Data Centres: Boom and Backlash
17JUN

Hill County folds, lawsuit lives on

3 min read
10:13UTC

Hill County, Texas rescinded its data-centre moratorium on Thursday 4 June, seven days after developer RCM Hill sued it for $100 million. The suit is still live.

IndustryDeveloping
Key takeaway

A $100m taking suit reversed a Texas data-centre ban in a week, before any judge ruled on it.

Hill County, Texas voted unanimously on Thursday 4 June to rescind its moratorium on data-centre development, not because a court ordered it but to cap taxpayer liability. The county had blocked RCM Hill LLC's 1,235 MW Project Aquila campus near Hillsboro; on Thursday 28 May the developer sued for $100 million, calling the freeze an unconstitutional taking of property. Seven days later the county folded.⁠1

Rescinding the moratorium did not end the litigation. RCM Hill still seeks a court declaration that the original freeze was unlawful, plus damages dated from the day it passed. That keeps the Fifth Amendment taking question alive even with no moratorium left to challenge. The Fifth Amendment bars government from taking private property without compensation, and developers are now testing whether a building freeze counts as exactly that. A ruling for RCM Hill would chill every other county weighing a ban.

The county did not abandon oversight altogether. It replaced the moratorium with disclosure rules: applicants must now declare water use, traffic, noise and economic effect, and notify the public more widely than before.

Three moratoriums have now fallen by three different routes. Maine's first-in-nation statewide ban fell to a governor's veto; Prince William County's fast-track rezoning fell to an appellate court; Hill County fell to a single lawyer's letter. Each consent tool has met a sharper instrument of restraint, and developers have learned that the threat of a ruling can work faster than the ruling itself.

Deep Analysis

In plain English

Hill County in rural Texas voted to block all new data-centre construction in 2026. A developer called RCM Hill had been planning a giant computer campus there, called Project Aquila, that would have used as much electricity as a city of roughly 900,000 homes. The county freeze stopped all construction. Seven days after RCM Hill sued the county for $100 million, claiming the freeze illegally took away its property rights under the US Constitution, the county reversed course and voted unanimously to lift the ban. The lawsuit is still alive: RCM Hill still wants compensation for the time its project was blocked. The case shows that a rural county with a small budget faces a very unequal legal fight when it tries to stop a billion-dollar data-centre project without a clear legal basis for doing so.

Deep Analysis
Root Causes

Hill County's original moratorium reflected a common pattern in rural Texas counties: a large-scale industrial project arrives with insufficient advance engagement, local officials face constituent pressure and respond with a blanket freeze rather than a structured review process. The county had no pre-existing land-use framework for facilities drawing more than 200 MW, so the moratorium was the default response in the absence of a permitting mechanism.

Project Aquila at 1,235 MW would have drawn roughly 1.5% of ERCOT's peak demand from a single rural county, an impact scale that requires a genuine public-interest analysis rather than a blanket halt.

RCM Hill's $100 million lawsuit converts the county's failure to design a permitting process into a direct fiscal liability, which is why the rescission came before any court hearing: the county's legal counsel almost certainly calculated that defending the moratorium in federal court was more expensive than permitting the project.

What could happen next?
  • Precedent

    RCM Hill's pre-adjudication reversal establishes that a federal taking lawsuit is sufficient deterrent to force rescission without a court ruling, lowering the bar for other developers facing rural moratoriums.

    Short term · Assessed
  • Risk

    Rural counties across Texas and other ERCOT states with no large-load permitting frameworks face the same asymmetric litigation exposure if they impose blanket moratoriums rather than structured review processes.

    Medium term · Assessed
  • Consequence

    The active damages claim creates an unresolved legal question on the quantum of loss for data-centre downtime, which could establish a precedent figure that all future taking claims cite.

    Medium term · Reported
First Reported In

Update #6 · Oregon bills data centres, not homes

Texas Tribune· 10 Jun 2026
Read original →
Causes and effects
This Event
Hill County folds, lawsuit lives on
A developer reversed a county ban using the threat of a constitutional ruling rather than a ruling itself, a faster lever than any electoral or appellate route.
Different Perspectives
Chilean data-centre developers
Chilean data-centre developers
Seven projects, one linked to Google, asked SEA this month for rulings that they fall outside full environmental review; four declared diesel-storage volumes just under the review-triggering tonnage, mirroring the mechanism Alto Jahuel used in July. The clustering suggests the threshold is being engineered, not sized to need.
An Coimisiun Pleanala
An Coimisiun Pleanala
Ireland's planning appeals body refused the €1.5bn Killala data centre on 17 September, overturning Mayo County Council's 2025 grant for lack of a fixed grid-connection agreement and no corporate renewable power-purchase agreement. The ruling makes matched-power evidence, not planning consent alone, the deciding factor.
Housing Assembly and Foxglove
Housing Assembly and Foxglove
The two groups' 6 August appeal, filed through the Legal Resources Centre, kept Cape Town's approval of Equinix's data centre suspended through this window over missing water, emissions, noise and diesel-generator data. Deputy Mayor Eddie Andrews confirmed on 20-21 September that the suspension holds.
Brazil (President Lula, signing Redata)
Brazil (President Lula, signing Redata)
Lula signed Lei 15.504 on 15 September, creating the Redata tax programme and keeping the Senate's water cap with no veto, while Aneel authorised Scala's AI City to join the national grid from January 2028. Brazil is recruiting capacity other markets are now turning away.
Aragon regional government (Eva Valle)
Aragon regional government (Eva Valle)
Aragon's economy chief Eva Valle said on 11 September that Spain's draft decree, requiring 80% hourly-matched renewables via a 10-year power-purchase agreement, is unmeetable by any project and threatens Blackstone, Azora and Microsoft builds already under way. Aragon holds 3,600 MW of granted grid access against 108 MW built.
Texas Governor Greg Abbott
Texas Governor Greg Abbott
Abbott ordered TCEQ on 21 September to halt every pending data-centre permit until projects pay their own way and complete ERCOT and Texas Water Development Board audits. Texas built the country's most permissive data-centre market; freezing it signals even that market has hit its grid limit.