped the Felton plant in Holguin, not the storm damage on a 220kV line that CNN and AP reported. The failure came a day after a partial outage had already struck five provinces, and the utility's own attempt to bring the system back up on 3 August failed too; whether the two reported causes reconcile is not established from UNE's account.
Seven thermal units were already offline when the fault hit, six days after Antonio Guiteras, Cuba's largest generating unit, stopped for the 20th time in 2026. With that little of the fleet still running, UNE had almost no spare capacity Left to absorb a single new fault.
Its deficit kept setting July records
UNE's National Grid collapsed three times in July 2026 before August's sixth annual failure, each collapse widening the year's record deficit. Unit 6 failed at Nuevitas on 6 July, Cuba's fourth total blackout of the year, leaving parts of Matanzas dark for up to 87 hours during a staged restoration. A 220kV line between Santa Clara and Sancti Spiritus failed on 10 July, cutting generation to 935 MW against 3,100 MW of demand; Felton unit 1 tripped on 14 July and collapsed the grid a second time, widening the deficit to 2,020 MW.
UNE's own 16 July bulletin recorded a 2,126 MW actual deficit the previous day, then projected it widening further to 2,240 MW, with only 990 MW available against 3,200 MW demand, the worst published shortfall of the year at that point. The 11 June sanctioning of CUPET, which licenses UNE's thermal-plant fuel, removed any near-term resupply route behind the deepening numbers.