Microsoft quits Nscale's Essex AI site

3 min read
18:53UTC

Microsoft pulled out of its anchor deal at Nscale's Loughton site after UK Power Networks warned grid capacity might not arrive until the 2030s.

TechnologyDeveloping
Key takeaway

Microsoft left Loughton because UK transmission capacity may not reach Essex until the 2030s.

Microsoft has withdrawn from its anchor agreement at Nscale's planned artificial intelligence (AI) data centre at Loughton in Essex, after UK Power Networks warned that grid capacity might not be available until the 2030s⁠1. The Telegraph reported the exit on 18 October, and Microsoft confirmed on 19 October that the withdrawal covers only Loughton⁠2.

Nscale, a UK AI cloud company, announced Loughton in September 2025 as a 50 MW site, expandable to 90 MW, holding 23,040 of Nvidia's GB300 chips, graphics processors (GPUs) built for AI work. First chips were due in early 2027 for Microsoft's Azure cloud. UK Power Networks runs the local lines and substations for London and the east and south-east of England; it says many data centres are waiting on transmission works, the high-voltage network upstream, which it does not own.

Nscale says it remains "committed to both the Loughton project and the UK" and is "exploring alternative power sources for the site". The company, which is preparing a New York listing reportedly valued at up to US$35bn, says the grid problem is London-wide and touches no other contract. Ministers created GB Grid in September so businesses can build and co-fund their own connections, but GB Grid does not touch transmission, where Loughton's wait sits.

Deep Analysis

In plain English

Nscale is a British company that builds data centres for artificial intelligence (AI): buildings packed with powerful computer chips. Microsoft had agreed to be the main customer at a planned Nscale site in Loughton, Essex. UK Power Networks, the company that runs local power lines in London and the south-east, warned that it might not be able to supply enough electricity until the 2030s. The bigger high-voltage lines that feed its network need upgrading first, and it does not own those. Without a date for power, Microsoft walked away from this site. Nscale says it still wants to build there and is looking at other ways to get electricity.

Deep Analysis
Root Causes

Connection offers in Great Britain have been handed out largely in order of application. Contracted offers in the demand queue reached 125 GW by mid-2025, up from 41 GW in November 2024. Speculative and real projects sit in the same line, so a ready project can wait behind ones that may never build.

Ownership adds a second cause. UK Power Networks runs local lines and substations, but the reinforcement Loughton needs sits upstream on the transmission network. The company that tells a developer its date does not control the works that set it.

What could happen next?
  • Consequence

    Nscale needs a new anchor customer or on-site power before Loughton can proceed.

    Short term · Assessed
  • Risk

    Investors in Nscale's planned New York listing may test the power dates at its other UK sites.

    Short term · Suggested
  • Meaning

    In England the binding constraint on AI sites is upstream transmission, not the site or the buyer.

    Medium term · Assessed
First Reported In

Update #17 · Stalled power line cuts A$140m from NEXTDC guidance

The Register· 22 Oct 2026
Read original →
Causes and effects
This Event
Microsoft quits Nscale's Essex AI site
A hyperscaler walked away from a UK AI site over the wait for transmission capacity, which no single developer or distributor can speed up.
Different Perspectives
Association of Investment Companies (Richard Stone)
Association of Investment Companies (Richard Stone)
The trust industry body criticised the Budget for leaving Venture Capital Trust relief at 20%. It had lobbied for the 30% rate to return.
Tax Justice UK
Tax Justice UK
The campaign group opposed the 10% founders' rate as a giveaway to a small group of wealthy owners. It said the BADR cut should have gone further, to abolition.
techUK
techUK
The trade body set the new relief against the BADR cut, which halves the most a seller can save to £30,000. It says the Budget takes back with BADR part of what it gives founders.
Startup Coalition
Startup Coalition
The founder lobby group welcomed the Budget package for startups. It treats the new relief as the strongest government support for founders in years.
HM Treasury
HM Treasury
The Treasury created a 10% founders' relief on up to £10m of lifetime gains and expects about 600 people a year to use it. It says the relief rewards founders behind the UK's fastest-growing companies.
Abu Dhabi Investment Council
Abu Dhabi Investment Council
The Abu Dhabi Investment Council holds notes in Nscale's $3.36bn pre-IPO raise, beside Third Point, Apollo, Citadel and Nvidia. No British institution appears among the named holders of notes that convert into shares at Nscale's New York listing.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.