MC Digital Realty, Digital Realty's venture with Mitsubishi, began building the 24 MW KIX15 data centre in Osaka on 7 October, with opening set for late 2028.

IndustryDeveloping
Key takeaway

MC Digital Realty began building the 24 MW KIX15 data centre in Osaka.

Deep Analysis

In plain English

Data centres are buildings full of computers that store data and run online services. Companies often put them near big cities, so information travels quickly to users. MC Digital Realty, a joint business of the American data-centre company Digital Realty and the Japanese trading house Mitsubishi Corporation, has started building a new one near Osaka, Japan's second-largest city region. It will provide 24 megawatts of power for computers and is due to open in late 2028.

What could happen next?
  • Consequence

    Osaka keeps adding capacity as Japan's second market despite national policy favouring regional sites.

  • Meaning

    A start in October 2026 and an opening in late 2028 put a 24 MW build at about two years from groundbreaking to service.

First Reported In

Update #16 · Malaysia bills data centres for idle grid

BERNAMA (Digital Realty release)· 18 Oct 2026
Read original →
Different Perspectives
Nexus Core Systems
Nexus Core Systems
Hired FiveNines Group, in a deal announced on 8 October, for early design, feasibility and permit work on a 20 MW AI data centre near Casablanca. It is the first named site of a planned 180 MW programme, still at concept design.
MC Digital Realty
MC Digital Realty
Began building the 24 MW KIX15 data centre in Osaka Prefecture on 7 October, due to open in the fourth quarter of 2028. The joint venture of Digital Realty and Mitsubishi Corporation says it will then run 10 data centres in Japan with about 220 MW of IT capacity.
KT Cloud
KT Cloud
Said on 7 October that it and Hyundai Engineering will build a 50 MW AI data centre at Cheongna, Incheon, from the fourth quarter of 2026. Completion is due in the first quarter of 2030, part of KT Cloud's target of more than 1 GW of AI capacity by 2031.
Town of Trebbin
Town of Trebbin
Said on 7 October that work has begun on two data-centre buildings and a substation under building permits already granted. The operating permit under the Federal Immission Control Act is still with Brandenburg's environment agency, so the town postponed its public presentation.
Óscar López, Digital Transformation minister
Óscar López, Digital Transformation minister
Said in Madrid on 8 October that he hopes to approve the data-centre royal decree shortly, with urgent processing to reach the cabinet before the 29 November election. He said the final text will take the more than 600 submissions into account, without saying what changes.
Hydro-Québec
Hydro-Québec
Defended its proposed Tarif CD before the Régie de l'énergie du Québec from 1 to 9 October, a rate for data centres of 5 MW or more that adds a premium when peak demand stays below 60% of forecast. Industrial consumers filed their own wording for the clause on who the rate covers.