Data Centres: Boom and Backlash
26NOV

Jemena halts power line to NEXTDC's M3

4 min read
18:00UTC

Jemena stopped work on the line to NEXTDC's West Footscray campus after local opposition, and NEXTDC cut its FY27 EBITDA guidance to A$245m-A$265m.

IndustryAssessed
Key takeaway

One delayed local power line cut NEXTDC's earnings guidance by more than a third.

Jemena, the electricity distributor for western Melbourne, has halted work on the power line to NEXTDC's M3 data centre at West Footscray. NEXTDC told the ASX on 21 October that Jemena cited "safety concerns and lack of access to work sites arising from community and stakeholder opposition to the works"⁠1. Jemena does not expect to restart before February 2027, and the council, as road authority, has not given consent while further consultation takes place.

NEXTDC, one of Australia's largest data-centre operators, now expects the first increase in grid supply to M3 in its 2028 financial year. Later increases depend on transformer projects at the Brooklyn Terminal Station, which are also delayed.

The company cut underlying EBITDA (earnings before interest, tax, depreciation and amortisation) guidance for its 2027 financial year to A$245m-A$265m from A$385m-A$410m, and net revenue to A$475m-A$500m from A$615m-A$640m. The new guidance excludes about A$140m each of revenue and EBITDA from the affected M3 contracts. Capital spending guidance drops to A$4.5bn-A$5.0bn from A$5.25bn-A$5.75bn, and every new development and land purchase is on hold "for the foreseeable future". The shares fell about 40% when trading resumed, ABC reported, after a halt NEXTDC requested on 19 October⁠2.

The M3 contracts carry service-level credits, refunds owed to customers for late or unpowered capacity, and may give customers the right to terminate. NEXTDC is assessing whether force majeure, a clause excusing delays outside its control, applies⁠3. In August the company presented a 565.1 megawatt (MW) binding order book, of which 197 MW was due to start billing in the year to June 2027; some contracts inside that figure may now carry termination rights. The board will report on capital spending and a possible sale of development sites by its annual meeting on 20 November.

Victoria's planning decision on M3 stages 6 and 7 is not now expected until 2027, because caretaker conventions, which bar major decisions in the run-up to a vote, apply before the 28 November state election. The state already requires new data centres to bring their own renewable power.

Deep Analysis

In plain English

NEXTDC is an Australian company that runs data centres: large buildings full of computers that store and process data for other businesses. A data centre is useless without a big supply of electricity. In Melbourne, the company Jemena owns the local power lines. It was building a new line to NEXTDC's M3 site in West Footscray, but stopped because of local opposition to the works. It says it will not start again before February 2027. NEXTDC had promised space at M3 to paying customers. Without the extra power, it cannot deliver that space on time. So it has lowered its forecast of how much money it will make, and may owe customers refunds.

Deep Analysis
Root Causes

Power to an operating campus depends on three parties NEXTDC does not own: Jemena, which builds the distribution line; the council, which as road authority must consent to the works; and the transmission-side substation at Brooklyn. Contracts with customers were signed against a supply timetable that needed all three to hold.

Victoria's electoral calendar adds a second constraint. Caretaker conventions before the 28 November state election push the planning decision on M3 stages 6 and 7 into 2027, so the wire delay and the consent delay now run side by side rather than one after the other.

What could happen next?
  • Risk

    Customers with M3 contracts may claim service-level credits or seek to terminate if force majeure does not apply.

    Short term · Assessed
  • Consequence

    NEXTDC may sell development sites; the board reports on this by its 20 November annual meeting.

    Short term · Suggested
  • Precedent

    Opposition to the distribution line, rather than to the data centre itself, has stopped supply to an operating campus.

    Medium term · Assessed
First Reported In

Update #17 · Stalled power line cuts A$140m from NEXTDC guidance

NEXTDC (ASX release via TradingView)· 22 Oct 2026
Read original →
Different Perspectives
MUFG
MUFG
Mitsubishi UFJ (MUFG) and Morgan Stanley are preparing to sell a loan of about $4.5bn secured on the GPUs CoreWeave runs for Meta in Dalton, Georgia, with price talk of 7% to 7.5%, Bloomberg reported. Meta's contract is expected to win the loan investment-grade ratings, though CoreWeave is rated below investment grade and the loan has not priced.
CX Tech
CX Tech
CX Tech's £16.5bn, 1,000 MW plan for the former Chapelcross nuclear site has drawn more than 10,000 representations, the most Dumfries and Galloway's planners have received, BBC News reported. The company says the scheme could support up to 750 construction jobs and about 540 permanent posts; comments close on 29 November.
Nate Glubish, Alberta's technology and innovation minister
Nate Glubish, Alberta's technology and innovation minister
Glubish tabled Bill 42 on 18 November to ban power plants and data centres on Class 1 and 2 farmland and within 600 m of homes, a day after the regulator approved a 1,494 MW plant that fails both tests. The bill exempts projects already approved or under review, so the Indus plant stands.
NEXTDC's chairman and chief executive
NEXTDC's chairman and chief executive
After a second pay strike and a defeated spill on 20 November, NEXTDC's leaders said they are exploring a joint venture for the S4 Sydney campus and do not expect to raise shareholder capital for contracted capacity. They raised FY27 underlying EBITDA guidance to A$260m-A$275m, still excluding about A$140m tied to Melbourne's stalled M3 site.
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
Friends of the Irish Environment, Friends of the Earth Ireland and ClientEarth
The three groups argued in the High Court on 18 November that the CRU's data-centre connection framework breaches the 2015 Climate Act by ignoring carbon budgets, which the CRU denies. Judge Micheal O'Connell reserved judgment with no date, so the framework stands meanwhile.
South Korean data-centre industry groups
South Korean data-centre industry groups
Industry groups told Etnews on 13 November that tougher grid scoring for one sector alone is unfair, three days before the climate and energy ministry raised the capital-region pass mark to 75 from 70. Pending applications are judged on the new bar; the pilot assessed 28 capital-region projects worth 1.9 GW.

Written with AI from Lowdown's published reporting. Not individually reviewed by an editor. Editorial standards.