PNAST
Brazil's national transmission-access policy, which allocates scarce grid connections through competitive rounds.
PNAST ran its first competitive round on 6 and 7 October 2026, with 451 MW of qualified bids chasing 228 MW at four São Paulo points; three data centres won it all, and a court then froze Replan awards.
Last refreshed: 18 October 2026 · Appears in 1 active topic
Can an auction for grid access survive challenges from projects promised capacity before it?
Timeline for PNAST
Set the competitive rules for the allocation
Data Centres: Boom and Backlash: Brazil auctions its grid to data centresGoverned the access round the court order partly froze
Data Centres: Boom and Backlash: Brazil judge freezes Replan grid awardsBackground
Brazil's National Transmission System Access Policy, PNAST, held its first competitive allocation over 6 and 7 October 2026. Bids from seven qualified projects totalled 451 MW across four São Paulo connection points, and three data centres won the whole 228 MW. That week a federal appeals judge suspended awards at the Replan substation while ANEEL considered Pahlavan's claim to capacity granted under the previous access rules.
The policy was created by Decree 12.772 of 5 December 2025. It ends first-come access to the high-voltage grid: permanent connections and increases in contracted use now pass through periodic access seasons, in which the grid operator ONS reviews all requests together and runs a competitive process wherever demand exceeds capacity. Proceeds go to lowering tariffs. The decree set the first season within ten months of publication and requires at least two seasons a year after that.
Transitional rules explain the first fight. Requests filed before the decree had to receive access opinions within ten months, with no priority over future capacity, and those opinions cannot be revalidated. Within weeks of publication an ANEEL director publicly questioned whether the decree could lawfully hand access powers to ONS.
What is PNAST in Brazil?
How does Brazil allocate transmission grid connections to data centres?
Where does the money from Brazil's grid access auctions go?
Why did a Brazilian court freeze grid awards at the Replan substation?