UNE forecasts a 2,240 MW shortfall

1 min read
10:44UTC

UNE told the public on 16 July to expect a 2,240 MW shortfall that day, with 990 MW of generation available against 3,200 MW of demand.

PoliticsDeveloping
Key takeaway

Cuba's grid operator forecast that more than two thirds of national demand would go unmet.

UNE (Unión Eléctrica Nacional), Cuba's state grid operator, published a Nota Informativa on Thursday 16 July recording an actual peak deficit of 2,126 MW the previous day, forecasting 2,240 MW for the 16th, and reporting 990 MW of available generation against 3,200 MW of maximum demand, with service disrupted across the full 24 hours "por falta de capacidad de generación" 1.

These are the grid operator's own numbers, not a diaspora estimate or an opposition tally, which is what makes them worth publishing. Cuban state institutions release little that outsiders can check against anything. UNE puts out a daily bulletin carrying a forecast, and a forecast can be marked against the following day's outturn. On this occasion the operator was telling Cubans before breakfast that more than two thirds of the island's demand would go unmet.

A forecast deficit set above the previous day's actual deficit, published two days after a total collapse, describes a system that has not recovered what it lost. The 990 MW of available generation is the figure to hold against the 3,200 MW peak, because the gap between them is not an emergency to be scheduled around. It is the ordinary operating condition of the grid, and the rotating blackout blocks are simply how the state decides who absorbs it. The bulletin's own phrase, "por falta de capacidad de generación", points past the wires and back at the fuel: no tanker has berthed anywhere on the island since CUPET's designation in June .

Deep Analysis

In plain English

UNE (Unión Eléctrica Nacional) is Cuba's state grid operator, and its Nota Informativa is the daily bulletin it publishes reporting how short the island's power supply fell the day before and how short it expects to fall the next day. The 16 July bulletin reported that 15 July's peak shortfall reached 2,126 MW, and forecast an even larger 2,240 MW shortfall for 16 July, with only 990 MW available against 3,200 MW of maximum demand. That means less than a third of the power the island needs at peak times was actually available, an unusually severe ratio even by the standards of Cuba's ongoing energy crisis.

What could happen next?
  • Meaning

    This bulletin is UNE's own primary confirmation that the deficit remains above 2,000 MW and is still climbing into mid to late July, rather than stabilising after the 10 and 14 July collapses.

First Reported In

Update #11 · Cuba blames the blockade for a 64% gas rise

Union Electrica Nacional (UNE)· 17 Jul 2026
Read original
Different Perspectives
Spain (Foreign Ministry and hotel investors)
Spain (Foreign Ministry and hotel investors)
Madrid has worked to shield Spanish hotel operators exposed to Cuba, and OFAC's General Licences 2 and 3 winding down the Guernsey-listed CEIBA Investments fund give those investors a defined exit rather than an abrupt block. Spain's stake in managing an orderly wind-down, not confronting the designation itself, keeps it distinct from Havana's collective-punishment framing.
Cuban Ministry of Foreign Affairs (MINREX)
Cuban Ministry of Foreign Affairs (MINREX)
Foreign Minister Bruno Rodriguez Parrilla called the 23 July designations "castigo colectivo" and defended the medical missions as protecting healthcare access for patients in the countries where Cuban doctors serve, without addressing the evasion allegation against Coral Maritima directly.
US Treasury (OFAC) and State Department
US Treasury (OFAC) and State Department
OFAC designated Cuba's medical-missions operators and named the Mariel-Coral Maritima transfer as GAESA sanctions evasion on 23 July, characterisations Washington has not independently substantiated in public documents reviewed. The administration frames the wave as closing hard-currency channels sector by sector, following the same pattern applied to tourism and financial clearing in June and July.
Human rights monitors (OCDH and Prisoners Defenders)
Human rights monitors (OCDH and Prisoners Defenders)
OCDH's 14 July dictamen named the specific offices responsible for holding Otero Alcántara past his sentence-expiry date; Prisoners Defenders counted 1,306 political prisoners, including 40 detained minors, on 9 July. Both oppose the Cuban government's account without endorsing Washington's sanctions instrument as a remedy.
US State Department
US State Department
Secretary Rubio said Cuba 'continues to ally itself with America's enemies' and framed the 13 July designations as deploying 'every tool at our disposal', now citing forced-labour export to Angola for the first time. These quotes rest on cached web snippets; state.gov was unreachable this run and could not be directly verified.
Cuban Ministry of Foreign Affairs
Cuban Ministry of Foreign Affairs
Foreign Minister Bruno Rodríguez Parrilla called the 13 July designation package 'criminal and genocidal' and said 'Cuba is not a threat and US intelligence agencies know it'. State media frame the 16 July gas-price rise as a direct consequence of the intensifying blockade, though Havana has not disclosed its own container-import shift dated 3 July.