Distributed Energy Activation Special Act
AI-generated illustration
LegislationKR

Distributed Energy Activation Special Act

Korean law, in force since June 2024, that created the grid impact assessment.

As of November 2026, the grid impact assessment created by South Korea's Distributed Energy Activation Special Act is harder to pass near Seoul: from 16 November data centres there need 75 points, up from 70.

Last refreshed: 26 November 2026

Key Question

Why is it harder to build a data centre near Seoul?

Timeline for Distributed Energy Activation Special Act

#19 16 Nov

Korea raises Seoul data-centre grid bar

Data Centres: Boom and Backlash
View full timeline →

Background

South Korea's Distributed Energy Activation Special Act aims to spread electricity supply and demand across the country instead of piling both onto the grid around Seoul.

The Act created the grid impact assessment as its main instrument. A business planning a large new load in a designated area must pass it before it can connect, and the bar for data centres in the capital region rose on 16 November 2026.

The Act matters to anyone siting a data centre in Korea, because the score decides whether a project can connect near Seoul or must look elsewhere. The same ministry has also planned a grid code for AI data centres, so the assessment is one of several levers pushing heavy users towards the regions that generate the power.

Key Issues
Grid assessment

Its grid test grows stricter near Seoul

The assessment is the Act's main tool for steering where large new loads plug in. On 16 November 2026 the climate ministry raised the pass mark for data centres in the capital region to 75 points from 70, and applied it to projects still waiting for a result. Approval notices can no longer be traded.

The aim is to pull big users towards the coastal plants that make Korea's power and away from crowded lines into the capital. Industry groups told Etnews on 13 November 2026 that a harsher standard for one sector alone is unfair. A grid code requiring AI data centres to ride through faults, flagged by the ministry in October 2026, had not been issued by mid-November.

Common Questions
What is Korea's Distributed Energy Activation Special Act?
A South Korean law, in force since June 2024, that requires large new power users in designated zones to pass a grid impact assessment before they connect, steering them away from the Seoul capital region.Source: https://www.law.go.kr/LSW/lsInfoP.do?lsiSeq=284359
What score does a Seoul data centre need to pass Korea's grid assessment?
75 points, up from 70, under rules in force since 16 November 2026. Pending applications are judged on the new standard.Source: Ministry of Climate, Energy and Environment
When did Korea's Distributed Energy Act take effect?
In June 2024. It was promulgated on 13 June 2023 and took effect one year later.Source: https://www.law.go.kr/LSW/lsInfoP.do?lsiSeq=284359
Which projects need a grid impact assessment in South Korea?
Businesses planning new loads of 10 MW or more in zones the climate minister designates, which include data centres in the Seoul capital region.Source: https://www.law.go.kr/LSW/lsInfoP.do?lsiSeq=284359
Source Material

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Updated 26 November 2026. Editorial standards.