Data Centres: Boom and Backlash
What we told you to watch, what each side claimed, and what we got wrong. Every verdict shows its evidence.
Happened 2 · Unresolved 1 · Open 75 · Corrections 132
What we told you to watch
Happened · 2
Whether the Alto Jahuel case file held by SEA (Servicio de Evaluacion Ambiental, Chile's environmental assessment service) becomes available, so the diesel storage specification reported there can be checked.
From the 8 Sept briefing · Judged 22 Oct 2026
SEA's Alto Jahuel case file is available and was checked.
“SEA's resolution specifies about 990 tonnes of diesel.”
Whether the CRU (Ireland's Commission for Regulation of Utilities, which regulates the energy networks) decides a modification to EirGrid's grid code (the technical rulebook binding anything connected to the network), MPID 345 (the modification proposal identifier on EirGrid's own register), whose entry still shows no approval or effective date.
From the 8 Sept briefing · Judged 22 Oct 2026
CRU approved MPID 345 on 22 September 2026.
“CRU approved MPID 345 on 22 September 2026.”
Unresolved · 1
NERC's November final ballot on the CLO standards, then the filing with FERC due by 31 December .
From the 24 Sept briefing · Judged 22 Oct 2026
Final ballot passed; Board adoption and FERC filing remain pending.
“The standards passed final ballot and advance to Board adoption.”
Still open · 75
Show the 10 most recentFingrid's submission of the revised KJV2026 (its grid code specifications for demand connections) to Finland's Energy Authority, ahead of a March 2027 confirmation target.
From the 8 Sept briefing · Deadline: March 2027
Whether PUCT grants ERCOT's good-cause exception on 20 August, and whether a revised Batch Zero classification timetable is published alongside it
From the 14 Aug briefing · Deadline: 20 August
Whether any load-serving entity, state commission or data-centre operator protests the IRAS terms in ER26-3380-000 before comments close at 5pm Eastern on 21 August
From the 14 Aug briefing · Deadline: 21 August
Whether the DPEA holds its 8 September target decision now the Edinburgh appeal carries a full EIA
From the 14 Aug briefing · Deadline: 8 September
Whether Nebius's next annual ICFR assessment reports the fixed-asset material weakness as remediated or carries it into 2027
From the 14 Aug briefing
Whether PJM's Interim Resource Adequacy Service filing, due at FERC around 7 August, allows curtailment of large loads connecting after 1 June 2027 without dedicated supply, and how the large-load registry sequences them.
From the 4 Aug briefing · Deadline: 7 August
What aggregate megawattage ERCOT's Batch Zero classification results show on 7 August, the first hard test of how much of the Texas queue is real rather than speculative.
From the 4 Aug briefing · Deadline: 7 August
Whether developers respond to Ofgem's fee before the consultation closes on 16 September by withdrawing applications, which would shrink the 125 GW book without a single refusal being issued.
From the 4 Aug briefing · Deadline: 16 September
Whether New Mexico's four sponsors pre-file their statewide moratorium bill ahead of the legislature reconvening in January 2027.
From the 4 Aug briefing · Deadline: January 2027
Whether the six RTOs' 20 July generation-adequacy filings, still not public, show any grid able to serve its data-centre queue
From the 25 Jul briefing · Deadline: 20 July
The Montgomery County, Maryland full council vote on 28 July
From the 25 Jul briefing · Deadline: 28 July
Microsoft and Meta capex on 29 July and Amazon's on 30 July, testing whether Alphabet's raise is matched across the big four
From the 25 Jul briefing · Deadline: 29 July
Whether New Mexico lawmakers table the promised statewide moratorium bill for the 2027 session
From the 25 Jul briefing
Whether Hochul signs, vetoes or amends the Responsible Data Center Development Act before the year-end deadline, now that her executive order covers the same ground
From the 15 Jul briefing
Whether the Indianapolis City-County Council ratifies the moratorium on 10 August or bends to Governor Braun's pro-investment stance
From the 15 Jul briefing · Deadline: 10 August
Whether Q2 hyperscaler capex, reported after 20 July, accelerates against the tightening permit map or shows the first sign of siting caution
From the 15 Jul briefing · Deadline: 20 July
Whether any developer challenges New York's executive order or Oregon's 29% tariff as a regulatory taking, the argument already filed against DOE curtailment
From the 15 Jul briefing
Whether Hochul signs or vetoes New York's freeze, making it the first US statewide moratorium to take effect
From the 7 Jul briefing
Whether Oregon's Public Utility Commission approves Portland General Electric's 29% large-load rate rise
From the 7 Jul briefing
Whether another state copies Virginia's per-kilowatt-hour consumption tax now that one is enacted
From the 7 Jul briefing
What each side claimed
Claims are what a named side said at the time. We record them as said and judge them only against later evidence.
No claims recorded yet.
What we got wrong
- MinorCorrected 22 Oct 2026We said
All Irish data centres must ride through voltage dips.
What was trueMPID 345 applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
Ireland applies MPID 345 to existing sites.
What was trueMPID 345 applies to existing transmission-connected sites.
- MinorCorrected 22 Oct 2026We said
MPID 345 requires large users to ride through voltage dips.
What was trueMPID 345 applies to transmission-connected demand facilities.
- MinorCorrected 22 Oct 2026We said
All non-compliant data centres must seek a derogation.
What was trueThe derogation route applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
All non-compliant sites must seek a derogation.
What was trueThe derogation route applies to transmission-connected sites.
- MinorCorrected 22 Oct 2026We said
All non-compliant data centres must seek a derogation.
What was trueThe derogation route applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
MPID 345 requires large users to ride through faults.
What was trueMPID 345 applies to transmission-connected demand facilities.
- MinorCorrected 22 Oct 2026We said
MPID 345 requires large users to ride through voltage dips.
What was trueMPID 345 applies to transmission-connected demand facilities.
- MinorCorrected 22 Oct 2026We said
All non-compliant data centres must seek a derogation.
What was trueThe derogation route applies to transmission-connected data centres.
- MinorCorrected 22 Oct 2026We said
MPID 345 requires large users to ride through voltage dips.
What was trueMPID 345 applies to transmission-connected demand facilities.
- MinorCorrected 18 Oct 2026We said
METI's preferred regions for new data centres are Hokkaido and Kyushu.
What was trueNo government source names preferred regions. The 2026 MIC white paper gives the Kanto and Kinki concentration (about 90%) and the aim of regional distribution; Hokkaido and Kyushu as hubs come from a Mitsubishi Research Institute proposal, not policy.
- MinorCorrected 18 Oct 2026We said
Suaram provided the platform for Kua Kia Soong's moratorium call
What was trueKua Kia Soong made the call in a personal letter published by Free Malaysia Today on 26 June 2026, signed as a former MP and former Suaram director; Suaram took no part
- MinorCorrected 18 Oct 2026We said
The multiple is at the top of emerging-market infrastructure valuations
What was trueThe multiple rested on an unsourced EBITDA figure; the comparison is removed
- MinorCorrected 18 Oct 2026We said
Teraco enterprise value $4.1bn, about 28x a publicly disclosed 2025 EBITDA of $145m
What was true$650m for 16 percentage points implies an equity value of about $4.1bn; no public source for a $145m EBITDA was found
- MinorCorrected 18 Oct 2026We said
Digital Realty has an enterprise value of roughly $50bn and the deals are 3% of it
What was trueNo source supports the $50bn figure; the claim is removed
- MinorCorrected 18 Oct 2026We said
Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June
What was trueOn 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed
- MinorCorrected 18 Oct 2026We said
Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June
What was trueOn 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed
- MinorCorrected 18 Oct 2026We said
Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June
What was trueOn 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed
- MinorCorrected 18 Oct 2026We said
Digital Realty raised its Teraco stake to 77% and bought Columbia Capital on 22 June
What was trueOn 22 June Digital Realty agreed to buy a further 16% of Teraco for about $650m, mainly in 3.4 million new shares, and said it plans to acquire the investment firm Columbia Capital for about $485m, mainly in 2.3 million shares; both deals were expected to close in the second half of 2026 (Digital Realty 8-K exhibit 99.1, 22 June 2026). The $475m Kansas City land purchase had completed
- MinorCorrected 18 Oct 2026We said
Teraco operates in South Africa, Nigeria and Kenya
What was trueTeraco's data centres are all in South Africa (Johannesburg, Cape Town, Durban), per teraco.co.za; Digital Realty's Kenyan and Nigerian sites are separate businesses