Korea raises Seoul data-centre grid bar

2 min read
18:00UTC

South Korea's climate ministry raised the grid pass mark for Seoul-area data centres to 75 points from 70, and applied it to projects still waiting for a result.

IndustryAssessed
Key takeaway

Seoul-area data centres now need 75 grid-assessment points, and pending projects get no grandfathering.

South Korea's Ministry of Climate, Energy and Environment brought its power-grid impact assessment rules into force on Monday 16 November⁠1. The assessment is a scored test that a large new power user must pass before it connects, set by ministerial notice under the Distributed Energy Activation Special Act. A data centre in the Seoul capital region now needs 75 points, up from 70, and a new scoring item widens the advantage for sites outside the region.

Projects that filed before 16 November but have no result yet are judged on the new standard. The ministry also bars developers from selling result notices. Each notice lasts a year, with one extension of up to a year. A developer who planned to win a Seoul-area pass and sell the site on now has neither the old pass mark nor a tradeable approval.

The pilot assessed 28 projects in the capital region, worth 1.9 GW, and 64 outside it, worth 7 GW. Industry groups told Etnews on 13 November that tougher scoring for one sector alone is unfair⁠2. A separate grid code, which would require AI data centres to stay connected through grid faults, has not yet been issued.

Deep Analysis

In plain English

In South Korea, anyone who wants to plug a very large user, such as a data centre, into the power grid must first pass a scored government test. The test checks whether the local grid can cope. From 16 November the pass mark for data centres in and around Seoul rose from 70 points to 75, and a new scoring item favours sites elsewhere in the country. Projects still waiting for a result are judged on the new rules. A pass can no longer be sold to another company, and it expires after a year unless it is extended once.

Deep Analysis
Root Causes

Korea's Distributed Energy Activation Special Act, in force since June 2024, created the grid impact assessment so that large new users must show where their power will come from before they connect. The 16 November rules are the first full use of that power.

Transmission lags generation. The high-voltage direct-current link meant to carry east-coast nuclear power to the capital region has run years behind schedule amid local opposition, so new load near Seoul competes for a fixed amount of incoming capacity.

Without a transfer ban, a pass could become a tradeable asset. Making result notices non-transferable, and valid for one year with one extension, removes the incentive to win a pass and sell the site rather than build.

What could happen next?
  • Consequence

    Developers holding pending Seoul-area applications must redesign or relocate to clear the higher bar.

  • Risk

    Provincial sites that pass the test may still wait years for fibre and staff, leaving approved capacity unbuilt.

First Reported In

Update #19 · US grids set a price to cut off data centres

Ministry of Climate, Energy and Environment (South Korea)· 26 Nov 2026
Read original →
Different Perspectives
MUFG
MUFG
Mitsubishi UFJ (MUFG) and Morgan Stanley are preparing to sell a loan of about $4.5bn secured on the GPUs CoreWeave runs for Meta in Dalton, Georgia, with price talk of 7% to 7.5%, Bloomberg reported. Meta's contract is expected to win the loan investment-grade ratings, though CoreWeave is rated below investment grade and the loan has not priced.
CX Tech
CX Tech
CX Tech's £16.5bn, 1,000 MW plan for the former Chapelcross nuclear site has drawn more than 10,000 representations, the most Dumfries and Galloway's planners have received, BBC News reported. The company says the scheme could support up to 750 construction jobs and about 540 permanent posts; comments close on 29 November.
Nate Glubish, Alberta's technology and innovation minister
Nate Glubish, Alberta's technology and innovation minister
Glubish tabled Bill 42 on 18 November to ban power plants and data centres on Class 1 and 2 farmland and within 600 m of homes, a day after the regulator approved a 1,494 MW plant that fails both tests. The bill exempts projects already approved or under review, so the Indus plant stands.
NEXTDC's chairman and chief executive
NEXTDC's chairman and chief executive
After a second pay strike and a defeated spill on 20 November, NEXTDC's leaders said they are exploring a joint venture for the S4 Sydney campus and do not expect to raise shareholder capital for contracted capacity. They raised FY27 underlying EBITDA guidance to A$260m-A$275m, still excluding about A$140m tied to Melbourne's stalled M3 site.
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
The three groups argued in the High Court on 18 November that the CRU's data-centre connection framework breaches the 2015 Climate Act by ignoring carbon budgets, which the CRU denies. Judge Micheal O'Connell reserved judgment with no date, so the framework stands meanwhile.
South Korean data-centre industry groups
South Korean data-centre industry groups
Industry groups told Etnews on 13 November that tougher grid scoring for one sector alone is unfair, three days before the climate and energy ministry raised the capital-region pass mark to 75 from 70. Pending applications are judged on the new bar; the pilot assessed 28 capital-region projects worth 1.9 GW.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.