Timeline

NESO

UK National Energy System Operator; managing a 50 GW data-centre grid queue that exceeds national peak demand — the bottleneck that drove OpenAI to pause its UK Stargate site.

8 of 8 entries (8 events, 0 interactions)

Filters
#710 Jun
#630 May

Mentioned in: SoftBank bets EUR 75bn on France

Data Centres: Boom and Backlash
#313 May

Issued the first transmission connection offers under Gate 2 Phase 1 beginning mid-May 2026

Data Centres: Boom and Backlash: UK Gate 2 grid offers begin issuing
#26 May
#227 Apr
#123 Apr

OpenAI pauses Cobalt Park Stargate site

Data Centres: Boom and Backlash
#59 Apr

Mentioned in: Texas grid queue hits 410 GW

Data Centres: Boom and Backlash
#127 Feb

Disclosed grid-connection register showing 50 GW of data centre demand

Data Centres: Boom and Backlash: UK queue: 50 GW DC vs 45 GW peak demand