Data Centres: Boom and Backlash
17JUN

9.3% of Malaysia's power, in one week

2 min read
10:13UTC

Malaysian data centres took 9.3% of national electricity in the second week of August, against a 7% average for the year, the Energy Commission's chief executive said.

IndustryDeveloping
Key takeaway

Malaysia's data-centre share of national power moves with the weather, peaking at 9.3% in August.

Malaysian data centres reached 9.3% of national electricity consumption in the second week of August, against a 7% average for the year to date, the Energy Commission's chief executive Siti Safinah Salleh said in a report published on 8 September⁠1. The regulator attributes the jump to hotter weather lifting cooling load.

The Energy Commission regulates Malaysia's electricity supply industry and publishes the national consumption figures, so this is a measurement rather than a forecast. A share that moves with the weather behaves nothing like the flat draw grid planners were sold. It means the reserve margin, the spare generation held above expected demand, has to cover data-centre cooling in the same hot week as everyone else's air conditioning.

Johor carries most of that load, on an outside estimate rather than a regulator's count. Wood Mackenzie put the state's data-centre maximum demand at about 3.8 GW, roughly 1.5 times Johor's own current electricity demand, and at about 51% of peninsular Malaysia's total data-centre maximum demand, in a report published on 18 June, before this window opened⁠2. Those two figures are the consultancy's estimates and not the Commission's measurements, and they cannot be quoted under the regulator's name.

The Commission's own projections run further out, with data centres taking 31% of peninsular demand by 2035 and Malaysia needing about 9 GW of new gas-fired capacity by 2032⁠3. Operators in Johor have chosen to argue their resource case on water: ZDATA said in July that its facility there runs solely on treated wastewater. The electricity number is the one the regulator has now written into the national accounts, where it can be tracked week by week whether the industry engages with it or not.

Deep Analysis

In plain English

Data centres use roughly the same amount of electricity all the time, but hotter weather makes the whole country use more power for air conditioning, and also makes the data centres themselves work harder to keep their own equipment cool. That is why their share of the national total jumped in the second week of August, when it was especially hot.

Deep Analysis
Root Causes

Data centres run a near-constant electrical load year round, while air-conditioning-driven household and commercial demand swings sharply with temperature.

When a heatwave lifts overall grid demand, data-centre consumption stays flat in absolute terms, so its share of the total falls when other demand spikes, and rises when cooling load pushes the whole system's demand curve up in a way that also makes the data centres themselves draw more power for their own cooling. Malaysia's 9.3% weekly peak reflects both effects moving together.

First Reported In

Update #14 · Brazil bill ties tax break to a water cap

Bernama via Yahoo Finance Canada· 8 Sept 2026
Read original →
Causes and effects
This Event
9.3% of Malaysia's power, in one week
A national regulator now reports data-centre consumption as a share of the country's power, and that share climbs when the weather turns hot.
Different Perspectives
Chilean data-centre developers
Chilean data-centre developers
Seven projects, one linked to Google, asked SEA this month for rulings that they fall outside full environmental review; four declared diesel-storage volumes just under the review-triggering tonnage, mirroring the mechanism Alto Jahuel used in July. The clustering suggests the threshold is being engineered, not sized to need.
An Coimisiun Pleanala
An Coimisiun Pleanala
Ireland's planning appeals body refused the €1.5bn Killala data centre on 17 September, overturning Mayo County Council's 2025 grant for lack of a fixed grid-connection agreement and no corporate renewable power-purchase agreement. The ruling makes matched-power evidence, not planning consent alone, the deciding factor.
Housing Assembly and Foxglove
Housing Assembly and Foxglove
The two groups' 6 August appeal, filed through the Legal Resources Centre, kept Cape Town's approval of Equinix's data centre suspended through this window over missing water, emissions, noise and diesel-generator data. Deputy Mayor Eddie Andrews confirmed on 20-21 September that the suspension holds.
Brazil (President Lula, signing Redata)
Brazil (President Lula, signing Redata)
Lula signed Lei 15.504 on 15 September, creating the Redata tax programme and keeping the Senate's water cap with no veto, while Aneel authorised Scala's AI City to join the national grid from January 2028. Brazil is recruiting capacity other markets are now turning away.
Aragon regional government (Eva Valle)
Aragon regional government (Eva Valle)
Aragon's economy chief Eva Valle said on 11 September that Spain's draft decree, requiring 80% hourly-matched renewables via a 10-year power-purchase agreement, is unmeetable by any project and threatens Blackstone, Azora and Microsoft builds already under way. Aragon holds 3,600 MW of granted grid access against 108 MW built.
Texas Governor Greg Abbott
Texas Governor Greg Abbott
Abbott ordered TCEQ on 21 September to halt every pending data-centre permit until projects pay their own way and complete ERCOT and Texas Water Development Board audits. Texas built the country's most permissive data-centre market; freezing it signals even that market has hit its grid limit.