Timeline
EirGrid
Ireland's state electricity transmission operator; its adequacy warning puts data centre reconnection on a collision course with grid capacity.
9 of 9 entries (9 events, 0 interactions)
Filters
#12 29 Jul
Proposed fault-ride-through and RoCoF compliance obligations via MPID 345
Data Centres: Boom and Backlash: Ireland writes the grid rules into contracts#11 15 Jul
Mentioned in: MISO's second grid emergency in July
Data Centres: Boom and Backlash#10 29 Jun
Issued a fault-ride-through demand-curtailment procedure with SONI
Data Centres: Boom and Backlash: Ireland codes a 900 MW load-loss limit#7 16 Jun
Published All-Island Resource Adequacy Assessment warning of demand exceeding supply through 2026-2028
Data Centres: Boom and Backlash: Irish regulators split over data centres#6 27 May
Mentioned in: Denmark halts its clean wind-grid queue
Data Centres: Boom and Backlash#2 27 Apr
Mentioned in: OpenAI puts a number on UK electricity gap
Data Centres: Boom and Backlash#2 27 Apr
Mentioned in: Pure DC Dublin microgrid surfaces as Irish template
Data Centres: Boom and Backlash#1 1 Apr
Failed to publish required data centre connection process by CRU-mandated 31 March 2026 deadline
Data Centres: Boom and Backlash: Pure DC's 110 MW Dublin microgrid skips queue#1 27 Feb